XML 28 R11.htm IDEA: XBRL DOCUMENT v3.5.0.2
Regulatory Matters
9 Months Ended
Sep. 30, 2016
Regulated Operations [Abstract]  
Regulatory Matters
Regulatory Matters
 
Retail Rate Case Filing with the Arizona Corporation Commission
 
On June 1, 2016, APS filed an application with the ACC for an annual increase in retail base rates of $165.9 million. This amount excludes amounts that are currently collected on customer bills through adjustor mechanisms. The application requests that some of the balances in these adjustor accounts (aggregating to approximately $267.6 million as of December 31, 2015) be transferred into base rates through the ratemaking process. This transfer would not have an incremental effect on average customer bills. The average annual customer bill impact of APS’s request is an increase of 5.74% (the average annual bill impact for a typical APS residential customer is 7.96%).

The principal provisions of the application are:

a test year ended December 31, 2015, adjusted as described below;
         
an original cost rate base of $6.8 billion, which approximates the ACC-jurisdictional portion of the book value of utility assets, net of accumulated depreciation and other credits, as of December 31, 2015;

the following proposed capital structure and costs of capital:
 
 
 
Capital Structure
 
Cost of Capital
 
Long-term debt
 
44.2
%
5.13
%
Common stock equity
 
55.8
%
10.50
%
Weighted-average cost of capital
 
 
 
8.13
%

 
a 1% return on the increment of fair value rate base above APS’s original cost rate base, as provided for by Arizona law;

a base rate for fuel and purchased power costs of $0.029882 per kilowatt-hour (“kWh”) based on estimated 2017 prices (a decrease from the current base fuel rate of $0.03207 per kWh);

authorization to defer for potential future recovery its share of the construction costs associated with installing selective catalytic reduction equipment at the Four Corners Power Plant (estimated at approximately $400 million in direct costs). APS proposes that the rates established in this rate case be increased through a step mechanism beginning in 2019 to reflect these deferred costs;

authorization to defer for potential future recovery in the Company’s next general rate case the construction costs APS incurs for its Ocotillo power plant modernization project, once the project reaches commercial operation. APS estimates the direct construction costs at approximately $500 million and that the new facility will be fully in service by early 2019;

authorization to defer until the Company’s next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes after the date the rate application is adjudicated;

updates and modifications to four of APS’s adjustor mechanisms - the Power Supply Adjustor (“PSA”), the Lost Fixed Cost Recovery Mechanism (“LFCR”), the Transmission Cost Adjustor (“TCA”) and the Environmental Improvement Surcharge (“EIS”);

a number of proposed rate design changes for residential customers, including:
change the on-peak time of use period from 12 p.m. - 7 p.m. to 3 p.m. - 8 p.m. Monday through Friday, excluding holidays;
reduce the difference in the on- and off-peak energy price and lower all energy charges;
offer four rate plan options, three of which have demand charges and a fourth that is available to non-partial requirements customers using less than 600 kWh on average per month; and
modify the current net metering tariff to provide for a credit at the retail rate for the portion of generation by rooftop solar customers that offsets their own load, and for a credit for excess energy delivered to the grid at an export rate.

proposed rate design changes for commercial customers, including an aggregation rider that allows certain large customers to qualify for a reduced rate, an extra-high load factor rate schedule for certain customers, and an economic development rate offering for new loads meeting certain criteria.

The Company requested that the increase become effective July 1, 2017.  On July 22, 2016, the administrative law judge set a procedural schedule for the rate proceedings. The ACC staff and interveners will begin filing their direct testimony on December 21, 2016, and the hearing will commence on March 22, 2017. The Commission staff supports completing the case within 12 months. APS cannot predict the outcome of its request.

Prior Rate Case Filing
 
On June 1, 2011, APS filed an application with the ACC for a net retail base rate increase of $95.5 million.  APS requested that the increase become effective July 1, 2012.  The request would have increased the average retail customer bill by approximately 6.6%.  On January 6, 2012, APS and other parties to the general retail rate case entered into an agreement (the "2012 Settlement Agreement") detailing the terms upon which the parties agreed to settle the rate case.  On May 15, 2012, the ACC approved the 2012 Settlement Agreement without material modifications.
 
