XML 41 R24.htm IDEA: XBRL DOCUMENT v3.6.0.2
Commitments and Contingencies
12 Months Ended
Dec. 31, 2016
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments

Capital Commitments — Xcel Energy has made commitments in connection with a portion of its projected capital expenditures. Xcel Energy’s capital commitments primarily relate to the following major projects:

NSP-Minnesota Upper Midwest Wind Projects NSP-Minnesota has issued a RFP, seeking up to 1,500 MW of wind energy projects. The RFP requests both PPAs and build-own-transfer proposals. NSP-Minnesota has submitted a request to self-build 750 MW of this total.

PSCo Advanced Grid Intelligence and Security Initiative PSCo is pursuing projects to update and advance its electric distribution grid to increase reliability and security standards, meet customer expectations, offer additional customer choice and control over energy usage and implement new rate structures.

PSCo Rush Creek Wind Farm PSCo has gained approval to build, own and operate a 600 MW wind generation facility and proposed transmission line in Colorado.
PSCo Gas Transmission Integrity Management Programs PSCo is proactively identifying and addressing the safety and reliability of natural gas transmission pipelines. The pipeline integrity efforts include primarily pipeline assessment and maintenance projects.

PSCo Electric Distribution Integrity Management Programs PSCo is assessing aging infrastructure for distribution assets and replacing worn components to increase system performance.

SPS Transmission NTC SPS has accepted NTCs for several hundred miles of transmission line and related substation projects based on needs identified through SPP’s various planning processes, including those associated with economics, reliability, generator interconnection or the load addition processes. Most significant are the 345 KV transmission line from TUCO to Yoakum County to Hobbs Plant and the Hobbs Plant to China Draw 345 KV transmission line.

Fuel Contracts — Xcel Energy has entered into various long-term commitments for the purchase and delivery of a significant portion of its current coal, nuclear fuel and natural gas requirements. These contracts expire in various years between 2017 and 2060. Xcel Energy is required to pay additional amounts depending on actual quantities shipped under these agreements.

The estimated minimum purchases for Xcel Energy under these contracts as of Dec. 31, 2016 are as follows:
(Millions of Dollars)
 
Coal
 
Nuclear fuel
 
Natural gas supply
 
Natural gas
storage and
transportation
2017
 
$
707.6

 
$
113.2

 
$
395.6

 
$
252.0

2018
 
372.0

 
60.8

 
187.4

 
195.4

2019
 
102.7

 
111.1

 
181.4

 
155.1

2020
 
49.3

 
37.7

 
186.1

 
141.4

2021
 
50.4

 
90.2

 
193.3

 
132.9

Thereafter
 
295.1

 
449.5

 
172.0

 
1,108.8

Total
 
$
1,577.1

 
$
862.5

 
$
1,315.8

 
$
1,985.6



Additional expenditures for fuel and natural gas storage and transportation will be required to meet expected future electric generation and natural gas needs. Xcel Energy’s risk of loss, in the form of increased costs from market price changes in fuel, is mitigated through the use of natural gas and energy cost-rate adjustment mechanisms, which provide for pass-through of most fuel, storage and transportation costs to customers.

PPAs NSP Minnesota, PSCo and SPS have entered into PPAs with other utilities and energy suppliers with expiration dates through 2039 for purchased power to meet system load and energy requirements and meet operating reserve obligations. In general, these agreements provide for energy payments, based on actual energy delivered and capacity payments. Certain PPAs accounted for as executory contracts also contain minimum energy purchase commitments. Capacity and energy payments are typically contingent on the independent power producing entity meeting certain contract obligations, including plant availability requirements. Certain contractual payments are adjusted based on market indices. The effects of price adjustments on our financial results are mitigated through purchased energy cost recovery mechanisms.

Included in electric fuel and purchased power expenses for PPAs accounted for as executory contracts were payments for capacity of $190.6 million, $230.6 million and $229.8 million in 2016, 2015 and 2014, respectively. At Dec. 31, 2016, the estimated future payments for capacity and energy that the utility subsidiaries of Xcel Energy are obligated to purchase pursuant to these executory contracts, subject to availability, are as follows:
(Millions of Dollars)
 
Capacity
 
Energy (a)
2017
 
$
165.8

 
$
91.8

2018
 
130.2

 
93.2

2019
 
85.0

 
98.7

2020
 
69.4

 
105.4

2021
 
79.4

 
139.8

Thereafter
 
300.3

 
522.7

Total
 
$
830.1

 
$
1,051.6

(a) 
Excludes contingent energy payments for renewable energy PPAs.

Additional energy payments under these PPAs and PPAs accounted for as operating leases will be required to meet expected future electric demand.

Leases — Xcel Energy leases a variety of equipment and facilities used in the normal course of business. Three of these leases qualify as capital leases and are accounted for accordingly. The assets and liabilities at the inception of a capital lease are recorded at the lower of fair market value or the present value of future lease payments and are amortized over the term of the contract.

WYCO was formed as a joint venture with CIG to develop and lease natural gas pipeline, storage, and compression facilities. Xcel Energy Inc. has a 50 percent ownership interest in WYCO. WYCO generally leases its facilities to CIG, and CIG operates the facilities, providing natural gas storage services to PSCo under separate service agreements.

PSCo accounts for its Totem natural gas storage service arrangement with CIG as a capital lease. As a result, PSCo had $127.0 million and $132.9 million of capital lease obligations recorded for the arrangement as of Dec. 31, 2016 and 2015, respectively. Xcel Energy Inc. eliminates 50 percent of the capital lease obligation related to WYCO in the consolidated balance sheet along with an equal amount of Xcel Energy Inc.’s equity investment in WYCO.

