XML 33 R20.htm IDEA: XBRL DOCUMENT v3.10.0.1
Environmental Matters
6 Months Ended
Jun. 30, 2018
Environmental Remediation Obligations [Abstract]  
Environmental Matters
14. ENVIRONMENTAL MATTERS

We own, or previously owned, properties that may require environmental remediation or action. We estimate the range of loss for environmental liabilities based on current remediation technology, enacted laws and regulations, industry experience gained at similar sites and an assessment of the probable level of involvement and financial condition of other potentially responsible parties (PRPs). When amounts are prudently expended related to site remediation, of those sites described herein, we have a recovery mechanism in place to collect 96.68% of remediation costs from Oregon customers, and we are allowed to defer environmental remediation costs allocated to customers in Washington annually until they are reviewed for prudence at a subsequent proceeding.

Our sites are subject to the remediation process prescribed by the Environmental Protection Agency (EPA) and the Oregon Department of Environmental Quality (ODEQ). The process begins with a remedial investigation (RI) to determine the nature and extent of contamination and then a risk assessment (RA) to establish whether the contamination at the site poses unacceptable risks to humans and the environment. Next, a feasibility study (FS) or an engineering evaluation/cost analysis (EE/CA) evaluates various remedial alternatives. It is at this point in the process when we are able to estimate a range of remediation costs and record a reasonable potential remediation liability, or make an adjustment to our existing liability. From this study, the regulatory agency selects a remedy and issues a Record of Decision (ROD). After a ROD is issued, we would seek to negotiate a consent decree or consent judgment for designing and implementing the remedy. We would have the ability to further refine estimates of remediation liabilities at that time.

Remediation may include treatment of contaminated media such as sediment, soil and groundwater, removal and disposal of media, institutional controls such as legal restrictions on future property use, or natural recovery. Following construction of the remedy, the EPA and ODEQ also have requirements for ongoing maintenance, monitoring and other post-remediation care that may continue for many years. Where appropriate and reasonably known, we will provide for these costs in our remediation liabilities described below.

Due to the numerous uncertainties surrounding the course of environmental remediation and the preliminary nature of several site investigations, in some cases, we may not be able to reasonably estimate the high end of the range of possible loss. In those cases, we have disclosed the nature of the possible loss and the fact that the high end of the range cannot be reasonably estimated where a range of potential loss is available. Unless there is an estimate within the range of possible losses that is more likely than other cost estimates within that range, we record the liability at the low end of this range. It is likely changes in these estimates and ranges will occur throughout the remediation process for each of these sites due to our continued evaluation and clarification concerning our responsibility, the complexity of environmental laws and regulations and the determination by regulators of remediation alternatives. In addition to remediation costs, we could also be subject to Natural Resource Damages (NRD) claims. We will assess the likelihood and probability of each claim and recognize a liability if deemed appropriate. Refer to "Other Portland Harbor" below.    

Environmental Sites
The following table summarizes information regarding liabilities related to environmental sites, which are recorded in other current liabilities and other noncurrent liabilities in the balance sheet:
 
 
Current Liabilities
 
Non-Current Liabilities
 
 
June 30,
 
December 31,
 
June 30,
 
December 31,
In thousands
 
2018
 
2017
 
2017
 
2018
 
2017
 
2017
Portland Harbor site:
 
 
 
 
 
 
 
 
 
 
 
 
Gasco/Siltronic Sediments
 
$
2,174

 
$
1,485

 
$
2,683

 
$
45,330

 
$
43,376

 
$
45,346

Other Portland Harbor
 
1,444

 
1,435

 
1,949

 
3,871

 
3,906

 
4,163

Gasco/Siltronic Upland site
 
9,947

 
9,441

 
13,422

 
45,578

 
49,319

 
47,835

Central Service Center site
 
25

 
31

 
25

 

 

 

Front Street site
 
906

 
829

 
1,009

 
10,683

 
10,788

 
10,757

Oregon Steel Mills
 

 

 

 
179

 
179

 
179

Total
 
$
14,496


$
13,221

 
$
19,088

 
$
105,641

 
$
107,568

 
$
108,280



PORTLAND HARBOR SITE. The Portland Harbor is an EPA listed Superfund site that is approximately 10 miles long on the Willamette River and is adjacent to NW Natural's Gasco uplands sites. We are one of over one hundred PRPs to the Superfund site. In January 2017, the EPA issued its Record of Decision, which selects the remedy for the clean-up of the Portland Harbor site (Portland Harbor ROD). The Portland Harbor ROD estimates the present value total cost at approximately $1.05 billion with an accuracy between -30% and +50% of actual costs.

