XML 82 R61.htm IDEA: XBRL DOCUMENT v3.3.1.900
Environmental Matters (Details) - USD ($)
12 Months Ended
Dec. 31, 2015
Dec. 31, 2014
Environmental Activity [Line Items]    
Remediation recovery percentage in Oregon 96.68%  
Loss Contingency Range Of Possible Loss Portland Harbor $791 million to $2.45 billion  
Portland Harbor Number Of Potentially Responsible Parties more than 100  
Loss Contingency Range Of Possible Loss Gasco Siltronic $44.9 million to $350 million  
Gasco Siltronic Sediments Project Liability $ 44,900,000.0  
Gasco Groundwater Source Control construction costs 19,000,000.0  
Gasco Groundwater Source Control Allocated Insurance Proceeds To Constructed Water Treatment Station 2,500,000  
Front Street liability for studies and design costs 1,300,000  
SRRM pre-tax regulatory disallowance 15,000,000  
Deferred environmental charges 95,000,000  
Interest disallowed on SRRM regulatory disallowance 2,800,000  
Oregon allocated insurance proceeds 93,000,000  
Deferred remediation expense to be collected 8,400,000  
Annual tariff rider collection 5,000,000  
Environmental Settlement Insurance Proceeds Received To Date 150,000,000  
Annual insurance proceeds to appy against remediation costs 5,000,000  
Insurance proceeds applied to prudently incurred remediation costs 53,200,000  
Environmental Regulatory Table [Abstract]    
Cash Paid for Environmental Sites 124,325,000 $ 113,740,000
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 16,931,000 15,384,000
Environmental Noncurrent Liabilities 108,095,000 80,123,000
Regulatory Assets, Current 69,178,000 68,562,000
Regulatory Assets, Noncurrent 370,711,000 368,908,000
Minimum [Member]    
Environmental Activity [Line Items]    
Front Street Remedial Costs 7,600,000  
Maximum [Member]    
Environmental Activity [Line Items]    
Front Street Remedial Costs 12,900,000  
Gasco Siltronic Sediments [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 2,229,000 1,767,000
Environmental Noncurrent Liabilities 42,641,000 38,019,000
Portland Harbor Other [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 1,972,000 1,934,000
Environmental Noncurrent Liabilities 5,073,000 4,338,000
Gasco Upland [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 10,599,000 9,535,000
Environmental Noncurrent Liabilities 52,117,000 37,117,000
Siltronic Upland [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 951,000 957,000
Environmental Noncurrent Liabilities 337,000 348,000
Central Service Center [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 25,000 171,000
Environmental Noncurrent Liabilities 0 0
Front Street [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 1,155,000 1,020,000
Environmental Noncurrent Liabilities 7,748,000 122,000
Oregon Steel Mills [Member]    
Accrual for Environmental Loss Contingencies [Abstract]    
Environmental Current Liabilities 0 0
Environmental Noncurrent Liabilities 179,000 179,000
Environmental Restoration Costs [Member]    
Environmental Regulatory Table [Abstract]    
Environmental Regulatory Assets Noncurrent [1] 85,854,000 58,859,000
Accrual for Environmental Loss Contingencies [Abstract]    
Regulatory Assets, Current [2],[3] 9,270,000 0
Regulatory Assets, Noncurrent [3] $ 76,584,000 $ 58,859,000
[1] Includes cash paid, remaining liability and interest, net of insurance reimbursement, amounts collected from customers, and amounts reclassified to utility plant for the water treatment station
[2] Current environmental costs represent remediation costs management expects to collect from customers in the next 12 months. Amounts included in this estimate are still subject to a prudence and earnings test review by the OPUC and do not include the $5 million base rate rider. The Oregon amounts are recoverable through utility rates, subject to an earnings test.
[3] Current environmental costs represent remediation costs management expects to collect from customers in the next 12 months. Amounts included in this estimate are still subject to a prudence and earnings test review by the OPUC and do not include the $5 million base rate rider. The amounts allocable to Oregon are recoverable through utility rates, subject to an earnings test. See Note 15.