XML 112 R20.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Commitments and Contingencies
12 Months Ended
Dec. 31, 2019
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies Commitments and Contingencies
 
Palo Verde Generating Station
 
Spent Nuclear Fuel and Waste Disposal
 
On December 19, 2012, APS, acting on behalf of itself and the participant owners of Palo Verde, filed a second breach of contract lawsuit against the DOE in the United States Court of Federal Claims ("Court of Federal Claims").  The lawsuit sought to recover damages incurred due to DOE’s breach of the Contract for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste ("Standard Contract") for failing to accept Palo Verde's spent nuclear fuel and high level waste from January 1, 2007 through June 30, 2011, as it was required to do pursuant to the terms of the Standard Contract and the Nuclear Waste Policy Act.  On August 18, 2014, APS and DOE entered into a settlement agreement, stipulating to a dismissal of the lawsuit and payment by DOE to the Palo Verde owners for certain specified costs incurred by Palo Verde during the period January 1, 2007 through June 30, 2011. In addition, the settlement agreement, as amended, provides APS with a method for submitting claims and getting recovery for costs incurred through December 31, 2019.

APS has submitted five claims pursuant to the terms of the August 18, 2014 settlement agreement, for five separate time periods during July 1, 2011 through June 30, 2018. The DOE has approved and paid $84.3 million for these claims (APS’s share is $24.5 million). The amounts recovered were primarily recorded as adjustments to a regulatory liability and had no impact on reported net income. In accordance with the 2017 Rate Case Decision, this regulatory liability is being refunded to customers (see Note 4). On October 31, 2019, APS filed its next claim pursuant to the terms of the August 18, 2014 settlement agreement in the amount of $16 million (APS’s share is $4.7 million). On February 11, 2020, the DOE approved a payment of $15.4 million (APS’s share is $4.5 million).

Nuclear Insurance
 
Public liability for incidents at nuclear power plants is governed by the Price-Anderson Nuclear Industries Indemnity Act ("Price-Anderson Act"), which limits the liability of nuclear reactor owners to the amount of insurance available from both commercial sources and an industry-wide retrospective payment plan.  In accordance with the Price-Anderson Act, the Palo Verde participants are insured against public liability for a nuclear incident of up to approximately $13.9 billion per occurrence. Palo Verde maintains the maximum available nuclear liability insurance in the amount of $450 million, which is provided by American Nuclear Insurers ("ANI").  The remaining balance of approximately $13.5 billion of liability coverage is provided through a mandatory industry-wide retrospective premium program.  If losses at any nuclear power plant covered by the program exceed the accumulated funds, APS could be responsible for retrospective premiums.  The maximum retrospective premium per reactor under the program for each nuclear liability incident is approximately $137.6 million, subject to a maximum annual premium of approximately $20.5 million per incident.  Based on APS’s ownership interest in the three Palo Verde units, APS’s maximum retrospective premium per incident for all three units is approximately $120.1 million, with a maximum annual retrospective premium of approximately $17.9 million.

The Palo Verde participants maintain insurance for property damage to, and decontamination of, property at Palo Verde in the aggregate amount of $2.8 billion.  APS has also secured accidental outage insurance for a sudden and unforeseen accidental outage of any of the three units. The property damage, decontamination, and accidental outage insurance are provided by Nuclear Electric Insurance Limited ("NEIL").  APS is subject to retrospective premium adjustments under all NEIL policies if NEIL’s losses in any policy year exceed accumulated funds. The maximum amount APS could incur under the current NEIL
policies totals approximately $25.5 million for each retrospective premium assessment declared by NEIL’s Board of Directors due to losses.  In addition, NEIL policies contain rating triggers that would result in APS providing approximately $73.4 million of collateral assurance within 20 business days of a rating downgrade to non-investment grade.  The insurance coverage discussed in this and the previous paragraph is subject to certain policy conditions, sublimits and exclusions.
 
Fuel and Purchased Power Commitments and Purchase Obligations
 
APS is party to various fuel and purchased power contracts and purchase obligations with terms expiring between 2020 and 2043 that include required purchase provisions.  APS estimates the contract requirements to be approximately $590 million in 2020; $613 million in 2021; $624 million in 2022; $616 million in 2023; $581 million in 2024; and $5.5 billion thereafter.  However, these amounts may vary significantly pursuant to certain provisions in such contracts that permit us to decrease required purchases under certain circumstances. These amounts include estimated commitments relating to purchased power lease contracts (see Note 9).
 