Settlement Agreement
 
The 2012 Settlement Agreement provides for a zero net change in base rates, consisting of:  (1) a non-fuel base rate increase of $116.3 million; (2) a fuel-related base rate decrease of $153.1 million (to be implemented by a change in the base fuel rate for fuel and purchased power costs ("Base Fuel Rate") from $0.03757 to $0.03207 per kWh; and (3) the transfer of cost recovery for certain renewable energy projects from the Arizona Renewable Energy Standard and Tariff ("RES") surcharge to base rates in an estimated amount of $36.8 million.
  
Other key provisions of the 2012 Settlement Agreement include the following:
 
An authorized return on common equity of 10.0%;

A capital structure comprised of 46.1% debt and 53.9% common equity;

A test year ended December 31, 2010, adjusted to include plant that is in service as of March 31, 2012;
 
Deferral for future recovery or refund of property taxes above or below a specified 2010 test year level caused by changes to the Arizona property tax rate as follows:
 
Deferral of increases in property taxes of 25% in 2012, 50% in 2013 and 75% for 2014 and subsequent years if Arizona property tax rates increase; and

Deferral of 100% in all years if Arizona property tax rates decrease;
 
A procedure to allow APS to request rate adjustments prior to its next general rate case related to APS’s acquisition of additional interests in Units 4 and 5 and the related closure of Units 1-3 of the Four Corners Power Plant ("Four Corners") (APS made its filing under this provision on December 30, 2013, see "Four Corners" below);
 
Implementation of an LFCR rate mechanism to support energy efficiency and distributed renewable generation;
 
Modifications to the EIS to allow for the recovery of carrying costs for capital expenditures associated with government-mandated environmental controls, subject to an existing cents per kWh cap on cost recovery that could produce up to approximately $5 million in revenues annually;
 
Modifications to the Power Supply Adjustor ("PSA"), including the elimination of the 90/10 sharing provision;
 
A limitation on the use of the RES surcharge and the Demand Side Management Adjustor Charge ("DSMAC") to recoup capital expenditures not required under the terms of APS’s 2009 retail rate case settlement agreement (the "2009 Settlement Agreement");
  
Modification of the Transmission Cost Adjustor ("TCA") to streamline the process for future transmission-related rate changes; and
 
Implementation of various changes to rate schedules, including the adoption of an experimental "buy-through" rate that could allow certain large commercial and industrial customers to select alternative sources of generation to be supplied by APS.
 
The 2012 Settlement Agreement was approved by the ACC on May 15, 2012, with new rates effective on July 1, 2012.  This accomplished a goal set by the parties to the 2009 Settlement Agreement to process subsequent rate cases within twelve months of sufficiency findings from the ACC staff, which generally occurs within 30 days after the filing of a rate case.
 
Cost Recovery Mechanisms
 
APS has received regulatory decisions that allow for more timely recovery of certain costs through the following recovery mechanisms.
 
Renewable Energy Standard.  In 2006, the ACC approved the RES.  Under the RES, electric utilities that are regulated by the ACC must supply an increasing percentage of their retail electric energy sales from eligible renewable resources, including solar, wind, biomass, biogas and geothermal technologies.  In order to achieve these requirements, the ACC allows APS to include a RES surcharge as part of customer bills to recover the approved amounts for use on renewable energy projects.  Each year APS is required to file a five-year implementation plan with the ACC and seek approval for funding the upcoming year’s RES budget.
  
In December of 2014, the ACC voted that it had no objection to APS implementing an APS-owned rooftop solar research and development program aimed at learning how to efficiently enable the integration of rooftop solar and battery storage with the grid.  The first stage of the program, called the "Solar Partner Program," placed 8 MW of residential rooftop solar on strategically selected distribution feeders in an effort to maximize potential system benefits, as well as make systems available to limited-income customers who cannot easily install solar through transactions with third parties. The second stage of the program, which includes an additional 2 MW of rooftop solar and energy storage, will place two energy storage systems sized at 2 MW on two different high solar penetration feeders to test various grid-related operation improvements and system interoperability, and is planned to be in operation by the end of 2016.  The ACC expressly reserved that any determination of prudency of the residential rooftop solar program for rate making purposes shall not be made until the project is fully in service and APS requests cost recovery in a future rate case.

