Commitments and Contingencies (Estimated Planned Capital Expenditures) (Details) (USD $)
12 Months Ended
Dec. 31, 2011
MW
FPL [Member]
 
Planned Capital Expenditures [Line Items]  
2012 $ 3,675,000,000
2013 2,305,000,000
2014 1,760,000,000
2015 1,515,000,000
2016 1,470,000,000
Total 10,725,000,000
FPL [Member] | New Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 1,780,000,000 [1],[2],[3]
2013 625,000,000 [1],[2],[3]
2014 85,000,000 [1],[2],[3]
2015 0 [1],[2],[3]
2016 0 [1],[2],[3]
Total 2,490,000,000 [1],[2],[3]
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2012 109,000,000
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2013 40,000,000
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2014 2,000,000
Expected cost of power plant modernization 1,200,000,000
FPL [Member] | Existing Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 730,000,000 [1]
2013 660,000,000 [1]
2014 660,000,000 [1]
2015 525,000,000 [1]
2016 430,000,000 [1]
Total 3,005,000,000 [1]
FPL [Member] | Transmission and Distribution Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 830,000,000
2013 705,000,000
2014 690,000,000
2015 660,000,000
2016 705,000,000
Total 3,590,000,000
FPL [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 205,000,000
2013 125,000,000
2014 205,000,000
2015 250,000,000
2016 250,000,000
Total 1,035,000,000
FPL [Member] | General and Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 130,000,000
2013 190,000,000
2014 120,000,000
2015 80,000,000
2016 85,000,000
Total 605,000,000
FPL [Member] | Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - 2012 70,000,000
Allowance for funds used during construction (AFUDC) - 2013 87,000,000
Allowance for funds used during construction (AFUDC) - 2014 33,000,000
NextEra Energy Resources [Member]
 
Planned Capital Expenditures [Line Items]  
2012 3,410,000,000
2013 1,080,000,000
2014 525,000,000
2015 430,000,000
2016 345,000,000
Total 5,790,000,000
NextEra Energy Resources [Member] | Wind Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 1,490,000,000 [4]
2013 30,000,000 [4]
2014 20,000,000 [4]
2015 5,000,000 [4]
2016 5,000,000 [4]
Total 1,550,000,000 [4]
Planned new wind generation over the next year, low range (in megawatts) 1,150
Planned new wind generation over the next year, high range (in megawatts) 1,500
Planned new wind generation costs over the next year, low range 2,000,000,000
Planned new wind generation costs over the next year, high range 3,000,000,000
NextEra Energy Resources [Member] | Solar Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 1,435,000,000 [5]
2013 715,000,000 [5]
2014 145,000,000 [5]
2015 45,000,000 [5]
2016 0 [5]
Total 2,340,000,000 [5]
Planned new solar generation over 5 year period (in megawatts) 665
Planned new solar capacity of equity method investment (in megawatts) 550
Planned new solar capacity of projects requiring internal approvals (in megawatts) 270
Expected costs of new solar projects requiring internal approvals 1,000,000,000
NextEra Energy Resources [Member] | Nuclear Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 310,000,000 [6]
2013 255,000,000 [6]
2014 265,000,000 [6]
2015 280,000,000 [6]
2016 275,000,000 [6]
Total 1,385,000,000 [6]
NextEra Energy Resources [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Planned gas infrastructure costs, low range 400,000,000
Planned gas infrastructure costs, high range 600,000,000
NextEra Energy Resources [Member] | Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 175,000,000 [7]
2013 80,000,000 [7]
2014 95,000,000 [7]
2015 100,000,000 [7]
2016 65,000,000 [7]
Total 515,000,000 [7]
Corporate and Other [Member]
 
Planned Capital Expenditures [Line Items]  
2012 530,000,000 [8]
2013 85,000,000 [8]
2014 85,000,000 [8]
2015 75,000,000 [8]
2016 75,000,000 [8]
Total 850,000,000 [8]
Allowance for funds used during construction (AFUDC) - 2012 41,000,000
Allowance for funds used during construction (AFUDC) - 2013 $ 14,000,000
[1] Includes AFUDC of approximately $70 million, $87 million and $33 million in 2012 to 2014, respectively.
[2] Consists of projects that have received FPSC approval. Includes pre-construction costs and carrying charges (equal to a pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $109 million, $40 million and $2 million in 2012 to 2014, respectively. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit. Excludes capital expenditures for the modernization of the Port Everglades facility, which if the project proceeds and the required regulatory approvals are obtained is expected to cost approximately $1.2 billion and be placed in-service in 2016.
[3] Includes land, generating structures, transmission interconnection and integration and licensing.
[4] Consists of capital expenditures for planned new wind projects that have received applicable internal approvals and related transmission. NEER plans to add new wind generation of approximately 1,150 mw to 1,500 mw in 2012, at a total cost of approximately $2 billion to $3 billion.
[5] Consists of capital expenditures for planned new solar projects totaling 665 mw that have received applicable internal approvals and related transmission, including equity contributions associated with an equity method investment in a 550 mw solar project. Excludes solar projects requiring internal approvals with generation totaling 270 mw with an estimated cost of approximately $1 billion.
[6] Includes nuclear fuel.
[7] Consists of capital expenditures that have received applicable internal approvals. NEER plans to add natural gas infrastructure projects at a total cost of approximately $400 million to $600 million in 2010 through 2014.
[8] Consists of capital expenditures that have received applicable internal approvals and includes AFUDC related to Lone Star of approximately $41 million and $14 million in 2012 and 2013, respectively.