Montana General Electric Rate Case

In September 2018, we filed an electric rate case with the Montana Public Service Commission (MPSC) requesting an annual increase to electric rates of approximately $34.9 million, which represents an approximate 6.6% increase in annual base revenues. Our request is based on a return on equity of 10.65% and an overall rate of return of 7.42% (except for Colstrip Unit 4, which the MPSC previously set for the life of the facility at a 10% return on equity and an 8.25% rate of return), based on approximately $2.35 billion of electric rate base and a capital structure of 51% debt and 49% equity.  

We also requested that approximately $13.8 million of the proposed rate increase be approved on an interim basis effective November 1, 2018. In March, 2019, the MPSC issued an order approving an increase in rates of approximately $10.5 million on an interim and refundable basis effective April 1, 2019. On April 5, 2019, we filed rebuttal testimony, which responded to intervenor testimony and included certain known and measurable adjustments. This testimony reflects a request for an annual increase of $30.7 million, an approximately $4.2 million reduction from our original request.

A hearing is scheduled to commence on May 13, 2019. Interim rates will remain in effect on a refundable basis until the MPSC issues a final order.

Montana QF Tariff Filing

Under the Public Utility Regulatory Policies Act, electric utilities are required, with certain exceptions, to purchase energy and capacity from independent power producers that are QFs. In May 2016, we filed an application for approval of a revised tariff for standard rates for small QFs (3 MW or less). In November 2017, the MPSC issued an order (QF Order) approving new rates that were substantially lower than the previous rates and reducing the maximum contract term from 25 to 15 years. In the QF Order, the MPSC also ordered that it would apply the same 15-year contract term to our future owned and contracted electric supply resources. We, as well as Cypress Creek Renewables, LLC, Vote Solar, and Montana Environmental Information Center (collectively, Vote Solar), sought judicial review of the QF Order before the Montana State District Court.

On April 2, 2019, the Montana State District Court (Court) reversed the MPSC’s decisions to reduce the contract term to 15 years and apply that term to our supply resources. In addition, the Court found that the MPSC approved rates were too low to reflect avoided cost and ordered the MPSC to provide new calculations to the Court within 20 days. While the Court's decision regarding application of maximum contract length to our future owned and contracted resources is consistent with our initial request for judicial review, we appealed the portion of the Court's decision to increase standard rates to the Montana Supreme Court. In addition, we filed a joint motion along with the MPSC and Montana Consumer Counsel to stay the requirement to provide calculations to the Court. Vote Solar filed a motion to amend the District Court’s decision to address inconsistencies in the order. Our QF purchased power expenses are tracked through the Power Cost and Credits Adjustment Mechanism (PCCAM), so any future increases in rates paid to QFs will be reflected through the application of that mechanism.

Cost Recovery Mechanisms

Montana Electric Tracker - We submitted electric tracker filings for recovery of supply costs for the 12-month periods ended June 30, 2016 and 2017, which are subject to a prudency review. The MPSC approved interim rates for these tracker periods, but has not established a schedule for adjudication of these filings.