On July 1, 2015, APS filed its 2016 RES Implementation Plan and proposed a RES budget of approximately $148 million. On January 12, 2016, the ACC approved APS’s plan and requested budget.

On July 1, 2016, APS filed its 2017 RES Implementation Plan and proposed a budget of approximately $150 million. APS’s budget request included additional funding to process the high volume of residential rooftop solar interconnection requests and also requested a permanent waiver of the residential distributed energy requirement for 2017 contained in the RES rules.

In September of 2016, the ACC initiated a proceeding which will examine the possible modernization and expansion of the RES.  The ACC noted that many of the provisions of the original rule may no longer be appropriate, and the underlying economic assumptions associated with the rule have changed dramatically.  The proceeding will review such issues as the rapidly declining cost of solar generation, an increased interest in community solar projects, energy storage options, and the decline in fossil fuel generation due to stringent regulations of the United States Environmental Protection Agency ("EPA").  The proceeding will also examine the feasibility of increasing the standard to 30% of retail sales by 2030, in contrast to the current standard of 15% of retail sales by 2025.  APS cannot predict the outcome of this proceeding.
 
Demand Side Management Adjustor Charge.  The ACC Electric Energy Efficiency Standards require APS to submit a Demand Side Management Implementation Plan ("DSM Plan") for review by and approval of the ACC. In March 2014, the ACC approved a Resource Savings Initiative that allows APS to count towards compliance with the ACC Electric Energy Efficiency Standards, savings from improvements to APS’s transmission and delivery system, generation and facilities that have been approved through a DSM Plan. 

On March 20, 2015, APS filed an application with the ACC requesting a budget of $68.9 million for 2015 and minor modifications to its DSM portfolio going forward, including for the first time three resource savings projects which reflect energy savings on APS's system. The ACC approved APS’s 2015 DSM budget on November 25, 2015. In its decision, the ACC also approved that verified energy savings from APS's resource savings projects could be counted toward compliance with the Electric Energy Efficiency Standard, however, the ACC ruled that APS was not allowed to count savings from systems savings projects toward determination of its achievement tier level for its performance incentive, nor may APS include savings from conservation voltage reduction in the calculation of its LFCR mechanism.

On June 1, 2015, APS filed its 2016 DSM Plan requesting a budget of $68.9 million and minor modifications to its DSM portfolio to increase energy savings and cost effectiveness of the programs. On April 1, 2016, APS filed an amended 2016 DSM Plan that sought minor modifications to its existing DSM Plan and requested to continue the current DSMAC and current budget of $68.9 million. On July 12, 2016, the ACC approved APS’s amended DSM Plan and directed APS to spend up to an additional $4 million on a new residential demand response or load management program that facilitates energy storage technology.
 
Electric Energy Efficiency. On June 27, 2013, the ACC voted to open a new docket investigating whether the Electric Energy Efficiency Standards should be modified.  The ACC held a series of three workshops in March and April 2014 to investigate methodologies used to determine cost effective energy efficiency programs, cost recovery mechanisms, incentives, and potential changes to the Electric Energy Efficiency and Resource Planning Rules.

On November 4, 2014, the ACC staff issued a request for informal comment on a draft of possible amendments to Arizona’s Electric Energy Efficiency Standards. The draft proposed substantial changes to the rules and energy efficiency standards. The ACC accepted written comments and took public comment regarding the possible amendments on December 19, 2014. A formal rulemaking has not been initiated and there has been no additional action on the draft to date. On July 12, 2016, the ACC ordered that ACC staff convene a workshop within 120 days to discuss a number of issues related to the Electric Energy Efficiency Standards, including the process of determining the cost effectiveness of DSM programs and the treatment of peak demand and capacity reductions, among others.
 
