Commitments and Contingencies, Environmental Contingencies - Site Contingencies (Details)
$ in Millions
12 Months Ended
Dec. 31, 2018
USD ($)
Dec. 31, 2017
USD ($)
Ashland MGP Site | NSP-Wisconsin    
Manufactured Gas Plant (MGP) Site [Abstract]    
Current Cost Estimate for Site Remediation $ 192  
Accrual for Environmental Loss Contingencies, Gross 27 $ 30
Estimated Amount Spent on Cleanup $ 165  
Approved Amortization Period for Recovery of Remediation Costs in Natural Gas Rates 10 years  
Carrying Cost Percentage to be Applied to Unamortized Regulatory Asset 3.00%  
Other MGP, Landfill, or Disposal Sites    
Manufactured Gas Plant (MGP) Site [Abstract]    
Number of Identified MGP, Landfill, or Disposal Sites Under Current Investigation and/or Remediation 12  
Accrual for Environmental Loss Contingencies $ 19 $ 9
Federal Coal Ash Regulation [Domain]    
Site Contingency [Line Items]    
Number of sites where regulated ash units will still be in operation at a specified date 9  
Federal Coal Ash Regulation [Domain] | PSCo    
Manufactured Gas Plant (MGP) Site [Abstract]    
Number of sites where statistically significant increases over established groundwater standards exist 2  
Federal Coal Ash Regulation [Domain] | NSP-Minnesota    
Site Contingency [Line Items]    
Estimated cost of construction of a new impoundment $ 6  
Number of impoundments where closure plans will be expedited 1