Of the various fuel and purchased power contracts mentioned above, some of those contracts for coal supply include take-or-pay provisions.  The current coal contracts with take-or-pay provisions have terms expiring through 2031.
 
The following table summarizes our estimated coal take-or-pay commitments (dollars in thousands):
 
 
 Years Ended December 31,
 
2020
 
2021
 
2022
 
2023
 
2024
 
Thereafter
Coal take-or-pay commitments (a)
$
185,347

 
$
186,554

 
$
187,400

 
$
189,120

 
$
193,192

 
$
1,240,964

 
(a)
Total take-or-pay commitments are approximately $2.2 billion.  The total net present value of these commitments is approximately $1.6 billion.
 
APS may spend more to meet its actual fuel requirements than the minimum purchase obligations in our coal take-or-pay contracts. The following table summarizes actual amounts purchased under the coal contracts which include take-or-pay provisions for each of the last three years (dollars in thousands):
 
 
Year Ended December 31,
 
2019
 
2018
 
2017
Total purchases
$
204,888

 
$
206,093

 
$
165,220


 
Renewable Energy Credits
 
APS has entered into contracts to purchase renewable energy credits to comply with the RES.  APS estimates the contract requirements to be approximately $36 million in 2020; $35 million in 2021; $31 million in 2022; $30 million in 2023; $28 million in 2024; and $133 million thereafter.  These amounts do not include purchases of renewable energy credits that are bundled with energy.
 
Coal Mine Reclamation Obligations
 
APS must reimburse certain coal providers for amounts incurred for final and contemporaneous coal mine reclamation.  We account for contemporaneous reclamation costs as part of the cost of the delivered coal.  We utilize site-specific studies of costs expected to be incurred in the future to estimate our final reclamation obligation.  These studies utilize various assumptions to estimate the future costs.  Based on the most recent reclamation studies, APS recorded an obligation for the coal mine final reclamation of approximately $166 million at December 31, 2019 and $213 million at December 31, 2018. Under our current coal supply agreements, APS expects to make payments for the final mine reclamation as follows:  $17 million in 2020; $16 million in 2021; $17 million in 2022; $18 million in 2023; $19 million in 2024; and $88 million thereafter.  Any amendments to current coal supply agreements may change the timing of the contribution. Portions of these funds will be held in an escrow account and distributed to certain coal providers under the terms of the applicable coal supply agreements.

Superfund-Related Matters
 
The Comprehensive Environmental Response Compensation and Liability Act ("CERCLA" or "Superfund") establishes liability for the cleanup of hazardous substances found contaminating the soil, water or air.  Those who released, generated, transported to, or disposed of hazardous substances at a contaminated site are among the parties who are potentially responsible ("PRPs").  PRPs may be strictly, and often are jointly and severally, liable for clean-up. On September 3, 2003, EPA advised APS that EPA considers APS to be a PRP in the Motorola 52nd Street Superfund Site, Operable Unit 3 ("OU3") in Phoenix, Arizona.  APS has facilities that are within this Superfund site.  APS and Pinnacle West have agreed with EPA to perform certain investigative activities of the APS facilities within OU3.  In addition, on September 23, 2009, APS agreed with EPA and one other PRP to voluntarily assist with the funding and management of the site-wide groundwater remedial investigation and feasibility study ("RI/FS").  Based upon discussions between the OU3 working group parties and EPA, along with the results of recent technical analyses prepared by the OU3 working group to supplement the RI/FS for OU3, APS anticipates finalizing the RI/FS in the spring or summer of 2020. We estimate that our costs related to this investigation and study will be approximately $2 million.  We anticipate incurring additional expenditures in the future, but because the overall investigation is not complete and ultimate remediation requirements are not yet finalized, at the present time expenditures related to this matter cannot be reasonably estimated.
 
On August 6, 2013, Roosevelt Irrigation District ("RID") filed a lawsuit in Arizona District Court against APS and 24 other defendants, alleging that RID’s groundwater wells were contaminated by the release of hazardous substances from facilities owned or operated by the defendants.  The lawsuit also alleges that, under Superfund laws, the defendants are jointly and severally liable to RID.  The allegations against APS arise out of APS’s current and former ownership of facilities in and around OU3.  As part of a state governmental investigation into groundwater contamination in this area, on January 25, 2015, ADEQ sent a letter to APS seeking information concerning the degree to which, if any, APS’s current and former ownership of these facilities may have contributed to groundwater contamination in this area.  APS responded to ADEQ on May 4, 2015. On December 16, 2016, two RID environmental and engineering contractors filed an ancillary lawsuit for recovery of costs against APS and the other defendants in the RID litigation. That same day, another RID service provider filed an additional ancillary CERCLA lawsuit against certain of the defendants in the main RID litigation, but excluded APS and certain other parties as named defendants. Because the ancillary lawsuits concern past costs allegedly incurred by these RID vendors, which were ruled unrecoverable directly by RID in November of 2016, the additional lawsuits do not increase APS's exposure or risk related to these matters.