PSCo records amortization for its capital leases as cost of natural gas sold and transported on the consolidated statements of income. Total amortization expenses under capital lease assets were approximately $8.1 million, $8.2 million and $7.2 million for 2016, 2015 and 2014, respectively. Following is a summary of property held under capital leases:
(Millions of Dollars)
 
Dec. 31, 2016
 
Dec. 31, 2015
Gas storage facilities
 
$
200.5

 
$
200.5

Gas pipeline
 
20.7

 
20.7

Property held under capital leases
 
221.2

 
221.2

Accumulated depreciation
 
(65.3
)
 
(57.2
)
Total property held under capital leases, net
 
$
155.9

 
$
164.0



The remainder of the leases, primarily for office space, railcars, generating facilities, natural gas pipeline transportation, vehicles, aircraft and power-operated equipment, are accounted for as operating leases. Total expenses under operating lease obligations for Xcel Energy were approximately $255.3 million, $265.3 million and $271.9 million for 2016, 2015 and 2014, respectively. These expenses include capacity payments for PPAs accounted for as operating leases of $216.4 million, $223.6 million and $228.2 million in 2016, 2015 and 2014, respectively, recorded to electric fuel and purchased power expenses.

Included in the future commitments under operating leases are estimated future capacity payments under PPAs that have been accounted for as operating leases in accordance with the applicable accounting guidance.

Future commitments under operating and capital leases are:
(Millions of Dollars)
 
Operating
Leases
 
        PPA (a) (b)
Operating
Leases
 
Total
Operating
Leases
 
Capital Leases
 
2017
 
$
25.2

 
$
212.3

 
$
237.5

 
$
15.1

 
2018
 
25.2

 
212.8

 
238.0

 
14.7

 
2019
 
29.7

 
230.6

 
260.3

 
14.5

 
2020
 
24.4

 
244.2

 
268.6

 
14.3

 
2021
 
23.5

 
246.6

 
270.1

 
13.7

 
Thereafter
 
170.1

 
1,919.4

 
2,089.5

 
245.0

 
Total minimum obligation
 
 
 
 
 
 
 
317.3

 
Interest component of obligation
 
 
 
 
 
 
 
(224.9
)
 
Present value of minimum obligation
 
 
 
 
 
 
 
$
92.4

(c) 
(a) 
Amounts do not include PPAs accounted for as executory contracts.
(b) 
PPA operating leases contractually expire through 2039.
(c) 
Future commitments exclude certain amounts related to Xcel Energy’s 50 percent ownership interest in WYCO.

Variable Interest Entities — The accounting guidance for consolidation of variable interest entities requires enterprises to consider the activities that most significantly impact an entity’s financial performance, and power to direct those activities, when determining whether an enterprise is a variable interest entity’s primary beneficiary.

PPAs Under certain PPAs, NSP-Minnesota, PSCo and SPS purchase power from independent power producing entities for which the utility subsidiaries are required to reimburse natural gas or biomass fuel costs, or to participate in tolling arrangements under which the utility subsidiaries procure the natural gas required to produce the energy that they purchase. In addition, certain solar PPAs provide the utility subsidiaries with an option to purchase emission allowances or sharing provisions related to production credits generated by the solar facility under contract. These specific PPAs create a variable interest in the independent power producing entity.

Xcel Energy has determined that certain independent power producing entities are variable interest entities. Xcel Energy is not subject to risk of loss from the operations of these entities, and no significant financial support has been, or is required to be provided other than contractual payments for energy and capacity set forth in the PPAs.

Xcel Energy has evaluated each of these variable interest entities for possible consolidation, including review of qualitative factors such as the length and terms of the contract, control over O&M, control over dispatch of electricity, historical and estimated future fuel and electricity prices, and financing activities. Xcel Energy has concluded that these entities are not required to be consolidated in its consolidated financial statements because it does not have the power to direct the activities that most significantly impact the entities’ economic performance. Xcel Energy’s utility subsidiaries had approximately 3,537 and 3,698 MW of capacity under long-term PPAs as of Dec. 31, 2016, and 2015, respectively, with entities that have been determined to be variable interest entities. These agreements have expiration dates through the year 2041.

Fuel Contracts — SPS purchases all of its coal requirements for its Harrington and Tolk electric generating stations from TUCO under contracts for those facilities that expire in December 2017. TUCO arranges for the purchase, receiving, transporting, unloading, handling, crushing, weighing, and delivery of coal to meet SPS’ requirements. TUCO is responsible for negotiating and administering contracts with coal suppliers, transporters and handlers.

No significant financial support has been, or is required to be provided to TUCO by SPS, other than contractual payments for delivered coal. However, the fuel contracts create a variable interest in TUCO due to SPS’ reimbursement of certain fuel procurement costs. SPS has determined that TUCO is a variable interest entity. SPS has concluded that it is not the primary beneficiary of TUCO because SPS does not have the power to direct the activities that most significantly impact TUCO’s economic performance.

Low-Income Housing Limited Partnerships — Eloigne and NSP-Wisconsin have entered into limited partnerships for the construction and operation of affordable rental housing developments which qualify for low-income housing tax credits. Xcel Energy Inc. has determined Eloigne and NSP-Wisconsin’s low-income housing limited partnerships to be variable interest entities primarily due to contractual arrangements within each limited partnership that establish sharing of ongoing voting control and profits and losses that does not consistently align with the partners’ proportional equity ownership. These limited partnerships are designed to qualify for low-income housing tax credits. Eloigne and NSP-Wisconsin generally receive a larger allocation of the tax credits than the general partners at inception of the arrangements. Xcel Energy Inc. has determined that Eloigne and NSP-Wisconsin have the power to direct the activities that most significantly impact these entities’ economic performance, and therefore Xcel Energy Inc. consolidates these limited partnerships in its consolidated financial statements.