Our potential liability is a portion of the costs of the remedy for the entire Portland Harbor Superfund site. The cost of that remedy is expected to be allocated among more than 100 PRPs. In addition, we are actively pursuing clarification and flexibility under the ROD in order to better understand our obligation under the clean-up. We are also participating in a non-binding allocation process with the other PRPs in an effort to resolve our potential liability. The Portland Harbor ROD does not provide any additional clarification around allocation of costs among PRPs and, as a result of issuance of the Portland Harbor ROD, we have not modified any of our recorded liabilities at this time.

We manage our liability related to the Superfund site as two distinct remediation projects, the Gasco/Siltronic Sediments and Other Portland Harbor projects.

Gasco/Siltronic Sediments. In 2009, NW Natural and Siltronic Corporation entered into a separate Administrative Order on Consent with the EPA to evaluate and design specific remedies for sediments adjacent to the Gasco uplands and Siltronic uplands sites. We submitted a draft EE/CA to the EPA in May 2012 to provide the estimated cost of potential remedial alternatives for this site. At this time, the estimated costs for the various sediment remedy alternatives in the draft EE/CA for the additional studies and design work needed before the cleanup can occur, and for regulatory oversight throughout the clean-up range from $47.5 million to $350 million. We have recorded a liability of $47.5 million for the sediment clean-up, which reflects the low end of the range. At this time, we believe sediments at this site represent the largest portion of our liability related to the Portland Harbor site discussed above. 

Other Portland Harbor. While we still believe liabilities associated with the Gasco/Siltronic sediments site represent our largest exposure, we do have other potential exposures associated with the Portland Harbor ROD, including NRD costs and harborwide clean-up costs (including downstream petroleum contamination), for which allocations among the PRPs have not yet been determined. 

The Company and other parties have signed a cooperative agreement with the Portland Harbor Natural Resource Trustee council to participate in a phased NRD assessment to estimate liabilities to support an early restoration-based settlement of NRD claims. One member of this Trustee council, the Yakama Nation, withdrew from the council in 2009, and in 2017, filed suit against the Company and 29 other parties seeking remedial costs and NRD assessment costs associated with the Portland Harbor, set forth in the complaint. The complaint seeks recovery of alleged costs totaling $0.3 million in connection with the selection of a remedial action for the Portland Harbor as well as declaratory judgment for unspecified future remedial action costs and for costs to assess the injury, loss or destruction of natural resources resulting from the release of hazardous substances at and from the Portland Harbor site. The Yakama Nation has filed two amended complaints addressing certain pleading defects and dismissing the State of Oregon. We have recorded a liability for NRD claims which is at the low end of the range of the potential liability; the high end of the range cannot be reasonably estimated at this time. The NRD liability is not included in the aforementioned range of costs provided in the Portland Harbor ROD.

GASCO UPLANDS SITE. A predecessor of NW Natural, Portland Gas and Coke Company, owned a former gas manufacturing plant that was closed in 1958 (Gasco site) and is adjacent to the Portland Harbor site described above. The Gasco site has been under investigation by us for environmental contamination under the ODEQ Voluntary Clean-Up Program (VCP). It is not included in the range of remedial costs for the Portland Harbor site noted above. We manage the Gasco site in two parts, the uplands portion and the groundwater source control action.

We submitted a revised Remedial Investigation Report for the uplands to ODEQ in May 2007. In March 2015, ODEQ approved the RA, enabling us to begin work on the FS in 2016. We have recognized a liability for the remediation of the uplands portion of the site which is at the low end of the range of potential liability; the high end of the range cannot be reasonably estimated at this time.

In September 2013, we completed construction of a groundwater source control system, including a water treatment station, at the Gasco site. We have estimated the cost associated with the ongoing operation of the system and have recognized a liability which is at the low end of the range of potential cost. We cannot estimate the high end of the range at this time due to the uncertainty associated with the duration of running the water treatment station, which is highly dependent on the remedy determined for both the upland portion as well as the final remedy for our Gasco sediment exposure.

OTHER SITES. In addition to those sites above, we have environmental exposures at three other sites: Central Service Center, Front Street and Oregon Steel Mills. We may have exposure at other sites that have not been identified at this time. Due to the uncertainty of the design of remediation, regulation, timing of the remediation and in the case of the Oregon Steel Mills site, pending litigation, liabilities for each of these sites have been recognized at their respective low end of the range of potential liability; the high end of the range could not be reasonably estimated at this time.
 