On April 5, 2018, RID and the defendants in that particular litigation executed a settlement agreement, fully resolving RID's CERCLA claims concerning both past and future cost recovery. APS's share of this settlement was immaterial. In addition, the two environmental and engineering vendors voluntarily dismissed their lawsuit against APS and the other named defendants without prejudice. An order to this effect was entered on April 17, 2018. With this disposition of the case, the vendors may file their lawsuit again in the future. On August 16, 2019, Maricopa County, one of the three direct defendants in the service provider lawsuit, filed a third-party complaint seeking contribution for its liability, if any, from APS and 28 other third-party defendants. We are unable to predict the outcome of these matters; however, we do not expect the outcome to have a material impact on our financial position, results of operations or cash flows.
 
Environmental Matters
 
APS is subject to numerous environmental laws and regulations affecting many aspects of its present and future operations, including air emissions of both conventional pollutants and greenhouse gases, water quality, wastewater discharges, solid waste, hazardous waste, and CCRs.  These laws and regulations can change from time to time, imposing new obligations on APS resulting in increased capital, operating, and other costs.  Associated capital expenditures or operating costs could be material.  APS intends to seek recovery of any such environmental compliance costs through our rates, but cannot predict whether it will obtain such recovery.  The following proposed and final rules involve material compliance costs to APS.
 
Regional Haze Rules.  APS has received the final rulemaking imposing new pollution control requirements on Four Corners. EPA required the plant to install pollution control equipment that constitutes BART to lessen the impacts of emissions on visibility surrounding the plant. In addition, EPA issued a final rule for Regional Haze compliance at Cholla that does not involve the installation of new pollution controls and that will replace an earlier BART determination for this facility. See below for details of the Cholla BART approval.

Four Corners. Based on EPA’s final standards, APS's 63% share of the cost of required controls for Four Corners Units 4 and 5 was approximately $400 million, which has been incurred.  In addition, APS and El Paso entered into an asset purchase agreement providing for the purchase by APS, or an affiliate of APS, of El Paso's 7% interest in Four Corners Units 4 and 5. 4CA purchased the El Paso interest on July 6, 2016. NTEC purchased the interest from 4CA on July 3, 2018. See "Four Corners - 4CA Matter" below for a discussion of the NTEC purchase. The cost of the pollution controls related to the 7% interest is approximately $45 million, which was assumed by NTEC through its purchase of the 7% interest.

Cholla. APS believed that EPA’s original 2012 final rule establishing controls constituting BART for Cholla, which would require installation of SCR controls, was unsupported and that EPA had no basis for disapproving Arizona’s State Implementation Plan ("SIP") and promulgating a FIP that was inconsistent with the state’s considered BART determinations under the regional haze program.  In September 2014, APS met with EPA to propose a compromise BART strategy, whereby APS would permanently close Cholla Unit 2 and cease burning coal at Units 1 and 3 by the mid-2020s. (See "Cholla" in Note 4 for information regarding future plans for Cholla and details related to the resulting regulatory asset.) APS made the proposal with the understanding that additional emission control equipment is unlikely to be required in the future because retiring and/or converting the units as contemplated in the proposal is more cost effective than, and will result in increased visibility improvement over, the BART requirements for oxides of nitrogen ("NOx") imposed through EPA's BART FIP. In early 2017, EPA approved a final rule incorporating APS's compromise proposal, which took effect for Cholla on April 26, 2017.
 