Equity financing for these entities has been provided by Eloigne, NSP-Wisconsin and the general partner of each limited partnership. Xcel Energy’s risk of loss is limited to its capital contributions, adjusted for any distributions and its share of undistributed profits and losses; no significant additional financial support has been, or is required to be provided to the limited partnerships by Eloigne or NSP-Wisconsin. Mortgage-backed debt typically comprises the majority of the financing at inception of each limited partnership and is paid over the life of the limited partnership arrangement. Obligations of the limited partnerships are generally secured by the housing properties of each limited partnership, and the creditors of each limited partnership have no significant recourse to Xcel Energy Inc. or its subsidiaries. Likewise, the assets of the limited partnerships may only be used to settle obligations of the limited partnerships, and not those of Xcel Energy Inc. or its subsidiaries.

Amounts reflected in Xcel Energy’s consolidated balance sheets for the Eloigne and NSP-Wisconsin low-income housing limited partnerships include the following:
(Thousands of Dollars)
 
Dec. 31, 2016
 
Dec. 31, 2015
Current assets
 
$
7,102

 
$
6,274

Property, plant and equipment, net
 
49,638

 
51,480

Other noncurrent assets (a)
 
918

 
977

Total assets
 
$
57,658

 
$
58,731

 
 
 
 
 
Current liabilities
 
$
7,769

 
$
7,540

Mortgages and other long-term debt payable (a)
 
30,343

 
30,665

Other noncurrent liabilities
 
658

 
644

Total liabilities
 
$
38,770

 
$
38,849


(a) 
Amounts reflect the classification of debt issuance costs as a deduction from the carrying amount of the related debt. See Note 2, Accounting Pronouncements for more information on the adoption of ASU 2015-03.

Technology Agreements — Xcel Energy has a contract that extends through December 2019 with International Business Machines Corp. (IBM) for information technology services. The contract is cancelable at Xcel Energy’s option, although Xcel Energy would be obligated to pay 50 percent of the contract value for early termination. Xcel Energy capitalized or expensed $118.7 million, $109.5 million and $111.3 million associated with the IBM contract in 2016, 2015 and 2014, respectively.

Xcel Energy’s contract with Accenture for information technology services extends through December 2020. The contract is cancelable at Xcel Energy’s option, although there are financial penalties for early termination. Xcel Energy capitalized or expensed $34.6 million, $17.3 million and $27.3 million associated with the Accenture contract in 2016, 2015 and 2014, respectively.

Committed minimum payments under these obligations are as follows:
(Millions of Dollars)
 
IBM
Agreement
 
Accenture
Agreement
2017
 
$
31.6

 
$
10.0

2018
 
30.6

 
10.5

2019
 
30.5

 
10.7

2020
 

 
11.0

2021
 

 

Thereafter
 

 



Guarantees and Indemnifications

Xcel Energy Inc. and its subsidiaries provide guarantees and bond indemnities under specified agreements or transactions. The guarantees and bond indemnities issued by Xcel Energy Inc. guarantee payment or performance by its subsidiaries. As a result, Xcel Energy Inc.’s exposure under the guarantees and bond indemnities is based upon the net liability of the relevant subsidiary under the specified agreements or transactions. Most of the guarantees and bond indemnities issued by Xcel Energy Inc. and its subsidiaries limit the exposure to a maximum amount stated in the guarantees and bond indemnities. As of Dec. 31, 2016 and 2015, Xcel Energy Inc. and its subsidiaries had no assets held as collateral related to their guarantees, bond indemnities and indemnification agreements.

Guarantees and Surety Bonds

The following table presents guarantees and bond indemnities issued and outstanding as of Dec. 31, 2016:
(Millions of Dollars)
 
Guarantor
 
Guarantee
Amount
 
Current
Exposure
 
Triggering
Event
Guarantee of customer loans for the Farm Rewiring Program (a)
 
NSP-Wisconsin
 
$
1.0

 
$
0.1

 
(e) 
Guarantee of the indemnification obligations of Xcel Energy Services Inc. under the aircraft leases (b)
 
Xcel Energy Inc.
 
13.0

 

 
(f) 
Guarantee of residual value of assets under the Bank of Tokyo-Mitsubishi Capital Corporation Equipment Leasing Agreement (c)
 
NSP-Minnesota
 
4.8

 

 
(g) 
Total guarantees issued
 
 
 
$
18.8

 
$
0.1

 
 
Guarantee performance and payment of surety bonds for Xcel Energy Inc.’s utility subsidiaries (d)
 
Xcel Energy Inc.
 
$
43.0

 
(i) 
 
(h) 
(a) 
The term of this guarantee expires in 2020, which is the final scheduled repayment date for the loans. As of Dec. 31, 2016, no claims had been made by the lender.
(b) 
The terms of this guarantee expires in 2021 and 2023 when the associated leases expire.
(c) 
The term of this guarantee expires in 2019 when the associated lease expires.
(d) 
The surety bonds primarily relate to workers compensation benefits and utility projects. The workers compensation bonds are renewed annually and the project based bonds expire in conjunction with the completion of the related projects.
(e) 
The debtor becomes the subject of bankruptcy or other insolvency proceedings.
(f) 
Nonperformance and/or nonpayment.
(g) 
Actual fair value of leased assets is less than the guaranteed residual value amount at the end of the lease term.
(h) 
Failure of any one of Xcel Energy Inc.’s utility subsidiaries to perform under the agreement that is the subject of the relevant bond. In addition, per the indemnity agreement between Xcel Energy Inc. and the various surety companies, the surety companies have the discretion to demand that collateral be posted.
(i) 
Due to the magnitude of projects associated with the surety bonds, the total current exposure of this indemnification cannot be determined. Xcel Energy Inc. believes the exposure to be significantly less than the total amount of the outstanding bonds.

