Commitments and Contingencies, Planned Capital Expenditures (Details) (USD $)
9 Months Ended
Sep. 30, 2011
mW
FPL [Member]
 
Planned Capital Expenditures [Line Items] 
2011$ 1,135,000,000
20123,780,000,000
20132,295,000,000
20141,690,000,000
20151,500,000,000
Total10,400,000,000
FPL [Member] | New Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011460,000,000[1],[2],[3]
20121,780,000,000[1],[2],[3]
2013610,000,000[1],[2],[3]
201475,000,000[1],[2],[3]
20150[1],[2],[3]
Total2,925,000,000[1],[2],[3]
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 201134,000,000
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2012100,000,000
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 201332,000,000
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 20142,000,000
Expected cost of Port Everglades power plant modernization1,200,000,000
FPL [Member] | Existing Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011275,000,000[2]
2012765,000,000[2]
2013665,000,000[2]
2014645,000,000[2]
2015515,000,000[2]
Total2,865,000,000[2]
FPL [Member] | Transmission And Distribution Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011220,000,000
2012835,000,000
2013685,000,000
2014650,000,000
2015635,000,000
Total3,025,000,000
FPL [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011125,000,000
2012205,000,000
2013125,000,000
2014205,000,000
2015250,000,000
Total910,000,000
FPL [Member] | General And Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
201155,000,000
2012195,000,000
2013210,000,000
2014115,000,000
2015100,000,000
Total675,000,000
FPL [Member] | Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
Allowance for funds used during construction (AFUDC) - 201110,000,000
Allowance for funds used during construction (AFUDC) - 201280,000,000
Allowance for funds used during construction (AFUDC) - 201386,000,000
Allowance for funds used during construction (AFUDC) - 201433,000,000
NextEra Energy Resources [Member]
 
Planned Capital Expenditures [Line Items] 
20111,155,000,000
20122,550,000,000
20131,045,000,000
2014475,000,000
2015385,000,000
Total5,610,000,000
NextEra Energy Resources [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011205,000,000[4]
2012295,000,000[4]
2013260,000,000[4]
2014260,000,000[4]
2015280,000,000[4]
Total1,300,000,000[4]
NextEra Energy Resources [Member] | Wind Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011290,000,000[5]
2012960,000,000[5]
201385,000,000[5]
201420,000,000[5]
20155,000,000[5]
Total1,360,000,000[5]
Planned new wind generation over current year and next year, low range (in megawatts)1,400
Planned new wind generation over current year and next year, high range (in megawatts)2,000
Planned new wind generation costs over current year and next year, low range3,000,000,000
Planned new wind generation costs over current year and next year, high range4,000,000,000
Planned new wind generation added to date in curret year (in megawatts)150
NextEra Energy Resources [Member] | Solar Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011540,000,000[6]
20121,135,000,000[6]
2013630,000,000[6]
2014110,000,000[6]
20155,000,000[6]
Total2,420,000,000[6]
Planned new solar generation over 5 year period 2010 - 2014, low range (in megawatts)670
Planned New Solar Capacity of Equity Method Investment550
Planned new solar capacity of projects requiring internal approvals270
Expected cost of new solar projects requiring internal approals1,000,000,000
NextEra Energy Resources [Member] | Natural Gas Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
Planned gas infrastructure costs over 5 year period 2010 - 2014, low range400,000,000
Planned gas infrastructure costs over 5 year period 2010 - 2014, high range600,000,000
NextEra Energy Resources [Member] | Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items] 
2011120,000,000[7]
2012160,000,000[7]
201370,000,000[7]
201485,000,000[7]
201595,000,000[7]
Total530,000,000[7]
Corporate And Other [Member]
 
Planned Capital Expenditures [Line Items] 
2011150,000,000[8]
2012520,000,000[8]
201375,000,000[8]
201430,000,000[8]
201530,000,000[8]
Total805,000,000[8]
Allowance for funds used during construction (AFUDC) - 20115,000,000
Allowance for funds used during construction (AFUDC) - 201242,000,000
Allowance for funds used during construction (AFUDC) - 2013$ 14,000,000
[1]Consists of projects that have received FPSC approval. Includes pre-construction costs and carrying charges (equal to a pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $34 million, $100 million, $32 million and $2 million in 2011 to 2014, respectively. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit. Excludes capital expenditures for the modernization of the Port Everglades facility, which if the project proceeds and the required regulatory approvals are obtained is expected to cost approximately $1.2 billion and be placed in-service in 2016.
[2]Includes allowance for funds used during construction (AFUDC) of approximately $10 million, $80 million, $86 million and $33 million in 2011 to 2014, respectively.
[3]Includes land, generating structures, transmission interconnection and integration and licensing.
[4]Includes nuclear fuel.
[5]Consists of capital expenditures for planned new wind projects that have received applicable internal approvals and related transmission. NextEra Energy Resources plans to add new wind generation of approximately 1,400 mw to 2,000 mw in 2011 and 2012, at a total cost of approximately $3 billion to $4 billion. These amounts include 150 mw added to date in 2011.
[6]Consists of capital expenditures for planned new solar projects totaling 670 mw that have received applicable internal approvals and related transmission, including equity contributions associated with an equity method investment in a 550 mw solar project. Excludes solar projects requiring internal approvals with generation totaling 270 mw with an estimated cost of approximately $1 billion, over half of which is expected to be incurred in 2016.
[7]Consists of capital expenditures that have received applicable internal approvals. NextEra Energy Resources plans to add natural gas infrastructure projects at a total cost of approximately $400 million to $600 million in 2010 through 2014.
[8]Consists of capital expenditures that have received applicable internal approvals and includes AFUDC of approximately $5 million, $42 million and $14 million in 2011 to 2013, respectively.