XML 49 R36.htm IDEA: XBRL DOCUMENT v3.23.3
COMMITMENTS AND CONTINGENCIES (Tables)
9 Months Ended
Sep. 30, 2023
Commitments and Contingencies Disclosure [Abstract]  
Schedule of Future Obligation under Transportation Agreements As of September 30, 2023, future payments under non-cancelable firm transportation and gathering agreements were as follows:
Payments Due by Period
(in millions)TotalLess than 1
Year
1 to 3 Years3 to 5 Years5 to 8 YearsMore than 8
Years
Infrastructure currently in service$8,454 $955 $1,979 $1,768 $1,796 $1,956 
Pending regulatory approval and/or construction (1) 
1,239 46 187 217 322 467 
Total transportation charges$9,693 $1,001 $2,166 $1,985 $2,118 $2,423 
            
(1)Based on estimated in-service dates as of September 30, 2023.