Rate Matters and Regulation
9 Months Ended
Sep. 30, 2012
Regulated Operations [Abstract]  
Rate Matters and Regulation
Rate Matters and Regulation

Except as set forth below, the circumstances set forth in Note 13 to OG&E's Financial Statements included in OG&E's 2011 Form 10-K appropriately represent, in all material respects, the current status of OG&E's regulatory matters.
Completed Regulatory Matters

Contract and Wind Energy Purchase Agreement Filing

On December 1, 2011, OG&E filed an application with the OCC requesting approval of a 20-year agreement that is intended to provide wind power to help meet the current and future power generation needs of Oklahoma State University. The project calls for OG&E to contract with NextEra Energy to build a 60 megawatt wind farm near Blackwell, Oklahoma, to support the Oklahoma State University project in which NextEra Energy will build, own and operate the wind farm and OG&E will purchase the electric output. The wind farm is expected to be in service by the end of 2012. On February 22, 2012, OG&E, the Attorney General and the Public Utility Division of the OCC signed a settlement agreement whereby the stipulating parties requested that the OCC issue an order approving the agreement for electric service with Oklahoma State University. On March 12, 2012, OG&E received an order from the OCC approving the settlement agreement. Pursuant to the terms of the power purchase agreement between OG&E and NextEra Energy, OG&E will purchase the electric output of the wind farm and use that power to provide service to Oklahoma State University and its other retail customers.

SPP Transmission Projects

In 2007, the SPP notified OG&E to construct 44 miles of a new 345 kilovolt transmission line originating at OG&E's existing Sooner 345 kilovolt substation and proceeding generally in a northerly direction to the Oklahoma/Kansas Stateline (referred to as the Sooner-Rose Hill project). At the Oklahoma/Kansas Stateline, the line connects to the companion line constructed in Kansas by Westar Energy. The transmission line was placed in service in April 2012. The total capital expenditures associated with this project were $45 million.

In January 2009, OG&E received notification from the SPP to begin construction on 50 miles of a new 345 kilovolt transmission line and substation upgrades at OG&E's Sunnyside substation, among other projects. In April 2009, Western Farmers Electric Cooperative assigned to OG&E the construction of 50 miles of line designated by the SPP to be built by Western Farmers Electric Cooperative.  The new line extends from OG&E's Sunnyside substation near Ardmore, Oklahoma, 123.5 miles to the Hugo substation owned by Western Farmers Electric Cooperative near Hugo, Oklahoma.  The transmission line was completed in April 2012. The total capital expenditures associated with this project were $157 million.

As discussed below, the OCC approved a settlement agreement in OG&E's 2011 Oklahoma rate case filing that included an expedited procedure for recovering the costs of the two projects.  On July 31, 2012, OG&E filed an application with the OCC requesting an order authorizing recovery for the two projects through the SPP transmission systems additions rider. On October 2, 2012, all parties signed a settlement agreement in this matter which stated: (i) the parties agree not to oppose requested relief sought by OG&E, (ii) OG&E will host meetings to discuss the SPP’s transmission planning process, including any future transmission projects for which OG&E has received a notice to construct from the SPP, and (iii) there will be opportunities for parties to provide input related to transmission planning studies that the SPP performs to identify future transmission projects. On October 25, 2012, the OCC issued an order approving the settlement agreement and granting OG&E cost recovery for the two projects. OG&E initiated cost recovery beginning with the first billing cycle in November 2012.

2011 Oklahoma Rate Case Filing

As previously reported in OG&E's 2011 Form 10-K, on July 28, 2011, OG&E filed its application with the OCC requesting an annual rate increase of $73.3 million, or a 4.3 percent increase in its rates. OG&E requested a return on equity of 11.0 percent based on a common equity percentage of 53.0 percent. In its application, OG&E requested recovery of increases in its operating costs and to begin earning on approximately $500 million of new capital investments made on behalf of its Oklahoma customers during the previous two and one-half years. On July 2, 2012, OG&E and other parties associated with its rate increase reached a settlement agreement in this matter. Key terms of the settlement agreement include: (i) an annual net increase of approximately $4.3 million in OG&E's rates to its Oklahoma retail customers, (ii) OG&E's Oklahoma retail authorized return on equity will be 10.2 percent, (iii) the rate of return to be used under various recovery riders previously approved by the OCC, including riders for OG&E's smart grid implementation and Crossroads wind farm will be based on OG&E's actual debt and equity ratios as reflected in OG&E's application and a 10.2 percent return on equity, (iv) depreciation rates proposed by OG&E will be implemented in the same month new customer rates go into effect, (v) the pension and postretirement medical cost tracker will remain in effect, (vi) a procedure was established to expedite the recovery of the cost of specified high-voltage transmission projects and (vii) extension of funding for OG&E's system hardening program. On July 9, 2012, the OCC issued an order approving the settlement agreement in this matter. OG&E expects the impact of the rate increase on its customers and service territory to be minimal as the rate increase will be more than offset by lower fuel costs attributable to prior fuel over recoveries from lower than forecasted fuel costs. OG&E implemented the new rates effective in early August.