Indemnification Agreements

Xcel Energy Inc. and its subsidiaries provide indemnifications through contracts entered into in the normal course of business. These are primarily indemnifications against adverse litigation outcomes in connection with underwriting agreements, as well as breaches of representations and warranties, including corporate existence, transaction authorization and income tax matters with respect to assets sold. Xcel Energy Inc.’s and its subsidiaries’ obligations under these agreements may be limited in terms of duration and amount. The maximum potential amount of future payments under these indemnifications cannot be reasonably estimated as the obligated amounts of these indemnifications often are not explicitly stated.

Environmental Contingencies

Xcel Energy has been or is currently involved with the cleanup of contamination from certain hazardous substances at several sites. In many situations, the subsidiary involved believes it will recover some portion of these costs through insurance claims. Additionally, where applicable, the subsidiary involved is pursuing, or intends to pursue, recovery from other PRPs and through the regulated rate process. New and changing federal and state environmental mandates can also create added financial liabilities for Xcel Energy, which are normally recovered through the regulated rate process. To the extent any costs are not recovered through the options listed above, Xcel Energy would be required to recognize an expense.

Site Remediation Various federal and state environmental laws impose liability, without regard to the legality of the original conduct, where hazardous substances or other regulated materials have been released to the environment. Xcel Energy Inc.’s subsidiaries may sometimes pay all or a portion of the cost to remediate sites where past activities of their predecessors or other parties have caused environmental contamination. Environmental contingencies could arise from various situations, including sites of former MGPs operated by Xcel Energy Inc.’s subsidiaries or their predecessors, or other entities; and third-party sites, such as landfills, for which one or more of Xcel Energy Inc.’s subsidiaries are alleged to be a PRP that sent wastes to that site.

MGP Sites

Ashland MGP Site — NSP-Wisconsin has been named a PRP for contamination at a site in Ashland, Wis. The Ashland/Northern States Power Lakefront Superfund Site (the Site) includes NSP-Wisconsin property, previously operated as a MGP facility (the Upper Bluff), and two other properties: an adjacent city lakeshore park area (Kreher Park); and an area of Lake Superior’s Chequamegon Bay adjoining the park.

In 2012, under a settlement agreement with the EPA, NSP-Wisconsin agreed to remediate the Phase I Project Area (which includes the Upper Bluff and Kreher Park areas of the Site). The current cost estimate for the cleanup of the Phase I Project Area is approximately $72.4 million, of which approximately $56.7 million has been spent.

NSP-Wisconsin performed a wet dredge pilot study in the summer of 2016 and demonstrated that a wet dredge remedy can meet the performance standards for remediation of the Sediments. As a result, the EPA authorized NSP-Wisconsin to extend the wet dredge pilot to additional areas of the Site. In January 2017, under a settlement agreement with the EPA, NSP-Wisconsin agreed to remediate the Phase II Project Area (the Sediments). The settlement agreement was lodged with the U.S. District Court for the Western District of Wisconsin (District Court) in January 2017, and a 30-day public comment period lapsed in February 2017. If the settlement is timely approved by the District Court, NSP-Wisconsin anticipates a full scale wet dredge remedy of the Sediments will be performed in 2017, with restoration activities concluding in 2018.

At Dec. 31, 2016 and 2015, NSP-Wisconsin had recorded a total liability of $64.3 million and $94.4 million, respectively, for the entire site.

NSP-Wisconsin has deferred the unrecovered portion of the estimated Site remediation costs as a regulatory asset. The PSCW has consistently authorized NSP-Wisconsin rate recovery for all remediation costs incurred at the Site. In 2012, the PSCW agreed to allow NSP-Wisconsin to pre-collect certain costs, to amortize costs over a ten-year period and to apply a three percent carrying cost to the unamortized regulatory asset. In April 2016, NSP-Wisconsin filed a limited natural gas rate case for recovery of additional expenses associated with remediating the Site. In December 2016, the PSCW issued a written order approving the requested increase in annual recovery of MGP clean-up costs from $7.6 million in 2016 to $12.4 million in 2017.

Fargo, N.D. MGP Site — In May 2015, underground pipes, tars and impacted soils were discovered in a right-of-way in Fargo, N.D. that appeared to be associated with a former MGP operated by NSP-Minnesota or prior companies. NSP-Minnesota removed impacted soils and other materials from the right-of-way at that time and commenced an investigation of the historic MGP and adjacent properties (the Fargo MGP Site). Based on the investigation, NSP-Minnesota has recommended that targeted source removal of impacted soils and historic MGP infrastructure should be performed. The North Dakota Department of Health approved NSP-Minnesota’s proposed cleanup plan in January 2017. The timing and final scope of remediation is dependent on whether current property owners will agree to provide reasonable access to NSP-Minnesota to perform and implement the approved cleanup plan.

NSP-Minnesota has initiated insurance recovery litigation in North Dakota. The U.S. District Court for the District of North Dakota agreed to the parties’ request for a stay of the litigation until May 2017.

