XML 52 R41.htm IDEA: XBRL DOCUMENT v3.7.0.1
Rate Matters, SPS (Details) - SPS
$ in Millions
1 Months Ended 12 Months Ended
Apr. 30, 2017
USD ($)
Feb. 28, 2017
USD ($)
Dec. 31, 2016
USD ($)
Nov. 30, 2016
USD ($)
MW
Sep. 30, 2016
USD ($)
Feb. 29, 2016
USD ($)
Jun. 30, 2015
USD ($)
Dec. 31, 2015
USD ($)
PUCT Proceeding - Appeal of the Texas 2015 Electric Rate Case Decision                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Revised Requested Rate Increase             $ 42.1  
PUCT Proceeding - Texas 2016 Electric Rate Case                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Revised Requested Rate Increase         $ 61.5      
Public Utilities, Requested Rate Increase (Decrease), Amount           $ 71.9    
Public Utilities, Requested Rate Increase (Decrease), Percentage           14.40%    
Public Utilities, Requested Return on Equity, Percentage           10.25%    
Public Utilities, Requested Rate Base, Amount           $ 1,700.0    
Public Utilities, Requested Equity Capital Structure, Percentage           53.97%    
Public Utilities, Revised requested rate increase, including rate case expenses         $ 65.5      
Public Utilities, Total Estimated Impact of Stipulation     $ 51.8          
Texas 2016 TCRF Application [Member]                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Requested Rate Increase (Decrease), Amount   $ 16.1            
Public Utilities, Requested Rate Increase (Decrease), Percentage   1.80%            
NMPRC Proceeding - New Mexico 2016 Electric Rate Case                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Requested Rate Increase (Decrease), Amount       $ 41.4        
Public Utilities, Requested Rate Increase (Decrease), Percentage       10.90%        
Public Utilities, Requested Return on Equity, Percentage       10.10%        
Public Utilities, Requested Rate Base, Amount       $ 832.0        
Public Utilities, Requested Equity Capital Structure, Percentage       53.97%        
Public Utilities, Future Decline in MW Sales from Certain Wholesale Customers included in Rate Case | MW       380        
Public Utilities, Capital Expenditures       $ 20.1        
Public Utilities, Changes in Allocator, Including Wholesale Load Reductions       11.5        
Public Utilities, Transmission Expenses       4.7        
Public Utilities, Depreciation, Including Adjustment of Tolk Service Life       3.6        
Public Utilities, Rate Case Expenses       1.1        
Public Utilities, Other net       0.4        
SPP Open Access Transmission Tariff Upgrade Costs                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Billed Charges For Transmission Service Upgrades       $ 12.8        
Public Utility Commission of Texas (PUCT) | PUCT Proceeding - Appeal of the Texas 2015 Electric Rate Case Decision                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Approved Rate Decrease, Net of Rate Case Expenses               $ 4.0
Southwest Power Pool (SPP) | SPP Open Access Transmission Tariff Upgrade Costs                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Length of Payment Period Requested, In Years         5 years      
Subsequent Event [Member] | PUCT Proceeding - Texas 2016 Electric Rate Case                
Public Utilities, General Disclosures [Line Items]                
Public Utilities, Mechanism Ensuring Recovery of Revenue Using Final Rates $ 13.8