PSA Mechanism and Balance.  The PSA provides for the adjustment of retail rates to reflect variations in retail fuel and purchased power costs.  The following table shows the changes in the deferred fuel and purchased power regulatory asset (liability) for 2016 and 2015 (dollars in thousands):
 
 
Nine Months Ended 
 September 30,
 
2016
 
2015
Beginning balance
$
(9,688
)
 
$
6,925

Deferred fuel and purchased power costs — current period
46,185

 
137

Amounts charged to customers
(28,365
)
 
(19,284
)
Ending balance
$
8,132

 
$
(12,222
)

 
The PSA rate for the PSA year beginning February 1, 2016 is $0.001678 per kWh, as compared to $0.000887 per kWh for the prior year.  This new rate is comprised of a forward component of $0.001975 per kWh and a historical component of $(0.000297) per kWh.  On October 15, 2015, APS notified the ACC that it was initiating a PSA transition component of $(0.004936) per kWh for the months of November 2015, December 2015, and January 2016. The PSA transition component is a mid-year adjustment to the PSA rate that may be established when conditions change sufficiently to cause high balances to accrue in the PSA balancing account. The transition component expired on February 1, 2016. Any uncollected (overcollected) deferrals during the PSA year, after accounting for the transition component, will be included in the calculation of the PSA rate for the PSA year beginning February 1, 2017.
 
Transmission Rates, Transmission Cost Adjustor and Other Transmission Matters In July 2008, the United States Federal Energy Regulatory Commission ("FERC") approved an Open Access Transmission Tariff for APS to move from fixed rates to a formula rate-setting methodology in order to more accurately reflect and recover the costs that APS incurs in providing transmission services.  A large portion of the rate represents charges for transmission services to serve APS's retail customers ("Retail Transmission Charges").  In order to recover the Retail Transmission Charges, APS was previously required to file an application with, and obtain approval from, the ACC to reflect changes in Retail Transmission Charges through the TCA.  Under the terms of the 2012 Settlement Agreement, however, an adjustment to rates to recover the Retail Transmission Charges will be made annually each June 1 and will go into effect automatically unless suspended by the ACC.
 
The formula rate is updated each year effective June 1 on the basis of APS's actual cost of service, as disclosed in APS's FERC Form 1 report for the previous fiscal year.  Items to be updated include actual capital expenditures made as compared with previous projections, transmission revenue credits and other items.  The resolution of proposed adjustments can result in significant volatility in the revenues to be collected.  APS reviews the proposed formula rate filing amounts with the ACC staff.  Any items or adjustments which are not agreed to by APS and the ACC staff can remain in dispute until settled or litigated at FERC.  Settlement or litigated resolution of disputed issues could require an extended period of time and could have a significant effect on the Retail Transmission Charges because any adjustment, though applied prospectively, may be calculated to account for previously over- or under-collected amounts.
 
Effective June 1, 2015, APS’s annual wholesale transmission rates for all users of its transmission system decreased by approximately $17.6 million for the twelve-month period beginning June 1, 2015 in accordance with the FERC-approved formula.  An adjustment to APS’s retail rates to recover FERC-approved transmission charges went into effect automatically on June 1, 2015.

Effective June 1, 2016, APS's annual wholesale transmission rates for all users of its transmission system increased by approximately $24.9 million in accordance with the FERC-approved formula.  An adjustment to APS’s retail rates to recover FERC approved transmission charges went into effect automatically on June 1, 2016.

APS's formula rate protocols have been in effect since 2008. Recent FERC orders suggest that FERC is examining the structure of formula rate protocols and may require companies such as APS to make changes to their protocols in the future.
 