As of Dec. 31, 2016 and Dec. 31, 2015, NSP-Minnesota had recorded a liability of $11.3 million and $2.7 million, respectively, for the Fargo MGP Site, with the increase due to the remediation activities proposed by NSP-Minnesota. In December 2015, the NDPSC approved NSP-Minnesota’s request to defer costs associated with the Fargo MGP Site, resulting in deferral of all investigation and response costs with the exception of approximately 12 percent allocable to the Minnesota jurisdiction. Uncertainties related to the liability recognized include obtaining access to perform the approved remediation, final designs that will be developed to implement the approved cleanup plan and the potential for contributions from entities that may be identified as PRPs.

Other MGP Sites Xcel Energy is currently involved in investigating and/or remediating several other MGP sites where regulated materials may have been deposited. Xcel Energy has identified seven sites across all of its service territories where former MGP activities have or may have resulted in site contamination and are under current investigation and/or remediation. At some or all of these MGP sites, there are other parties that may have responsibility for some portion of any remediation. Xcel Energy anticipates that the majority of the remediation at these sites will continue through at least 2017. Xcel Energy had accrued $2.0 million and $2.1 million for all of these sites at Dec. 31, 2016 and 2015, respectively. There may be insurance recovery and/or recovery from other PRPs that will offset any costs incurred. Xcel Energy anticipates that any amounts spent will be fully recovered from customers.

Environmental Requirements

Water and Waste
Asbestos Removal — Some of Xcel Energy’s facilities contain asbestos. Most asbestos will remain undisturbed until the facilities that contain it are demolished or removed. Xcel Energy has recorded an estimate for final removal of the asbestos as an ARO. It may be necessary to remove some asbestos to perform maintenance or make improvements to other equipment. The cost of removing asbestos as part of other work is not expected to be material and is recorded as incurred as operating expenses for maintenance projects, capital expenditures for construction projects or removal costs for demolition projects.

Coal Ash Regulation — Xcel Energy’s operations are subject to federal and state laws that impose requirements for handling, storage, treatment and disposal of solid waste. In 2015, the EPA published a final rule regulating the management and disposal of coal combustion residuals (“CCR” or coal ash) as a nonhazardous waste. In December 2016, the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which includes provisions that allow the CCR rule to be implemented through a state or federal based permit program and that give the EPA direct enforcement authority.  Xcel Energy is in the process of evaluating whether the costs of implementing the CCR rule under the potential federal and/or state permit programs could have a material impact on the results of operations, financial position or cash flows.

In 2015, industry and environmental non-governmental organizations sought judicial review of the final CCR rule. In June 2016, the D.C. Circuit issued an order remanding and vacating certain elements of the rule as a result of partial settlements with these parties. A final court decision is anticipated in the first half of 2017. Until a final decision is reached in the case, it is uncertain whether the litigation or partial settlements will have any significant impact on results of operations, financial position or cash flows on Xcel Energy. Xcel Energy believes that these associated costs would be recoverable through regulatory mechanisms.

Federal Clean Water Act (CWA) Effluent Limitations Guidelines (ELG) — In 2015, the EPA issued a final ELG rule for power plants that use coal, natural gas, oil or nuclear materials as fuel and discharge treated effluent to surface waters as well as utility-owned landfills that receive coal combustion residuals.  Xcel Energy estimates that the capital cost to comply with the ELG rule for Colorado will range from $9 million to $21 million, and could change as Xcel Energy continues to assess alternate compliance technologies.  Xcel Energy is in the process of evaluating whether the costs of compliance at NSP-Minnesota and NSP-Wisconsin could have a material impact on the results of operations, financial position or cash flows. The anticipated costs of compliance with the final rule at SPS are not expected to have a material impact on the results of operations, financial position or cash flows. Xcel Energy believes that compliance costs would be recoverable through regulatory mechanisms.

Federal CWA Section 316(b) — Section 316(b) of the federal CWA requires the EPA to regulate cooling water intake structures to assure that these structures reflect the best technology available for minimizing adverse environmental impacts to aquatic species. The EPA published the final 316(b) rule in 2014. The rule prescribes technology for protecting fish that get stuck on plant intake screens (known as impingement) and describes a process for site-specific determinations by each state for sites that must protect the small aquatic organisms that pass through the intake screens into the plant cooling systems (known as entrainment). For Xcel Energy, these requirements will primarily impact plants within the NSP-Minnesota service territory. The timing of compliance with the requirements will vary from plant-to-plant since the new rule does not have a final compliance deadline. Xcel Energy estimates the likely cost for complying with impingement requirements may be incurred between 2017 and 2027 and is approximately $53 million with the majority needed for NSP-Minnesota. Xcel Energy believes at least six NSP-Minnesota plants and two NSP-Wisconsin plants could be required by state regulators to make improvements to reduce entrainment. The exact cost of the entrainment improvements is uncertain, but could be up to $192 million depending on the outcome of certain entrainment studies and cost-benefit analyses. Xcel Energy anticipates these costs will be fully recoverable in rates.

Federal CWA Waters of the United States Rule In June 2015, the EPA and the U.S. Army Corps of Engineers published a final rule that significantly expands the types of water bodies regulated under the CWA and broadens the scope of waters subject to federal jurisdiction. The expansion of the term “Waters of the U.S.” will subject more utility projects to federal CWA jurisdiction, thereby potentially delaying the siting of new generation projects, pipelines, transmission lines and distribution lines, as well as increasing project costs and expanding permitting and reporting requirements. In October 2015, the U.S. Court of Appeals for the Sixth Circuit issued a nationwide stay of the final rule and subsequently ruled that it, rather than the federal district courts, had jurisdiction over challenges to the rule.  In January 2017, the U.S. Supreme Court agreed to resolve the dispute as to which court should hear challenges to the rule. A ruling is expected by June 2017.

