XML 43 R12.htm IDEA: XBRL DOCUMENT v3.22.4
Property Plant and Equipment Property Plant and Equipment
12 Months Ended
Dec. 31, 2022
Property, Plant and Equipment [Abstract]  
Property, Plant and Equipment Disclosure
Major classes of property, plant and equipment
(Millions of Dollars)Dec. 31, 2022Dec. 31, 2021
Property, plant and equipment, net
Electric plant$49,639 $48,680 
Natural gas plant8,514 7,758 
Common and other property2,970 2,602 
Plant to be retired (a)
2,217 1,200 
CWIP2,124 1,969 
Total property, plant and equipment65,464 62,209 
Less accumulated depreciation(17,502)(17,060)
Nuclear fuel3,183 3,081 
Less accumulated amortization(2,892)(2,773)
Property, plant and equipment, net$48,253 $45,457 
(a)Amounts as of Dec. 31, 2021 include Sherco Units 1, 2 and 3 and A.S. King for NSP-Minnesota; Comanche Unit 1 and 2 and Craig Units 1 and 2 for PSCo; and Tolk and coal generation assets at Harrington pending facility gas conversion for SPS. Following the June 2022 approval of PSCo’s revised resource plan settlement, amounts as of Dec. 31, 2022 include the addition of Comanche Unit 3, Hayden Units 1 and 2 and coal generation assets at Pawnee pending facility gas conversion as well as the removal of Comanche Unit 1 that was retired in 2022. Amounts are presented net of accumulated depreciation.
Joint Ownership of Generation, Transmission and Gas Facilities
The utility subsidiaries’ jointly owned assets as of Dec. 31, 2022:
(Millions of Dollars, Except Percent Owned)Plant in ServiceAccumulated DepreciationPercent Owned
NSP-Minnesota
Electric generation:
Sherco Unit 3$623 $468 59 %
Sherco common facilities180 115 80 
Sherco substation59 
Electric transmission:
Grand Meadow11 50 
Huntley Wilmarth49 50 
CapX2020818 124 51 
Total NSP-Minnesota (a)
$1,686 $715 
(a)Projects additionally include $4 million in CWIP.
(Millions of Dollars, Except Percent Owned)Plant in ServiceAccumulated DepreciationPercent Owned
NSP-Wisconsin
Electric transmission:
La Crosse, WI to Madison, WI$177 $20 37 %
CapX2020166 34 80 
Total NSP-Wisconsin (a)
$343 $54 
(a)Projects additionally include $1 million in CWIP.
(Millions of Dollars, Except Percent Owned)Plant in ServiceAccumulated DepreciationPercent Owned
PSCo
Electric generation:
Hayden Unit 1$157 $99 76 %
Hayden Unit 2151 81 37 
Hayden common facilities42 29 53 
Craig Units 1 and 282 51 10 
Craig common facilities39 24 
Comanche Unit 3918 174 67 
Comanche common facilities28 82 
Electric transmission:
Transmission and other facilities186 72 Various
Gas transmission:
Rifle, CO to Avon, CO25 60 
Gas transmission compressor50 
Total PSCo (a)
$1,636 $544 
(a)Projects additionally include $10 million in CWIP.
Each company’s share of operating expenses and construction expenditures is included in the applicable utility accounts. Respective owners are responsible for providing their own financing.