Lost Fixed Cost Recovery Mechanism.  The LFCR mechanism permits APS to recover on an after-the-fact basis a portion of its fixed costs that would otherwise have been collected by APS in the kWh sales lost due to APS energy efficiency programs and to distributed generation such as rooftop solar arrays.  The fixed costs recoverable by the LFCR mechanism were established in the 2012 Settlement Agreement and amount to approximately 3.1 cents per residential kWh lost and 2.3 cents per non-residential kWh lost.  The LFCR adjustment has a year-over-year cap of 1% of retail revenues.  Any amounts left unrecovered in a particular year because of this cap can be carried over for recovery in a future year.  The kWh’s lost from energy efficiency are based on a third-party evaluation of APS’s energy efficiency programs.  Distributed generation sales losses are determined from the metered output from the distributed generation units.
 
APS files for a LFCR adjustment every January. APS filed its 2014 annual LFCR adjustment on January 15, 2014, requesting a LFCR adjustment of $25.3 million, effective March 1, 2014.  The ACC approved APS’s LFCR adjustment without change on March 11, 2014, which became effective April 1, 2014. APS filed its 2015 annual LFCR adjustment on January 15, 2015, requesting an LFCR adjustment of $38.5 million, which was approved on March 2, 2015, effective for the first billing cycle of March. APS filed its 2016 annual LFCR adjustment on January 15, 2016, requesting an LFCR adjustment of $46.4 million (a $7.9 million annual increase), to be effective for the first billing cycle of March 2016. The ACC approved the 2016 annual LFCR to be effective in May 2016. Because the LFCR mechanism has a balancing account that trues up any under or over recoveries, the two months delay in implementation did not have an adverse effect on APS.

Net Metering

On July 12, 2013, APS filed an application with the ACC proposing a solution to address the cost shift brought by the current net metering rules.  On December 3, 2013, the ACC issued its order on APS's net metering proposal. The ACC instituted a charge on customers who install rooftop solar panels after December 31, 2013. The charge of $0.70 per kilowatt became effective on January 1, 2014, and is estimated to collect $4.90 per month from a typical future rooftop solar customer to help pay for their use of the electric grid. The fixed charge does not increase APS's revenue because it is credited to the LFCR.
 
In making its decision, the ACC determined that the current net metering program creates a cost shift, causing non-solar utility customers to pay higher rates to cover the costs of maintaining the electric grid.  The ACC acknowledged that the $0.70 per kilowatt charge addresses only a portion of the cost shift. 
 
On October 20, 2015, the ACC voted to conduct a generic evidentiary hearing on the value and cost of distributed generation to gather information that will inform the ACC on net metering issues and cost of service studies in upcoming utility rate cases.  A hearing was held in April 2016. On October 7, 2016, an Administrative Law Judge (the "ALJ") issued a recommendation in the docket concerning the value and cost of distributed generation. The ALJ recommended a change to how customers are compensated for energy that they export from rooftop solar systems. Instead of retail rate net metering, the ALJ recommended that the amount of compensation be established by using both an avoided cost calculation and a grid-scale solar resource proxy calculation that would be updated in subsequent utility rate cases. The ALJ recommended that the change to how APS pays for exported rooftop solar energy apply only to those customers who apply to interconnect their distributed generation systems after a decision in APS’s currently pending rate case. The ALJ found rooftop solar customers to be partial requirements customers, but recommended that whether rooftop solar customers should be placed into a separate customer class for purposes of ratemaking be decided in individual utility rate cases. Exceptions to the ALJ recommendation are due November 15, 2016. On December 13, 2016, the ACC will discuss at an open meeting the ALJ recommendation concerning the value and cost of distributed generation.  APS cannot predict the outcome of this proceeding.

In 2015, Arizona jurisdictional utilities UNS Electric, Inc. and Tucson Electric Power Company ("TEP") both filed applications with the ACC requesting rate increases. These applications include rate design changes to mitigate the cost shift caused by net metering. On December 9, 2015 and February 23, 2016, APS filed testimony in the UNS Electric, Inc. rate case in support of the UNS Electric, Inc. proposed rate design changes. APS actively participated in the related hearings held in March 2016. On August 18, 2016, the ACC issued a decision which ordered that net metering be considered in a separate, phase 2 of the UNS Electric, Inc. rate case to occur after the ACC decides issues raised in the separate, generic docket concerning the value and cost of distributed generation discussed above. APS has also intervened in the upcoming TEP rate case. On June 24, 2016, APS filed testimony in the TEP rate case in support of the TEP proposed rate design changes. In August 2016, the ACC also bifurcated the TEP rate case into two phases, the first of which will address revenue requirements and other traditional rate case issues while the second will address net metering issues. The outcomes of these proceedings will not directly impact our financial position.