Air
GHG Emission Standard for Existing Sources (Clean Power Plan or CPP) — In 2015, a final rule was published by the EPA for GHG emission standards for existing power plants.  Under the rule, states were required to develop implementation plans by September 2016, with the possibility of an extension to September 2018, or submit to a federal plan for the state prepared by the EPA.  Among other things, the rule requires that state plans include enforceable measures to ensure emissions from existing power plants achieve the EPA’s state-specific interim (2022-2029) and final (2030 and thereafter) emission performance targets.  The CPP was challenged by multiple parties in the D.C. Circuit Court.  In January 2016, the D.C. Circuit Court denied requests to stay the effectiveness of the rule. In February 2016, the U.S. Supreme Court issued an order staying the final CPP rule. In September 2016, the D.C. Circuit Court heard oral arguments in the consolidated challenges to the CPP. The stay will remain in effect until the D.C. Circuit Court reaches its decision and the U.S. Supreme Court either declines to review the lower court’s decision or reaches a decision of its own. During the pendency of the stay, states are not required to submit implementation plans and the EPA will not enforce deadlines or issue a federal plan for any state. Several of the states served by Xcel Energy have suspended formal planning efforts, while others are continuing.

Xcel Energy has undertaken a number of initiatives that reduce GHG emissions and respond to state renewable and energy efficiency goals.  The CPP could require additional emission reductions in states in which Xcel Energy operates.  If state plans do not provide credit for the investments Xcel Energy has already made to reduce GHG emissions, or if they require additional initiatives or emission reductions, then their requirements would potentially impose additional substantial costs.  Until Xcel Energy has more information about SIPs or the EPA finalizes its proposed federal plan for the states that do not develop related plans, Xcel Energy cannot predict the costs of compliance with the final rule once it takes effect.  Xcel Energy believes compliance costs will be recoverable through regulatory mechanisms.  If Xcel Energy’s regulators do not allow recovery of all or a part of the cost of capital investment or the O&M costs incurred to comply with the CPP or cost recovery is not provided in a timely manner, it could have a material impact on results of operations, financial position or cash flows.

CSAPR — CSAPR addresses long range transport of PM and ozone by requiring reductions in SO2 and NOx from utilities in the eastern half of the United States using an emissions trading program. For Xcel Energy, the rule applies in Minnesota, Wisconsin and Texas.

CSAPR was adopted to address interstate emissions impacting downwind states’ attainment of the 1997 ozone NAAQS and the 1997 and 2006 particulate NAAQS. As the EPA revises NAAQS, it will consider whether to make any further reductions to CSAPR emission budgets and whether to change which states are included in the emissions trading program. In December 2015, the EPA proposed adjustments to CSAPR emission budgets which address attainment of the more stringent 2008 ozone NAAQS. In September 2016, the EPA adopted a final rule that reduced the ozone season emission budget for NOx in Texas by approximately 22 percent, which is expected to lead to increased costs to purchase emission allowances. In November 2016, the EPA proposed to remove Texas from the particle NAAQS program. If adopted as proposed, Texas would no longer be subject to the annual SO2 and NOx emission budgets under CSAPR. Xcel Energy does not anticipate these increased costs to purchase emission allowances will have a material impact on the results of operations, financial position or cash flows.

Regional Haze Rules — The regional haze program is designed to address widespread haze that results from emissions from a multitude of sources. The BART requirements of the EPA’s regional haze rules require the installation and operation of emission controls for industrial facilities emitting air pollutants that reduce visibility in national parks and wilderness areas. Under BART, regional haze plans identify facilities that will have to reduce SO2, NOx and PM emissions and set emission limits for those facilities. BART requirements can also be met through participation in interstate emission trading programs such as the CAIR and its successor, CSAPR. The regional haze plans developed by Minnesota and Colorado have been fully approved and are being implemented in those states. States are required to revise their plans every ten years. The next plans for Minnesota and Colorado will be due in 2021. Texas’ first regional haze plan is still undergoing federal review as described below.

Actions affecting Harrington Units: Texas developed a SIP that finds the CAIR equal to BART for EGUs. As a result, no additional controls beyond CAIR compliance would be required. In 2014, the EPA proposed to approve the BART portion of the SIP, with substitution of CSAPR compliance for Texas’ reliance on CAIR. In January 2016, the EPA adopted a final rule that defers its approval of CSAPR compliance as BART until the EPA considers further adjustments to CSAPR emission budgets under the D.C. Circuit Court’s remand of the Texas SO2 emission budgets. In June 2016, the EPA issued a memorandum which allows Texas to voluntarily adopt the CSAPR emission budgets limiting annual SO2 and NOx emissions and rely on those emission budgets to satisfy Texas’ BART obligations under the regional haze rules. The Texas Commission on Environmental Quality (TCEQ) has not utilized this option. The EPA then published a proposed rule in January 2017 that could have the effect of requiring installation of dry scrubbers to reduce SO2 emissions from Harrington Units 1 and 2. Investment costs associated with dry scrubbers for Harrington Units 1 and 2 could be approximately $400 million. The EPA’s deadline to issue a final BART rule for Texas is September 2017.

