Costs and Estimated Earnings Related to Billings on Uncompleted Contracts
6 Months Ended
Aug. 31, 2011
Costs and Estimated Earnings Related to Billings on Uncompleted Contracts [Abstract] 
Costs and Estimated Earnings Related to Billings on Uncompleted Contracts
Note 5. — Costs and Estimated Earnings Related to Billings on Uncompleted Contracts
          Information relative to contracts in progress consisted of the following:
                 
    August 31,     February 28,  
    2011     2011  
Costs incurred to date on uncompleted contracts
  $ 6,915     $ 5,598  
Estimated earnings recognized to date on these contracts
    3,734       2,941  
 
           
 
    10,649       8,539  
Billings to date
    (8,563 )     (7,373 )
 
           
Costs and estimated earnings in excess of billings, net
  $ 2,086     $ 1,166  
 
           
 
               
Costs and estimated earnings in excess of billings
  $ 2,573     $ 2,192  
Billings in excess of costs and estimated earnings
    (487 )     (1,026 )
 
           
 
  $ 2,086     $ 1,166  
 
           
          Costs and estimated earnings in excess of billings are the results of contracts in progress (jobs) in completing orders to customers’ specifications on contracts accounted for under FASB ASC 605-35, “Revenue Recognition: Construction-Type and Production-Type Contracts.” Costs included are material, labor, and overhead. These jobs require design and engineering effort for a specific customer purchasing a unique product. The Company records revenue on these fixed-price and cost-plus contracts on the percentage of completion basis using the ratio of costs incurred to estimated total costs at completion as the measurement basis for progress toward completion and revenue recognition. Any losses identified on contracts are recognized immediately. Contract accounting requires significant judgment relative to assessing risks, estimating contract costs and making related assumptions for schedule and technical issues. With respect to contract change orders, claims, or similar items, judgment must be used in estimating related amounts and assessing the potential for realization. These amounts are only included in contract value when they can be reliably estimated and realization is probable. Billings are generated based on specific contract terms, which might be a progress payment schedule, specific shipments, etc. None of the above contracts in progress contain post-shipment obligations.
          Changes in job performance, manufacturing efficiency, final contract settlements, and other factors affecting estimated profitability may result in revisions to costs and income and are recognized in the period in which the revisions are determined.
          As of August 31, 2011 and February 28, 2011, there were no production costs that exceeded the aggregate estimated cost of all in-process and delivered units relating to long-term contracts. Additionally, there were no claims outstanding that would affect the ultimate realization of full contract values. As of August 31, 2011 and February 28, 2011, there were no progress payments that had been netted against inventory.