XML 70 R38.htm IDEA: XBRL DOCUMENT v3.3.1.900
Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2015
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Planned Capital Expenditures
At December 31, 2015, estimated capital expenditures for 2016 through 2020 for which applicable internal approvals (and also FPSC approvals for FPL, if required) have been received were as follows:
 
2016
 
2017
 
2018
 
2019
 
2020
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
1,085

 
$
45

 
$

 
$

 
$

 
$
1,130

Existing
620

 
960

 
680

 
520

 
550

 
3,330

Transmission and distribution
1,930

 
1,990

 
1,985

 
2,485

 
2,335

 
10,725

Nuclear fuel
170

 
125

 
190

 
170

 
210

 
865

General and other
245

 
265

 
240

 
185

 
185

 
1,120

Total
$
4,050

 
$
3,385

 
$
3,095

 
$
3,360

 
$
3,280

 
$
17,170

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(d)
$
2,040

 
$
75

 
$
30

 
$
25

 
$
25

 
$
2,195

Solar(e)
1,240

 
10

 

 

 

 
1,250

Nuclear, including nuclear fuel
300

 
240

 
270

 
310

 
265

 
1,385

Natural gas pipelines(f)
1,020

 
740

 
465

 
35

 
15

 
2,275

Other
495

 
60

 
75

 
50

 
65

 
745

Total
$
5,095

 
$
1,125

 
$
840

 
$
420

 
$
370

 
$
7,850

Corporate and Other
$
215

 
$
160

 
$
115

 
$
140

 
$
135

 
$
765

______________________
(a)
Includes AFUDC of approximately $76 million, $14 million and $11 million for 2016 through 2018, respectively.
(b)
Includes land, generation structures, transmission interconnection and integration and licensing.
(c)
Excludes capital expenditures of approximately $1.0 billion for the natural gas-fired combined-cycle unit in Okeechobee County, Florida for the period from the end of 2016 (when approval by the Florida Power Plant Siting Board (Siting Board), comprised of the Florida governor and cabinet is expected) through 2019. Also excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive and maintain an NRC license for each unit.
(d)
Consists of capital expenditures for new wind projects and related transmission totaling approximately 1,365 MW.
(e)
Includes capital expenditures for new solar projects and related transmission totaling approximately 1,045 MW.
(f)
Includes capital expenditures for construction of three natural gas pipelines, including equity contributions associated with equity investments in joint ventures for two pipelines and AFUDC associated with the third pipeline. The natural gas pipelines are subject to certain conditions. See Contracts below.
Required Capacity and/or Minimum Payments

The required capacity and/or minimum payments under the contracts discussed above as of December 31, 2015 were estimated as follows:
 
2016
 
2017
 
2018
 
2019
 
2020
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges(a)
$
185

 
$
170

 
$
140

 
$
120

 
$
110

 
$
690

Minimum charges, at projected prices:(b)
 
 
 
 
 
 
 
 
 
 
 
Natural gas, including transportation and storage(c)
$
1,020

 
$
930

 
$
870

 
$
865

 
$
920

 
$
13,050

Coal, including transportation
$
65

 
$
40

 
$

 
$

 
$

 
$

NEER
$
3,670

 
$
735

 
$
625

 
$
135

 
$
85

 
$
535

Corporate and Other(d)(e)
$
60

 
$
5

 
$
5

 
$

 
$
5

 
$

______________________
(a)
Capacity charges under these contracts, substantially all of which are recoverable through the capacity clause, totaled approximately $434 million, $485 million and $487 million for the years ended December 31, 2015, 2014 and 2013, respectively. Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $262 million, $299 million and $263 million for the years ended December 31, 2015, 2014 and 2013, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes approximately $200 million, $295 million, $290 million, $360 million and $7,885 million in 2017, 2018, 2019, 2020 and thereafter, respectively, of firm commitments, subject to certain conditions as noted above, related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.
(d)
Includes an approximately $35 million commitment to invest in clean power and technology businesses through 2021.
(e)
Excludes approximately $1,115 million, in 2016, of joint obligations of NEECH and NEER which are included in the NEER amounts above.