COMMITMENTS AND CONTINGENCIES Nuclear (Details)
12 Months Ended
Dec. 31, 2015
USD ($)
Dec. 31, 2021
Dec. 31, 2020
Dec. 31, 2019
Dec. 31, 2014
USD ($)
Forecasted Incremental Capital Costs Associated With Schedule Delays, 2015 Petition $ 539,000,000        
EPC Contract Amendment, New Nuclear Construction Completion Bonus 151,000,000        
Aggregate Nominal Coverage of Bond 100,000,000        
Aggregate Nominal Coverage of Bond, SCE&G Share 55,000,000        
EPC Contract Amendment, Fixed Price Option, Increase In Total New Nuclear Project Cost $ 774,000,000        
Emission Rate Standard For Coal Fired Power Plants Under Clean Air Act 1,400        
Goal For Reduced Carbon Dioxide Emissions From 2005 Levels By 2030 Under Clean Air Act 32.00%        
Number of States affected by CSAPR 28        
Capital costs, owners [Domain]          
Forecasted incremental capital costs, 2015 petition $ 245,000,000        
Forecasted Total Capital Costs, 2015 Petition 5,200,000,000.0        
Capital costs, Other [Domain] [Domain]          
Forecasted incremental capital costs, 2015 petition 453,000,000        
Forecasted Total Capital Costs, 2015 Petition 6,800,000,000.0        
SCE&G          
EPC Contract Amendment, Credit Applied To Target Component Of New Units Contract Price 27,000,000        
EPC Contract Amendment, Increase In Fixed Component Of Contract Price 165,000,000        
EPC Contract Amendment, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 255,000,000        
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Per Month 55,000,000        
EPC Contract Amendment, Increase In Total New Nuclear Project Cost 286,000,000        
Total New Nuclear Project Cost Approved By SCPSC In September 2015 7,000,000,000        
EPC Contract Amendment, Fixed Price Option, Project Cost Including Fixed Option Price Increase 7,600,000,000.0        
EPC Contract Amendment, Total New Nuclear Project Cost Including Amendment Increase 7,000,000,000        
Aggregate Nominal Coverage of Bond 100,000,000        
Aggregate Nominal Coverage of Bond, SCE&G Share 55,000,000        
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015 3,345,000,000.000        
EPC Contract Amendment, Fixed Price Option, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 186,000,000        
EPC Contract Amendment, Fixed Price Option, New Nuclear Construction Completion Bonus 83,000,000        
Summer Station New Units [Domain]          
Jointly Owned Utility Plant, Ownership Amount of Construction Work in Progress 3,400,000,000       $ 2,700,000,000
jointly owned utility plant ownership, construction financing cost 3,200,000,000        
EPC Contract Amendment, Credit Applied To Target Component Of New Units Contract Price 50,000,000        
EPC Contract Amendment, Increase In Fixed Component Of Contract Price 300,000,000        
EPC Contract Amendment, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 463,000,000        
EPC Contract Amendment, New Nuclear Construction Completion Bonus 275,000,000        
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Per Month 100,000,000        
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015 6,082,000,000.000        
EPC Contract Amendment, Fixed Price Option, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 338,000,000        
EPC Contract Amendment, Fixed Price Option, New Nuclear Construction Completion Bonus 150,000,000        
Nuclear Production Tax Credits 1,400,000,000        
Scenario, Forecast [Member] | SCE&G          
Additional ownership in new units   2.00% 2.00% 1.00%  
Minimum [Member] | SCE&G          
Additional ownership in new units, dollars 750,000,000        
Maximum [Member] | SCE&G          
Additional ownership in new units, dollars $ 850,000,000