Actions affecting Tolk units: In January 2016, the EPA adopted a final rule establishing a federal implementation plan for the state of Texas, which imposed SO2 emission limitations that reflect the installation of dry scrubbers on Tolk Units 1 and 2, with compliance required by February 2021. Investment costs associated with dry scrubbers could be approximately $600 million. SPS appealed the EPA’s decision and requested a stay of the final rule. The Fifth Circuit granted the stay and decided that the Fifth Circuit is the appropriate venue for this case. The EPA sought a remand of its order and SPS and others have opposed the terms of that remand. A decision is expected in late 2017 or early 2018. It is likely that Texas and other affected entities including SPS would continue to challenge the determinations to date.  The new Administration has not yet taken any public position regarding its views of the proposed and final regional haze regulations affecting SPS facilities in Texas.  The risk of these controls being imposed along with the risk of investments to provide cooling water to Tolk have caused SPS to seek to decrease the remaining depreciable life of the Tolk units.

Implementation of the NAAQS for SO2 — The EPA adopted a more stringent NAAQS for SO2 in 2010. The EPA is requiring states to evaluate areas in three phases. The first phase includes areas near PSCo’s Pawnee plant and SPS’ Tolk and Harrington plants.  The Pawnee plant recently installed an SO2 scrubber and the Tolk and Harrington Plants utilize low sulfur coal to reduce SO2 emissions. In June 2016, the EPA issued final designations which found the area near the Tolk plant to be meeting the NAAQS and the areas near the Harrington and Pawnee plants as “unclassifiable.” The area near the Harrington plant is to be monitored for three years and a final designation is expected to be made by December 2020. It is anticipated that the area near the Pawnee plant will be able to show compliance with the NAAQS through air dispersion modeling performed by the Colorado Department of Public Health and Environment.

The areas near the remaining Xcel Energy power plants will be evaluated in the next designation phase, ending December 2017. The remaining plants, PSCo’s Comanche and Hayden plants along with NSP-Minnesota’s King and Sherco plants, utilize scrubbers to control SO2 emissions. NSP-Minnesota’s King plant demonstrated compliance with the SO2 NAAQS as part of their recent permit renewal. In late 2016, Xcel Energy submitted air dispersion modeling to the Colorado Department of Public Health and Environment, MPCA and the EPA which demonstrated that PSCo’s Comanche and Hayden plants as well as NSP-Minnesota’s Sherco plant comply with the NAAQS. If an area is designated nonattainment in 2020, the states will need to evaluate all SO2 sources in the area. The state would then submit an implementation plan, which would be due by 2022, designed to achieve the NAAQS by 2025. The TCEQ could require additional SO2 controls at Harrington as part of such a plan. Xcel Energy cannot evaluate the impacts until the designation of nonattainment areas is made and any required state plans are developed. Xcel Energy believes that should SO2 control systems be required or require upgrades for a plant, compliance costs or the costs of alternative cost-effective generation will be recoverable through regulatory mechanisms and therefore does not expect a material impact on results of operations, financial position or cash flows.

Revisions to the NAAQS for Ozone — In 2015, the EPA revised the NAAQS for ozone by lowering the eight-hour standard from 75 parts per billion (ppb) to 70 ppb. In areas where Xcel Energy operates, current monitored air quality concentrations comply with the new standard in the Twin Cities Metropolitan Area in Minnesota and meet the 70 ppb level in the Texas panhandle. In documents issued with the new standard, the EPA projects that both areas will meet the new standard. The Denver Metropolitan Area is currently not meeting the prior ozone standard and will therefore not meet the new, more stringent standard, however PSCo’s scheduled retirement of coal fired plants in Denver should help in any plan to mitigate non-attainment.

Asset Retirement Obligations

Recorded AROs — AROs have been recorded for property related to the following: electric production (nuclear, steam, wind, other and hydro), electric distribution and transmission, natural gas production, natural gas transmission and distribution, natural gas storage, thermal and general property. The electric production obligations include asbestos, ash-containment facilities, radiation sources, storage tanks, control panels and decommissioning. The asbestos recognition associated with electric production includes certain plants at NSP-Minnesota, NSP-Wisconsin, PSCo and SPS. NSP-Minnesota also recognized asbestos obligations for its general office building. AROs also have been recorded for NSP-Minnesota, NSP-Wisconsin, PSCo and SPS steam production related to ash-containment facilities such as bottom ash ponds, evaporation ponds and solid waste landfills. NSP-Minnesota and PSCo have also recorded AROs for the retirement and removal of assets at certain wind production facilities for which the land is leased and removal is required by contract.

Xcel Energy has recognized an ARO for the retirement costs of natural gas mains and lines at NSP-Minnesota, NSP-Wisconsin and PSCo and an ARO for the retirement of above ground gas gathering, extraction and wells related to gas storage facilities at PSCo. In addition, an ARO was recognized for the removal of electric transmission and distribution equipment at NSP-Minnesota, NSP-Wisconsin, PSCo and SPS, which consists of many small potential obligations associated with PCBs, mineral oil, storage tanks, lithium batteries, mercury and street lighting lamps. The electric and common general AROs include small obligations related to storage tanks, radiation sources and office buildings.

In April 2015, the EPA published the final rule regulating the management and disposal of coal combustion byproducts (e.g., coal ash) as a nonhazardous waste to the Federal Register. The rule became effective in October 2015. The estimated costs to comply with the final rule were incorporated into the cash flow revisions in 2015.

For the nuclear assets, the ARO is associated with the decommissioning of the NSP-Minnesota nuclear generating plants, Monticello and PI. See Note 14 for further discussion of nuclear obligations.

