Litigation and Environmental Matters
In the normal course of business, we are subject to various legal and regulatory proceedings. For such matters, we record liabilities when they are considered probable and estimable, based on currently available facts, our historical experience, and our estimates of the ultimate outcome or resolution of the liability in the future. While the outcome of these proceedings is uncertain and a loss in excess of the amount we have accrued is possible though not reasonably estimable, it is the opinion of management that any amounts exceeding the accruals will not have a material adverse impact on our financial position, results of operations or cash flows.
We maintain liability insurance for various risks associated with the operation of our natural gas pipelines and facilities, including for property damage and bodily injury. These liability insurance policies generally require us to be responsible for the first $1.0 million (self-insured retention) of each incident.
The National Transportation Safety Board (NTSB) is investigating an incident that occurred at a Dallas, Texas residence on February 23, 2018 that resulted in one fatality and injuries to four other residents. Together with the Railroad Commission of Texas and the Pipeline and Hazardous Materials Safety Administration, Atmos Energy is a party to the investigation and in that capacity is working closely with the NTSB to help determine the cause of this incident.
On March 29, 2018, a civil action was filed in Dallas, Texas against Atmos Energy in response to the February 23rd incident. The plaintiffs seek over $1.0 million in damages for, among with others, wrongful death and personal injury.
We are a party to various other litigation and environmental-related matters or claims that have arisen in the ordinary course of our business. While the results of such litigation and response actions to such environmental-related matters or claims cannot be predicted with certainty, we continue to believe the final outcome of such litigation and matters or claims will not have a material adverse effect on our financial condition, results of operations or cash flows.
Purchase Commitments
Our distribution divisions maintain supply contracts with several vendors that generally cover a period of up to one year. Commitments for estimated base gas volumes are established under these contracts on a monthly basis at contractually negotiated prices. Commitments for incremental daily purchases are made as necessary during the month in accordance with the terms of the individual contract.
Our Mid-Tex Division also maintains a limited number of long-term supply contracts to ensure a reliable source of gas for our customers in its service area, which obligate it to purchase specified volumes at prices indexed to natural gas hubs. At June 30, 2018, we were committed to purchase 53.6 Bcf within one year and 51.2 Bcf within two to three years under indexed contracts.
Regulatory Matters
Various regulatory agencies, including the SEC and the Commodities Futures Trading Commission, continue to adopt regulations implementing many of the provisions of the Dodd-Frank Act of 2010. We continue to enact new procedures and modify existing business practices and contractual arrangements to comply with such regulations.  Additional rulemakings are pending which we believe will result in new reporting and disclosure obligations. The costs associated with hedging certain risks inherent in our business may be further increased when these expected additional regulations are adopted.
As of June 30, 2018, formula rate mechanisms were pending regulatory approval in our Louisiana, Mid-Tex, Tennessee and West Texas service areas, infrastructure mechanisms were pending regulatory approval in our Mississippi service area and rate cases were pending regulatory approval in our Mid-Tex, Virginia and West Texas service areas. These regulatory proceedings are discussed in further detail below in Management’s Discussion and Analysis — Recent Ratemaking Developments. Additionally, as discussed in further detail in Note 6, all jurisdictions are addressing impacts of the TCJA.