Central Service Center site. We are currently performing an environmental investigation of the property under ODEQ's Independent Cleanup Pathway. This site is on ODEQ's list of sites with confirmed releases of hazardous substances, and cleanup is necessary. 
 
Front Street site. The Front Street site was the former location of a gas manufacturing plant we operated (the former Portland Gas Manufacturing site, or PGM). At ODEQ’s request, we conducted a sediment and source control investigation and provided findings to ODEQ. In December 2015, we completed a FS on the former Portland Gas Manufacturing site. 

In July 2017, ODEQ issued the PGM ROD. The ROD specifies the selected remedy, which requires a combination of dredging, capping, treatment, and natural recovery. In addition, the selected remedy also requires institutional controls and long-term inspection and maintenance. We revised the liability in the second quarter of 2017 to incorporate the estimated undiscounted cost of approximately $10.5 million for the selected remedy. Further, we have recognized an additional liability of $1.1 million for additional studies and design costs as well as regulatory oversight throughout the clean-up. We plan to complete the remedial design in 2018 and expect to construct the remedy details during 2019.

Oregon Steel Mills site. Refer to the “Legal Proceedings,” below.
 
Site Remediation and Recovery Mechanism (SRRM)
We have an SRRM through which we track and have the ability to recover past deferred and future prudently incurred environmental remediation costs allocable to Oregon, subject to an earnings test, for those sites identified therein. See Note 15 in the 2017 Form 10-K for a description of the SRRM collection process.

The following table presents information regarding the total regulatory asset deferred:
 
 
June 30,
 
December 31,
In thousands
 
2018
 
2017
 
2017
Deferred costs and interest (1)
 
$
46,862

 
$
50,131

 
$
45,546

Accrued site liabilities (2)
 
119,712

 
120,485

 
126,950

Insurance proceeds and interest
 
(95,824
)
 
(99,884
)
 
(94,170
)
Total regulatory asset deferral(1)
 
$
70,750

 
$
70,732

 
$
78,326

Current regulatory assets(3)
 
5,594

 
6,724

 
6,198

Long-term regulatory assets(3)
 
65,156

 
64,008

 
72,128


(1)
Includes pre-review and post-review deferred costs, amounts currently in amortization, and interest, net of amounts collected from customers.
(2) 
Excludes 3.32% of the Front Street site liability, or $0.4 million in 2018 and $0.4 million in 2017, as the OPUC only allows recovery of 96.68% of costs for those sites allocable to Oregon, including those that historically served only Oregon customers.
(3) 
Environmental costs relate to specific sites approved for regulatory deferral by the OPUC and WUTC. In Oregon, we earn a carrying charge on cash amounts paid, whereas amounts accrued but not yet paid do not earn a carrying charge until expended. We also accrue a carrying charge on insurance proceeds for amounts owed to customers. In Washington, a carrying charge related to deferred amounts will be determined in a future proceeding. Current environmental costs represent remediation costs management expects to collect from customers in the next 12 months. Amounts included in this estimate are still subject to a prudence and earnings test review by the OPUC and do not include the $5.0 million tariff rider. The amounts allocable to Oregon are recoverable through utility rates, subject to an earnings test.

ENVIRONMENTAL EARNINGS TEST. To the extent the utility earns at or below its authorized Return on Equity (ROE), remediation expenses and interest in excess of the $5.0 million tariff rider and $5.0 million insurance proceeds are recoverable through the SRRM. To the extent the utility earns more than its authorized ROE in a year, the utility is required to cover environmental expenses and interest on expenses greater than the $10.0 million with those earnings that exceed its authorized ROE.

Under the 2015 Order, the OPUC stated they would revisit the deferral and amortization of future remediation expenses, as well as the treatment of remaining insurance proceeds three years from the original Order, or earlier if we gain greater certainty about our future remediation costs, to consider whether adjustments to the mechanism may be appropriate. As it has been three years from the 2015 Order, we filed an update with the OPUC in March 2018 and recommended no changes.

WASHINGTON DEFERRAL. In Washington, cost recovery and carrying charges on amounts deferred for costs associated with services provided to Washington customers will be determined in a future proceeding.

Legal Proceedings
NW Natural is subject to claims and litigation arising in the ordinary course of business. Although the final outcome of any of these legal proceedings cannot be predicted with certainty, including the matter described below, we do not expect that the ultimate disposition of any of these matters will have a material effect on our financial condition, results of operations or cash flows. See also Part II, Item 1, “Legal Proceedings".

OREGON STEEL MILLS SITE. See Note 15 in the 2017 Form 10-K.

For additional information regarding other commitments and contingencies, see Note 14 in the 2017 Form 10-K.