XML 62 R50.htm IDEA: XBRL DOCUMENT v3.10.0.1
Contingencies (Details) - USD ($)
$ in Thousands
6 Months Ended 12 Months Ended
Jun. 30, 2018
Dec. 31, 2012
Site Contingency [Line Items]    
Litigation Settlement, Amount   $ 110,000
Environmental Costs Recovered $ 37,000  
Huntsville Site [Member]    
Site Contingency [Line Items]    
Environmental Remediation Expense To Date 5,900  
Additional Expected Project Expenditures Low Estimate 4,300  
Additional Expected Project Expenditures High Estimate 10,000  
Norco Site [Member] | Remediation, Project Management, Regulatory Oversight, and Investigative and Feasability Studies [Member]    
Site Contingency [Line Items]    
Environmental Remediation Expense To Date 63,200  
Additional Expected Project Expenditures Low Estimate 16,000  
Additional Expected Project Expenditures High Estimate $ 26,700