Included below is a discussion of various future commitments of the Company as of December 31, 2017. The commitments under these arrangements are not recorded in the accompanying consolidated balance sheets.
Drilling commitments – As of December 31, 2017, the Company has drilling rig contracts with various terms extending to February 2020 to ensure rig availability in its key operating areas. Future commitments as of December 31, 2017 total approximately $104 million, of which $73 million is expected to be incurred in 2018, $30 million in 2019 and $1 million in 2020. A portion of these future costs will be borne by other interest owners.
Transportation and processing commitments – The Company has entered into transportation and processing commitments to guarantee capacity on crude oil and natural gas pipelines and natural gas processing facilities. The commitments, which have varying terms extending as far as 2028, require the Company to pay per-unit transportation or processing charges regardless of the amount of capacity used. Future commitments remaining as of December 31, 2017 under the arrangements amount to approximately $1.43 billion, of which $197 million is expected to be incurred in 2018, $216 million in 2019, $186 million in 2020, $168 million in 2021, $166 million in 2022, and $497 million thereafter. A portion of these future costs will be borne by other interest owners. The Company is not committed under the above contracts to deliver fixed and determinable quantities of crude oil or natural gas in the future.
Litigation – In November 2010, a putative class action was filed in the District Court of Blaine County, Oklahoma by Billy J. Strack and Daniela A. Renner as trustees of certain named trusts and on behalf of other similarly situated parties against the Company. The Petition, as amended, alleged the Company improperly deducted post-production costs from royalties paid to plaintiffs and other royalty interest owners from crude oil and natural gas wells located in Oklahoma. The plaintiffs alleged a number of claims, including breach of contract, fraud, breach of fiduciary duty, unjust enrichment, and other claims and sought recovery of compensatory damages, interest, punitive damages and attorney fees on behalf of the proposed class. The Company denied all allegations and denied that the case was properly brought as a class action. On June 11, 2015, the trial court certified a “hybrid” class requested by plaintiffs over the objections of the Company. The Company appealed the trial court’s class certification order. On February 8, 2017, the Oklahoma Court of Civil Appeals reversed the trial court’s ruling on certification and remanded the case for further proceedings. The plaintiffs filed a Petition for Rehearing which was denied by the Oklahoma Court of Civil Appeals. Plaintiffs then filed a Petition for Writ of Certiorari on May 23, 2017 to the Oklahoma Supreme Court, which was denied on October 2, 2017. On October 10, 2017, Plaintiffs filed with the trial court a “Second Amended and Renewed Motion for Class Action Certification and Request that the Court to Set a Briefing Schedule Related to Class Certification.” During the litigation the Company was not able to estimate a reasonably possible loss or range of loss or what impact, if any, the ultimate resolution of the action would have on its financial condition, results of operations or cash flows due to the preliminary status of the matter, the complexity and number of legal and factual issues presented by the matter and uncertainties with respect to, among other things, the nature of the claims and defenses, the existence and the potential size of the class, the scope and types of the properties and agreements involved, the production years involved, and the ultimate potential outcome of the matter. The Company further disclosed that it was reasonably possible one or more events could occur in the near term that could impact the Company’s ability to estimate the potential effect of this matter if any, on its financial condition, results of operations or cash flows. During the litigation the Company also disclosed plaintiffs alleged underpayments in excess of $200 million as damages, which may increase with the passage of time, a majority of which would be comprised of interest. After certification of the case as a class action was reversed the parties continued settlement negotiations. Due to the uncertainty of and burdens of litigation, on February 16, 2018, the Company reached a settlement in connection with this matter. Under the settlement, if approved by the court, the Company will make payments and incur costs associated with the settlement of approximately $59.6 million. The Company has accrued a loss for such amount, which is included in “Accrued liabilities and other” on the consolidated balance sheets and “Litigation settlement” in the consolidated statements of comprehensive income (loss) as of and for the year ended December 31, 2017. The District Court of Garfield County, Oklahoma must approve the settlement.
The Company is involved in various other legal proceedings including, but not limited to, commercial disputes, claims from royalty and surface owners, property damage claims, personal injury claims, disputes with tax authorities and other matters. While the outcome of these legal matters cannot be predicted with certainty, the Company does not expect them to have a material effect on its financial condition, results of operations or cash flows. As of December 31, 2017 and 2016, the Company had recorded a liability in the consolidated balance sheets under the caption “Other noncurrent liabilities” of $7.6 million and $6.5 million, respectively, for various matters, none of which are believed to be individually significant.
Environmental risk – Due to the nature of the crude oil and natural gas business, the Company is exposed to possible environmental risks. The Company is not aware of any material environmental issues or claims.