Rate Matters and Regulation
3 Months Ended
Mar. 31, 2012
Regulated Operations [Abstract]  
Rate Matters and Regulation
Rate Matters and Regulation

Except as set forth below, the circumstances set forth in Note 13 to OG&E's Financial Statements included in OG&E's 2011 Form 10-K appropriately represent, in all material respects, the current status of any regulatory matters.

Completed Regulatory Matters

Contract and Wind Energy Purchase Agreement Filing

On December 1, 2011, OG&E filed an application with the OCC requesting approval of a 20-year agreement that is intended to provide wind power to help meet the current and future power generation needs of Oklahoma State University. The project calls for OG&E to contract with NextEra Energy to build a 60 MW wind farm near Blackwell, Oklahoma, to support the Oklahoma State University project in which NextEra Energy will build, own and operate the wind farm and OG&E will purchase the electric output. The wind farm is expected to be in service by the end of 2012. On February 22, 2012, OG&E, the Attorney General and the Public Utility Division of the OCC signed a settlement agreement whereby the stipulating parties requested that the OCC issue an order approving the agreement for electric service with Oklahoma State University. On March 12, 2012, OG&E received an order from the OCC approving the settlement agreement. Pursuant to the terms of the power purchase agreement between OG&E and NextEra Energy, OG&E will purchase the electric output of the wind farm and use that power to provide service to Oklahoma State University.

Southwest Power Pool Transmission/Substation Projects

In 2007, the Southwest Power Pool notified OG&E to construct 44 miles of a new 345 kilovolt transmission line originating at OG&E's existing Sooner 345 kilovolt substation and proceeding generally in a northerly direction to the Oklahoma/Kansas Stateline (referred to as the Sooner-Rose Hill project). At the Oklahoma/Kansas Stateline, the line connects to the companion line constructed in Kansas by Westar Energy. The transmission line was placed in service in April 2012. The total capital expenditures associated with this project were $45 million.

In January 2009, OG&E received notification from the Southwest Power Pool to begin construction on 50 miles of a new 345 kilovolt transmission line and substation upgrades at OG&E's Sunnyside substation, among other projects. In April 2009, Western Farmers Electric Cooperative assigned to OG&E the construction of 50 miles of line designated by the Southwest Power Pool to be built by Western Farmers Electric Cooperative.  The new line extends from OG&E's Sunnyside substation near Ardmore, Oklahoma, 123.5 miles to the Hugo substation owned by Western Farmers Electric Cooperative near Hugo, Oklahoma.  The transmission line was completed in April 2012. The total capital expenditures associated with this project were $157 million.
Pending Regulatory Matters

2011 Oklahoma Rate Case Filing

As previously reported in OG&E's 2011 Form 10-K, on July 28, 2011, OG&E filed its application with the OCC requesting an annual rate increase of $73.3 million, or a 4.3 percent increase in its rates. OG&E is requesting a return on equity of 11.0 percent based on a common equity percentage of 53 percent. Each 0.10 percent change in the requested return on equity affects the requested rate increase by $3.0 million. In its application, OG&E seeks to recover increases in its operating costs and to begin earning on approximately $500 million of new capital investments made on behalf of its Oklahoma customers during the previous two and one-half years. On November 9, 2011, the OCC Staff recommended a $6.2 million annual rate decrease based on a return on equity of 9.81 percent and a common equity percentage of 53 percent. The staff of the Oklahoma Attorney General recommended a return on equity of 9.818 percent and a common equity percentage of 49.5 percent. The staff of the Oklahoma Attorney General did not recommend a specific revenue requirement, but OG&E believes that adoption of the staff of the Oklahoma Attorney General's recommendations would result in a rate decrease. The Oklahoma Industrial Electric Consumers recommended a $56 million annual rate decrease based on a return on equity of 9.5 percent and a common equity percentage of 48 percent. OG&E filed rebuttal testimony on November 29, 2011 on the revenue requirement testimony filed by the parties on November 9, 2011. On November 16, 2011, the parties filed cost-of-service and rate design testimony and OG&E filed rebuttal testimony in those areas on December 2, 2011. The hearing in this matter began on December 13, 2011 and discussions have continued throughout the first quarter of 2012. Currently, OG&E and the other parties to this matter are waiting on the recommendation from the administrative law judge. There is no statutory deadline for the administrative law judge to make the recommendation in this matter. After the administrative law judge makes the recommendation in this matter, OG&E expects to receive a final order from the OCC.

Fuel Adjustment Clause Review for Calendar Year 2010

The OCC routinely reviews the costs recovered from customers through OG&E’s fuel adjustment clause. On August 19, 2011, the OCC Staff filed an application to review OG&E’s fuel adjustment clause for calendar year 2010, including the prudence of OG&E’s electric generation, purchased power and fuel procurement costs. OG&E responded by filing direct testimony and the minimum filing review package on October 18, 2011. On April 6, 2012 witnesses for the OCC Staff, the Oklahoma Attorney General and the Oklahoma Industrial Energy Consumers association filed responsive testimony. The witness for the Oklahoma Industrial Energy Consumers recommended that the OCC disallow recovery of approximately $44 million of costs previously recovered through OG&E’s fuel adjustment clause. These recommendations were based on allegations that OG&E’s lower cost coal-fired generation was underutilized and that OG&E failed to aggressively pursue purchasing power at a cost lower than its marginal cost of generation. OG&E’s rebuttal testimony will be filed by May 8, 2012 and the hearing on the merits is scheduled to begin on June 21, 2012. The witnesses for the OCC Staff and the Oklahoma Attorney General recommended that OG&E should provide additional information to allow them to reach a conclusion on their prudence review. OG&E believes that the recommendations of the witness for the Oklahoma Industrial Energy Consumers are without merit.