Smart Grid Project

As previously reported, OG&E filed an application with the APSC requesting pre-approval for system-wide deployment of smart grid technology and a recovery rider, including a credit for the Smart Grid grant awarded by the U.S. Department of Energy under the American Recovery and Reinvestment Act of 2009. On August 3, 2011, the APSC issued an order in this matter approving the settlement agreement. On August 31, 2012, the APSC issued an order authorizing implementation of the rider beginning with the first billing cycle in September 2012 through December 2012.

Request for Prudence Determination and Waiver of Competitive Bid Rules for One-Year Extension of Enogex Gas Transportation and Storage Agreement

On August 9, 2012, OG&E filed an application with the OCC requesting: (i) an order finding that a one-year extension of OG&E's gas transportation and storage agreement with Enogex is prudent, (ii) a waiver of the OCC's competitive procurement rules and (iii) finding that the one-year extension of the gas transportation and storage agreement complies with the OCC's affiliate transaction rules. On September 14, 2012, OG&E filed a settlement agreement in which all parties to this matter agreed to the one-year extension of the Enogex contract and cost recovery from ratepayers at the rates currently in effect. On October 25, 2012, the OCC issued an order approving the settlement agreement.

Pending Regulatory Matters

Fuel Adjustment Clause Review for Calendar Year 2010

The OCC routinely reviews the costs recovered from customers through OG&E’s fuel adjustment clause. On August 19, 2011, the OCC Staff filed an application to review OG&E’s fuel adjustment clause for calendar year 2010, including the prudence of OG&E’s electric generation, purchased power and fuel procurement costs. OG&E responded by filing direct testimony and the minimum filing review package on October 18, 2011. On April 6, 2012 witnesses for the OCC Staff, the Oklahoma Attorney General and the Oklahoma Industrial Energy Consumers association filed responsive testimony. The witness for the Oklahoma Industrial Energy Consumers recommended that the OCC disallow recovery of approximately $44 million of costs previously recovered through OG&E’s fuel adjustment clause. These recommendations were based on allegations that OG&E’s lower cost coal-fired generation was underutilized, that OG&E failed to aggressively pursue purchasing power at a cost lower than its marginal cost of generation and that OG&E should be found imprudent related to an unplanned outage at OG&E's Sooner 2 coal unit in November and December 2010. The witnesses for the OCC Staff and the Oklahoma Attorney General recommended that OG&E should provide additional information to allow them to reach a conclusion on their prudence review. On May 8, 2012, OG&E filed rebuttal testimony supporting the appropriateness of OG&E's use of coal-fired generation during 2010, OG&E's practice regarding purchasing power and the appropriateness of OG&E's management actions related to the Sooner 2 outage. A hearing on the merits was conducted on July 17 and 18, 2012. The witness for the Oklahoma Attorney General offered no further testimony. The witness for the OCC Staff recommended approval of OG&E's actions related to utilization of coal plants and practices related to purchasing power but recommended that OG&E refund $3 million to customers because of the Sooner 2 outage. On September 26, 2012, the administrative law judge recommended that the OCC find that for the calendar year 2010 OG&E’s generation, purchase power and fuel procurement processes and costs, including the cost of replacement power for the Sooner 2 outage, were prudent and no disallowance for any of these expenses is warranted. A hearing in this matter is scheduled on November 8, 2012. OG&E expects to receive an order from the OCC in November 2012.

SPP Transmission Projects

On January 31, 2012, the SPP approved the Integrated Transmission Plan Near Term and Integrated Transmission Plan 10-year projects. These plans include two projects to be built by OG&E: (i) construction of 47 miles of transmission line from OG&E's Gracemont substation in a northwestern direction to a companion transmission line to be built by American Electric Power to its Elk City substation at an estimated cost of $75 million for OG&E, which is expected to be in service by early 2018, and (ii) construction of 126 miles of transmission line from OG&E's Woodward District Extra High Voltage substation in a southeastern direction to OG&E's Cimarron substation and construction of a new substation on this transmission line, the Mathewson substation, at an estimated cost of $210 million for OG&E, which is expected to be in service by early 2021. On April 9, 2012, OG&E received a notice to construct these projects from the SPP. On June 26, 2012, OG&E responded to the SPP that OG&E will construct the projects discussed above and is moving forward with more detailed cost estimates that must be reviewed and approved by the SPP.

Market-Based Rate Authority
On June 29, 2012, OG&E filed its triennial market power update with the FERC to retain its market-based rate authorization in the SPP's energy imbalance service market but to surrender its market-based rate authorization for any market-based rate sales outside the SPP's energy imbalance service market. A FERC order is pending.

Fuel Adjustment Clause Review for Calendar Year 2011

On July 31, 2012, the OCC Staff filed an application for a public hearing to review and monitor OG&E's application of the 2011 fuel adjustment clause. OG&E filed the necessary information and documents needed to satisfy the OCC's minimum filing requirement rules on October 1, 2012. A procedural schedule has not been established in this matter.

Crossroads Wind Farm

As previously reported, OG&E signed memoranda of understanding in February 2010 for approximately 197.8 megawatts of wind turbine generators and certain related balance of plant engineering, procurement and construction services associated with the Crossroads wind farm. On August 31, 2012, OG&E filed an application with the APSC requesting approval to recover the Arkansas portion of the costs of the Crossroads wind farm through a rider until such costs are included in OG&E's base rates as part of its next general rate proceeding. A hearing in this matter is scheduled to begin January 18, 2013. The OCC had previously authorized recovery of the Oklahoma portion of these costs.