Coal Combustion Waste. On December 19, 2014, EPA issued its final regulations governing the handling and disposal of CCR, such as fly ash and bottom ash. The rule regulates CCR as a non-hazardous waste under Subtitle D of the Resource Conservation and Recovery Act ("RCRA") and establishes national minimum criteria for existing and new CCR landfills and surface impoundments and all lateral expansions. These criteria include standards governing location restrictions, design and operating criteria, groundwater monitoring and corrective action, closure requirements and post closure care, and recordkeeping, notification, and internet posting requirements. The rule generally requires any existing unlined CCR surface impoundment that is contaminating groundwater above a regulated constituent’s groundwater protection standard to stop receiving CCR and either retrofit or close, and further requires the closure of any CCR landfill or surface impoundment that cannot meet the applicable performance criteria for location restrictions or structural integrity. Such closure requirements are deemed "forced closure" or "closure for cause" of unlined surface impoundments, and are the subject of recent regulatory and judicial activities described below.

Since these regulations were finalized, EPA has taken steps to substantially modify the federal rules governing CCR disposal. While certain changes have been prompted by utility industry petitions, others have resulted from judicial review, court-approved settlements with environmental groups, and statutory changes to RCRA. The following lists the pending regulatory changes that, if finalized, could have a material impact as to how APS manages CCR at its coal-fired power plants:

Following the passage of the Water Infrastructure Improvements for the Nation Act in 2016, EPA possesses authority to, either, authorize states to develop their own permit programs for CCR management or issue federal permits governing CCR disposal both in states without their own permit programs and on tribal lands. Although ADEQ has taken steps to develop a CCR permitting program, it is not clear when that program will be put into effect. On December 19, 2019, EPA proposed its own set of regulations governing the issuance of CCR management permits.

On March 1, 2018, as a result of a settlement with certain environmental groups, EPA proposed adding boron to the list of constituents that trigger corrective action requirements to remediate groundwater impacted by CCR disposal activities. Apart from a subsequent proposal issued on August 14, 2019 to add a specific, health-based groundwater protection standard for boron, EPA has yet to take action on this proposal.

Based on an August 21, 2018 D.C. Circuit decision, which vacated and remanded those provisions of the EPA CCR regulations that allow for the operation of unlined CCR surface impoundments, EPA recently proposed corresponding changes to federal CCR regulations. On November 4, 2019, EPA proposed that all unlined CCR surface impoundments, regardless of their impact (or lack thereof) upon surrounding groundwater, must cease operation and initiate closure by August 31, 2020 (with an optional three-month extension as needed for the completion of alternative disposal capacity).

On November 4, 2019, EPA also proposed to change the manner by which facilities that have committed to cease burning coal in the near-term may qualify for alternative closure. Such qualification would allow CCR disposal units at these plants to continue operating, even though they would otherwise be subject to forced closure under the federal CCR regulations. EPA’s proposal regarding alternative closure would require express EPA authorization for such facilities to continue operating their CCR disposal units under alternative closure.

We cannot at this time predict the outcome of these regulatory proceedings or when the EPA will take final action. Depending on the eventual outcome, the costs associated with APS’s management of CCR could materially increase, which could affect APS’s financial position, results of operations, or cash flows.

APS currently disposes of CCR in ash ponds and dry storage areas at Cholla and Four Corners. APS estimates that its share of incremental costs to comply with the CCR rule for Four Corners is approximately $22 million and its share of incremental costs to comply with the CCR rule for Cholla is approximately $15 million. The Navajo Plant currently disposes of CCR in a dry landfill storage area. To comply with the CCR rule for the Navajo Plant, APS's share of incremental costs is approximately $1 million, which has been incurred. Additionally, the CCR rule requires ongoing, phased groundwater monitoring.

As of October 2018, APS has completed the statistical analyses for its CCR disposal units that triggered assessment monitoring. APS determined that several of its CCR disposal units at Cholla and Four Corners will need to undergo corrective action. In addition, under the current regulations, all such disposal units must cease operating and initiate closure by October 31, 2020. APS initiated an assessment of corrective measures on January 14, 2019 and expects such assessment will continue through mid- to late-2020. As part of this assessment, APS continues to gather additional groundwater data and perform remedial evaluations as to the CCR disposal units at Cholla and Four Corners undergoing corrective action. In addition, APS will solicit input from the public, host public hearings, and select remedies as part of this process. Based on the work performed to date, APS currently estimates that its share of corrective action and monitoring costs at Four Corners will likely range from $10 million to $15 million, which would be incurred over 30 years. The analysis needed to perform a similar cost estimate for Cholla remains ongoing at this time. As APS continues to implement the CCR rule’s corrective action assessment process, the current cost estimates may change. Given uncertainties that may exist until we have fully completed the corrective action assessment process, we cannot predict any ultimate impacts to the Company; however, at this time we do not believe the cost estimates for Cholla and any potential change to the cost estimate for Four Corners would have a material impact on our financial position, results of operations or cash flows.