Appellate Review of Third-Party Regulatory Decision ("System Improvement Benefits" or "SIB")

In a recent appellate challenge to an ACC rate decision involving a water company, the Arizona Court of Appeals considered the question of how the ACC should determine the “fair value” of a utility’s property, as specified in the Arizona Constitution, in connection with authorizing the recovery of costs through rate adjustors outside of a rate case.  The Court of Appeals reversed the ACC’s method of finding fair value in that case, and raised questions concerning the relationship between the need for fair value findings and the recovery of capital and certain other utility costs through adjustors. The ACC sought review by the Arizona Supreme Court of this decision, and APS filed a brief supporting the ACC’s petition to the Arizona Supreme Court for review of the Court of Appeals’ decision.  On February 9, 2016, the Arizona Supreme Court granted review of the decision and on August 8, 2016, the Arizona Supreme Court vacated the Court of Appeals opinion and affirmed the ACC’s orders approving the water company’s SIB adjustor.

System Benefits Charge

The 2012 Settlement Agreement  provides that once APS achieved full funding of its decommissioning obligation under the sale leaseback agreements covering Unit 2 of Palo Verde, APS was required to implement a reduced System Benefits charge effective January 1, 2016.  Beginning on January 1, 2016, APS began implementing a reduced System Benefits charge.  The impact on APS retail revenues from the new System Benefits charge is an overall reduction of approximately $14.6 million per year with a corresponding reduction in depreciation and amortization expense.

Subpoena from Arizona Corporation Commissioner Robert Burns

On August 25, 2016, Commissioner Burns, individually and not by action of the ACC as a whole, filed subpoenas in APS’s current retail rate proceeding to APS and Pinnacle West for the production of records and information relating to a range of expenditures from 2011 through year-to-date 2016. The subpoenas request information concerning marketing and advertising expenditures, charitable donations, lobbying expenses, contributions to 501(c)(3) and (c)(4) nonprofits and political contributions. The return date for the production of information was set as September 15, 2016. The subpoenas also sought testimony from company personnel having knowledge of the material, including the Chief Executive Officer, on October 6, 2016.

On September 9, 2016, APS filed with the ACC a motion to quash the subpoenas, or alternatively stay APS’ obligations to comply with the subpoenas and decline to decide APS’ motion pending court proceedings. Contemporaneously with the filing of this motion, APS and Pinnacle West filed a complaint for special action and declaratory judgment in the Superior Court of Arizona for Maricopa County, seeking a declaratory judgment that Commissioner Burns’ subpoenas are contrary to law. On September 15, 2016, APS produced all non-confidential and responsive documents and offered to produce any remaining responsive documents that are confidential after an appropriate confidentiality agreement is signed. APS and Pinnacle West cannot predict the outcome of this matter.

