Commitments and Contingencies - Superfund-Related Matters and Southwest Power Outage (Details) (Arizona Public Service Company, USD $)
In Millions, unless otherwise specified
0 Months Ended 9 Months Ended 0 Months Ended
Jul. 07, 2014
Requirement
Jan. 22, 2014
Entity
Requirement
Sep. 08, 2011
item
MW
kV
Customer
Sep. 30, 2014
Aug. 06, 2013
Contaminated groundwater wells
Defendant
Superfund-Related Matters          
Costs related to investigation and study under Superfund site       $ 2  
Number of defendants against whom Roosevelt Irrigation District (RID) filed lawsuit         24
Southwest Power Outage          
Capacity of transmission line that tripped out of service (in kV)     500    
Period, after the transmission line went off-line, over which generation and transmission resources for the Yuma area were lost     10 minutes    
Number of customers losing service in Yuma area     69,700    
Capacity of firm load that were reported to have been affected due to outages affecting portions of southern Arizona, southern California and northern Mexico (in MW)     7,900    
Number of customers that were reported to have been affected due to outages     2,700,000    
Number of alleged entities   6      
Number of reliability standard requirements violations   7      
Number of reliability standard requirements neither admitted nor denied violations in settlement 4        
Amount of civil penalty agreed in settlement 3.25        
Civil penalty amount required to be paid in equal parts 2        
Civil penalty amount offset in exchange for completing certain reliability enhancements $ 1.25