Clean Power Plan/Affordable Clean Energy Regulations. On June 19, 2019, EPA took final action on its proposals to repeal EPA's 2015 Clean Power Plan (“CPP”) and replace those regulations with a new rule, the Affordable Clean Energy (“ACE”) regulations. EPA originally finalized the CPP on August 3, 2015, and those regulations had been stayed pending judicial review.

The ACE regulations are based upon measures that can be implemented to improve the heat rate of steam-electric power plants, specifically coal-fired EGUs. In contrast with the CPP, EPA's ACE regulations would not involve utility-level generation dispatch shifting away from coal-fired generation and toward renewable energy resources and natural gas-fired combined cycle power plants. EPA’s ACE regulations provide states and EPA regions such as the Navajo Nation with three years to develop plans establishing source-specific standards of performance based upon application of the ACE rule’s heat-rate improvement emission guidelines. While corresponding New Source Review (“NSR”) reform regulations were proposed as part of EPA’s initial ACE proposal, the finalized ACE regulations did not include such reform measures. EPA announced that it will be taking final action on EPA's NSR reform proposal for EGUs in the near future.

We cannot at this time predict the outcome of EPA's regulatory actions repealing and replacing the CPP. Various state governments, industry organizations, and environmental and public-health public interest groups have filed lawsuits in the D.C. Circuit challenging the legality of EPA’s action, both in repealing the CPP and issuing the ACE regulations. In addition, to the extent that the ACE regulations go into effect as finalized, it is not yet clear how the state of Arizona or EPA will implement these regulations as applied to APS’s coal-fired EGUs. In light of these uncertainties, APS is still evaluating the impact of the ACE regulations on its coal-fired generation fleet.

Other environmental rules that could involve material compliance costs include those related to effluent limitations, the ozone national ambient air quality standard and other rules or matters involving the Clean Air Act, Clean Water Act, Endangered Species Act, RCRA, Superfund, the Navajo Nation, and water supplies for our power plants.  The financial impact of complying with current and future environmental rules could jeopardize the economic viability of our coal plants or the willingness or ability of power plant participants to fund any required equipment upgrades or continue their participation in these plants.  The economics of continuing to own certain resources, particularly our coal plants, may deteriorate, warranting early retirement of those plants, which may result in asset impairments.  APS would seek recovery in rates for the book value of any remaining investments in the plants as well as other costs related to early retirement, but cannot predict whether it would obtain such recovery.
 
Federal Agency Environmental Lawsuit Related to Four Corners

On April 20, 2016, several environmental groups filed a lawsuit against the Office of Surface Mining Reclamation and Enforcement ("OSM") and other federal agencies in the District of Arizona in connection with their issuance of the approvals that extended the life of Four Corners and the adjacent mine.  The lawsuit alleges that these federal agencies violated both the Endangered Species Act ("ESA") and the National Environmental Policy Act ("NEPA") in providing the federal approvals necessary to extend operations at the Four Corners Power Plant and the adjacent Navajo Mine past July 6, 2016.  APS filed a motion to intervene in the proceedings, which was granted on August 3, 2016.

On September 15, 2016, NTEC, the company that owns the adjacent mine, filed a motion to intervene for the purpose of dismissing the lawsuit based on NTEC's tribal sovereign immunity. On September 11, 2017, the Arizona District Court issued an order granting NTEC's motion, dismissing the litigation with prejudice, and terminating the proceedings. On November 9, 2017, the environmental group plaintiffs appealed the district court order dismissing their lawsuit. On July 29, 2019, the Ninth Circuit Court of Appeals affirmed the September 2017 dismissal of the lawsuit, after which the environmental group plaintiffs petitioned the Ninth Circuit for rehearing on September 12, 2019. The Ninth Circuit denied this petition for rehearing on December 11, 2019.