Four Corners
 
On December 30, 2013, APS purchased Southern California Edison Company's ("SCE’s") 48% ownership interest in each of Units 4 and 5 of Four Corners.  The 2012 Settlement Agreement includes a procedure to allow APS to request rate adjustments prior to its next general rate case related to APS’s acquisition of the additional interests in Units 4 and 5 and the related closure of Units 1-3 of Four Corners.  APS made its filing under this provision on December 30, 2013. On December 23, 2014, the ACC approved rate adjustments resulting in a revenue increase of $57.1 million on an annual basis.  This includes the deferral for future recovery of all non-fuel operating costs for the acquired SCE interest in Four Corners, net of the non-fuel operating costs savings resulting from the closure of Units 1-3 from the date of closing of the purchase through its inclusion in rates.  The 2012 Settlement Agreement also provides for deferral for future recovery of all unrecovered costs incurred in connection with the closure of Units 1-3.  The deferral balance related to the acquisition of SCE’s interest in Units 4 and 5 and the closure of Units 1-3 was $65 million as of September 30, 2016 and is being amortized in rates over a total of 10 years. On February 23, 2015, the Arizona School Boards Association and the Association of Business Officials filed a notice of appeal in Division 1 of the Arizona Court of Appeals of the ACC decision approving the rate adjustments. APS has intervened and is actively participating in the proceeding. The Arizona Court of Appeals suspended the appeal pending the Arizona Supreme Court's decision in the SIB matter discussed above. On August 8, 2016, the Arizona Supreme Court issued its opinion in the SIB matter, and the Arizona Court of Appeals has now ordered supplemental briefing on how that SIB decision should affect the challenge to the Four Corners rate adjustment. We cannot predict when or how this matter will be resolved.
 
As part of APS’s acquisition of SCE’s interest in Units 4 and 5, APS and SCE agreed, via a "Transmission Termination Agreement" that, upon closing of the acquisition, the companies would terminate an existing transmission agreement ("Transmission Agreement") between the parties that provides transmission capacity on a system (the "Arizona Transmission System") for SCE to transmit its portion of the output from Four Corners to California.  APS previously submitted a request to FERC related to this termination, which resulted in a FERC order denying rate recovery of $40 million that APS agreed to pay SCE associated with the termination. On December 22, 2015, APS and SCE agreed to terminate the Transmission Termination Agreement and allow for the Transmission Agreement to expire according to its terms, which includes settling obligations in accordance with the terms of the Transmission Agreement. APS established a regulatory asset of $12 million in 2015 in connection with the payment required under the terms of the Transmission Agreement. On July 1, 2016, FERC issued an order denying APS’s request to recover the regulatory asset through its FERC-jurisdictional rates.  APS and SCE completed the termination of the Transmission Agreement on July 6, 2016. APS made the required payment to SCE and wrote-off the $12 million regulatory asset and charged operating revenues to reflect this order in the second quarter of 2016.  On July 29, 2016, APS filed a request for rehearing with FERC. In its order denying recovery FERC also referred to its enforcement division a question of whether the agreement between APS and SCE relating to the settlement of obligations under the Transmission Agreement was a jurisdictional contract that should have been filed with FERC. APS cannot predict the outcome of either matter.

Cholla

On September 11, 2014, APS announced that it would close Unit 2 of the Cholla Power Plant ("Cholla") and cease burning coal at the other APS-owned units (Units 1 and 3) at the plant by the mid-2020s, if EPA approves a compromise proposal offered by APS to meet required environmental and emissions standards and rules. On April 14, 2015, the ACC approved APS's plan to retire Unit 2, without expressing any view on the future recoverability of APS's remaining investment in the Unit. APS closed Unit 2 on October 1, 2015. Previously, APS estimated Cholla Unit 2’s end of life to be 2033. APS is currently recovering a return on and of the net book value of the unit in base rates and is seeking recovery of the unit’s decommissioning and other retirement-related costs over the remaining life of the plant in its current retail rate case. APS believes it will be allowed recovery of the remaining net book value of Unit 2 ($117 million as of September 30, 2016), in addition to a return on its investment. In accordance with GAAP, in the third quarter of 2014, Unit 2’s remaining net book value was reclassified from property, plant and equipment to a regulatory asset. If the ACC does not allow full recovery of the remaining net book value of Cholla Unit 2, all or a portion of the regulatory asset will be written off and APS’s net income, cash flows, and financial position will be negatively impacted.
Regulatory Assets and Liabilities 
The detail of regulatory assets is as follows (dollars in thousands):
 
 
Amortization Through
 
September 30, 2016
 
December 31, 2015
 
 
Current
 
Non-Current
 
Current
 
Non-Current
Pension
(a)
 
$

 
$
608,312

 
$

 
$
619,223

Retired power plant costs
2033
 
9,913

 
120,072

 
9,913

 
127,518

Income taxes — allowance for funds used during construction ("AFUDC") equity
2046
 
