Commitments and Contingencies (Estimated Planned Capital Expenditures) (Details)
$ in Millions
12 Months Ended
Dec. 31, 2022
USD ($)
MW
Planned Capital Expenditures [Line Items]  
Guarantor Obligations, Current Carrying Value $ 495
NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 8,875
2024 3,050
2025 880
2026 480
2027 420
Total 13,705
Wind Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 2,650
2024 1,095
2025 315
2026 20
2027 20
Total $ 4,100
Planned New Generation To Be Added over 5 Years | MW 2,955
Solar Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 $ 4,020
2024 1,145
2025 225
2026 0
2027 0
Total $ 5,390
Planned New Generation To Be Added over 5 Years | MW 6,618
Other Clean Energy Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 $ 1,175
2024 350
2025 55
2026 75
2027 45
Total 1,700
Nuclear Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 95
2024 215
2025 145
2026 260
2027 285
Total 1,000
Rate-Regulated Transmission [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 170
2024 65
2025 45
2026 10
2027 10
Total 300
Other Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2023 765
2024 180
2025 95
2026 115
2027 60
Total 1,215
FPL [Member]  
Planned Capital Expenditures [Line Items]  
2023 9,020
2024 8,080
2025 8,225
2026 8,875
2027 8,940
Total 43,140
FPL [Member] | New Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2023 3,060
2024 2,315
2025 2,820
2026 3,670
2027 3,150
Total 15,015
FPL [Member] | Existing Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2023 1,615
2024 1,175
2025 1,045
2026 1,280
2027 1,465
Total 6,580
FPL [Member] | Transmission and Distribution Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2023 3,545
2024 3,975
2025 3,645
2026 3,340
2027 3,575
Total 18,080
Planned Generation Capital Expenditures AFUDC First Year 60
Planned Generation Capital Expenditures AFUDC Second Year 50
Planned Generation Capital Expenditures AFUDC Third Year 55
Planned Generation Capital Expenditures AFUDC Fourth Year 30
Planned Generation Capital Expenditures AFUDC Fifth Year 30
FPL [Member] | Nuclear Fuel Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2023 125
2024 160
2025 200
2026 200
2027 225
Total 910
FPL [Member] | General and Other Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2023 675
2024 455
2025 515
2026 385
2027 525
Total 2,555
FPL [Member] | Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
Planned Generation Capital Expenditures AFUDC First Year 105
Planned Generation Capital Expenditures AFUDC Second Year 105
Planned Generation Capital Expenditures AFUDC Third Year 90
Planned Generation Capital Expenditures AFUDC Fourth Year 125
Planned Generation Capital Expenditures AFUDC Fifth Year $ 115