Four Corners National Pollutant Discharge Elimination System ("NPDES") Permit

On July 16, 2018, several environmental groups filed a petition for review before the EPA Environmental Appeals Board ("EAB") concerning the NPDES wastewater discharge permit for Four Corners, which was reissued on June 12, 2018.  The environmental groups allege that the permit was reissued in contravention of several requirements under the Clean Water Act and did not contain required provisions concerning EPA’s 2015 revised effluent limitation guidelines for steam-electric EGUs, 2014 existing-source regulations governing cooling-water intake structures, and effluent limits for surface seepage and subsurface discharges from coal-ash disposal facilities.  To address certain of these issues through a reconsidered permit, EPA took action on December 19, 2018 to withdraw the NPDES permit reissued in June 2018. Withdrawal of the permit moots the EAB appeal, and EPA filed a motion to dismiss on that basis. The EAB thereafter dismissed the environmental group appeal on February 12, 2019. EPA then issued a revised final NPDES permit for Four Corners on September 30, 2019. This permit is now subject to a petition for review before the EPA Environmental Appeals Board, based upon a November 1, 2019 filing by several environmental groups. We cannot predict the outcome of this review and whether the review will have a material impact on our financial position, results of operations or cash flows.

Four Corners

4CA Matter

On July 6, 2016, 4CA purchased El Paso’s 7% interest in Four Corners. NTEC had the option to purchase the 7% interest and ultimately purchased the interest on July 3, 2018. NTEC purchased the 7% interest at 4CA’s book value, approximately $70 million, and is paying 4CA the purchase price over a period of four years pursuant to a secured interest-bearing promissory note. In connection with the sale, Pinnacle West guaranteed certain obligations that NTEC will have to the other owners of Four Corners, such as NTEC's 7% share of capital expenditures and operating and maintenance expenses. Pinnacle West's guarantee is secured by a portion of APS's payments to be owed to NTEC under the 2016 Coal Supply Agreement.
The 2016 Coal Supply Agreement contained alternate pricing terms for the 7% interest in the event NTEC did not purchase the interest. Until the time that NTEC purchased the 7% interest, the alternate pricing provisions were applicable to 4CA as the holder of the 7% interest. These terms included a formula under which NTEC must make certain payments to 4CA for reimbursement of operations and maintenance costs and a specified rate of return, offset by revenue generated by 4CA’s power sales. The amount under this formula for calendar year 2018 (up to the date that NTEC purchased the 7% interest) is approximately $10 million, which was due to 4CA on December 31, 2019. Such payment was satisfied in January 2020 by NTEC directing to 4CA a prepayment from APS of future coal payment obligations.
Financial Assurances
 
In the normal course of business, we obtain standby letters of credit and surety bonds from financial institutions and other third parties. These instruments guarantee our own future performance and provide third parties with financial and performance assurance in the event we do not perform. As of December 31, 2019, standby letters of credit totaled $1.7 million and will expire in 2020. As of December 31, 2019, surety bonds expiring through 2020 totaled $14 million. The underlying liabilities insured by these instruments are reflected on our balance sheets, where applicable. Therefore, no additional liability is reflected for the letters of credit and surety bonds themselves.
 
We enter into agreements that include indemnification provisions relating to liabilities arising from or related to certain of our agreements.  Most significantly, APS has agreed to indemnify the equity participants and other parties in the Palo Verde sale leaseback transactions with respect to certain tax matters.  Generally, a maximum obligation is not explicitly stated in the indemnification provisions and, therefore, the overall maximum amount of the obligation under such indemnification provisions cannot be reasonably estimated.  Based on historical experience and evaluation of the specific indemnities, we do not believe that any material loss related to such indemnification provisions is likely.
 
Pinnacle West has issued parental guarantees and has provided indemnification under certain surety bonds for APS which were not material at December 31, 2019. In connection with the sale of 4CA's 7% interest to NTEC, Pinnacle West is guaranteeing certain obligations that NTEC will have to the other owners of Four Corners. (See "Four Corners - 4CA Matter" above for information related to this guarantee.) A maximum obligation is not explicitly stated in the guarantee and, therefore, the overall maximum amount of the obligation under such guarantee cannot be reasonably estimated; however, we consider the fair value of this guarantee to be immaterial.

In connection with BCE’s acquisition of minority ownership positions in the Clear Creek and Nobles 2 wind farms, Pinnacle West has issued parental guarantees to guarantee the obligations of BCE subsidiaries to make required equity contributions to fund project construction (the “Equity Contribution Guarantees”) and to
make production tax credit funding payments to borrowers of the projects (the “PTC Guarantees”).  The amounts guaranteed by Pinnacle West reduce as payments are made under the respective guaranteed agreements.  The Equity Contribution Guarantees are currently anticipated to be terminated upon completion of construction of the respective projects, which is anticipated to occur prior to December 31, 2020, and the PTC Guarantees (approximately $40 million as of December 31, 2019) are currently expected to be terminated ten years following the commercial operation date of the applicable project.