5,419

 
151,451

 
5,495

 
133,712

Deferred fuel and purchased power — mark-to-market (Note 6)
2019
 
30,748

 
53,350

 
71,852

 
69,697

Deferred fuel and purchased power (c) (e)
2017
 
8,132

 

 

 

Four Corners cost deferral
2024
 
6,689

 
58,566

 
6,689

 
63,582

Income taxes — investment tax credit basis adjustment
2045
 
1,852

 
46,699

 
1,766

 
48,462

Lost fixed cost recovery (b)
2017
 
55,297

 

 
45,507

 

Palo Verde VIEs (Note 5)
2046
 

 
18,620

 

 
18,143

Deferred compensation
2036
 

 
36,071

 

 
34,751

Deferred property taxes
(c)
 

 
67,547

 

 
50,453

Loss on reacquired debt
2034
 
1,592

 
16,521

 
1,515

 
16,375

Tax expense of Medicare subsidy
2024
 
1,512

 
10,774

 
1,520

 
12,163

Transmission vegetation management
2016
 

 

 
4,543

 

Mead-Phoenix transmission line CIAC
2050
 
332

 
10,791

 
332

 
11,040

Transmission cost adjustor (b)
2018
 

 
4,687

 

 
2,942

Coal reclamation
2026
 
418

 
5,286

 
418

 
6,085

Other
Various
 
316

 
3,403

 
5

 

Total regulatory assets (d)
 
 
$
122,220

 
$
1,212,150

 
$
149,555

 
$
1,214,146


(a)
This asset represents the future recovery of pension benefit obligations through retail rates.  If these costs are disallowed by the ACC, this regulatory asset would be charged to Other Comprehensive Income ("OCI") and result in lower future revenues.  See Note 4 for further discussion.
(b)
See "Cost Recovery Mechanisms" discussion above.
(c)
Per the provision of the 2012 Settlement Agreement.
(d)
There are no regulatory assets for which the ACC has allowed recovery of costs, but not allowed a return by exclusion from rate base.  FERC rates are set using a formula rate as described in "Transmission Rates, Transmission Cost Adjustor and Other Transmission Matters."
(e)
Subject to a carrying charge.


    
The detail of regulatory liabilities is as follows (dollars in thousands):
 
 
Amortization Through
 
September 30, 2016
 
December 31, 2015
 
 
Current
 
Non-Current
 
Current
 
Non-Current
Asset retirement obligations
2057
 
$

 
$
305,862

 
$

 
$
277,554

Removal costs
(a)
 
27,626

 
237,885

 
39,746

 
240,367

Other postretirement benefits
(d)
 
33,294

 
146,988

 
34,100

 
179,521

Income taxes — deferred investment tax credit
2045
 
3,774

 
93,578

 
3,604

 
97,175

Income taxes — change in rates
2046
 
1,771

 
70,233

 
1,113

 
72,454

Spent nuclear fuel
2047
 

 
71,884

 
3,051

 
67,437

Renewable energy standard (b)
2017
 
28,921

 
1,091

 
43,773

 
4,365

Demand side management (b)
2017
 
4,261

 
21,863

 
6,079

 
19,115

Sundance maintenance
2030
 

 
14,885

 

 
13,678

Deferred fuel and purchased power (b) (c)
2017
 

 

 
9,688

 

Deferred gains on utility property
2019
 
2,063

 
9,335

 
2,062

 
6,001

Transmission cost adjustor (b)
2017
 
2,077

 

 

 

Four Corners coal reclamation
2031
 

 
17,213

 

 
8,920

Other
Various
 
526

 
7,532

 
2,550

 
7,565

Total regulatory liabilities
 
 
$
104,313

 
$
998,349

 
$
145,766

 
$
994,152


(a)
In accordance with regulatory accounting guidance, APS accrues for removal costs for its regulated assets, even if there is no legal obligation for removal.
(b)
See "Cost Recovery Mechanisms" discussion above.
(c)
Subject to a carrying charge.
(d)
See Note 4.