A reconciliation of Xcel Energy’s AROs for the years ended Dec. 31, 2016 and 2015 is as follows:
(Thousands of Dollars)
 
Beginning
Balance
Jan. 1, 2016
 
Liabilities
Recognized
 
Liabilities
Settled
 
Accretion
 
Cash Flow Revisions (b)
 
Ending
Balance
Dec. 31, 2016
Electric plant
 
 
 
 
 
 
 
 
 
 
 
 
Nuclear production decommissioning
 
$
2,141,024

 
$

 
$

 
$
108,298

 
$

 
$
2,249,322

Steam and other production ash containment
 
131,587

 

 
(6,271
)
 
4,913

 
(13,843
)
 
116,386

Steam and other production asbestos
 
84,491

 

 

 
4,054

 
(103
)
 
88,442

Wind production
 
71,646

 
17,305

(a) 

 
3,166

 
61

 
92,178

Electric distribution
 
13,187

 

 

 
485

 
6,451

 
20,123

Other
 
4,543

 
645

 
(29
)
 
176

 
(451
)
 
4,884

Natural gas plant
 
 
 
 
 
 
 
 
 
 
 
 
Gas transmission and distribution
 
155,933

 

 

 
6,368

 
42,483

 
204,784

Other
 
3,966

 
185

 

 
158

 

 
4,309

Common and other property
 
 
 
 
 
 
 
 
 
 
 
 
Common general plant asbestos
 
551

 

 

 
28

 

 
579

Common miscellaneous
 
1,634

 

 

 
57

 
(469
)
 
1,222

Total liability
 
$
2,608,562

 
$
18,135

 
$
(6,300
)
 
$
127,703

 
$
34,129

 
$
2,782,229

(a) 
The liability recognized relates to the NSP-Minnesota Courtenay Wind Farm which was placed in service during 2016.
(b) 
In 2016, AROs were revised for changes in estimated cash flows and the timing of those cash flows. Changes in the gas transmission and distribution AROs were mainly related to increased miles of gas mains.
The aggregate fair value of NSP-Minnesota’s legally restricted assets, for purposes of funding future nuclear decommissioning, was $1.9 billion as of Dec. 31, 2016, consisting of external investment funds.

(Thousands of Dollars)
 
Beginning
Balance
Jan. 1, 2015
 
Liabilities
Recognized
 
Liabilities
Settled
 
Accretion
 
Cash Flow Revisions (a)
 
Ending
Balance
Dec. 31, 2015 (b)
Electric plant
 
 
 
 
 
 
 
 
 
 
 
 
Nuclear production decommissioning
 
$
2,037,947

 
$

 
$

 
$
103,077

 
$

 
$
2,141,024

Steam and other production ash containment
 
127,600

 

 

 
4,746

 
(759
)
 
131,587

Steam and other production asbestos
 
69,698

 
3,875

 

 
3,670

 
7,248

 
84,491

Wind production
 
38,260

 
31,085

(a) 

 
1,778

 
523

 
71,646

Electric distribution
 
12,593

 

 

 
463

 
131

 
13,187

Other
 
4,605

 
127

 
(273
)
 
178

 
(94
)
 
4,543

Natural gas plant
 
 
 
 
 
 
 
 
 
 
 
 
Gas transmission and distribution
 
149,964

 

 

 
5,969

 

 
155,933

Other
 
3,925

 

 

 
155

 
(114
)
 
3,966

Common and other property
 
 
 
 
 
 
 
 
 
 
 
 
Common general plant asbestos
 
505

 

 

 
27

 
19

 
551

Common miscellaneous
 
1,534

 

 

 
56

 
44

 
1,634

Total liability
 
$
2,446,631

 
$
35,087

 
$
(273
)
 
$
120,119

 
$
6,998

 
$
2,608,562


(a) 
The liability recognized relates to the NSP-Minnesota Pleasant Valley and Border Wind Farms which were placed in service during 2015.
(b) 
In 2015, AROs were revised for changes in estimated cash flows and the timing of those cash flows. Changes in the asbestos AROs were mainly related to updated cost estimates.

The aggregate fair value of NSP-Minnesota’s legally restricted assets, for purposes of funding future nuclear decommissioning, was $1.7 billion as of Dec. 31, 2015, consisting of external investment funds.

Indeterminate AROs — Outside of the known and recorded asbestos AROs, other plants or buildings may contain asbestos due to the age of many of Xcel Energy’s facilities, but no confirmation or measurement of the amount of asbestos or cost of removal could be determined as of Dec. 31, 2016. Therefore, an ARO has not been recorded for these facilities.

Removal Costs — Xcel Energy records a regulatory liability for the plant removal costs of generation, transmission and distribution facilities of its utility subsidiaries that are recovered currently in rates. Generally, the accrual of future non-ARO removal obligations is not required. However, long-standing ratemaking practices approved by applicable state and federal regulatory commissions have allowed provisions for such costs in historical depreciation rates. These removal costs have accumulated over a number of years based on varying rates as authorized by the appropriate regulatory entities. Given the long time periods over which the amounts were accrued and the changing of rates over time, the utility subsidiaries have estimated the amount of removal costs accumulated through historic depreciation expense based on current factors used in the existing depreciation rates.

The accumulated balances by entity were as follows at Dec. 31:
(Millions of Dollars)
 
2016
 
2015
NSP-Minnesota
 
$
419

 
$
430

PSCo
 
367

 
364

SPS
 
209

 
204

NSP-Wisconsin
 
140

 
132

Total Xcel Energy
 
$
1,135

 
$
1,130



Nuclear Insurance

On Dec. 31, 2016, NSP-Minnesota’s public liability for claims resulting from any nuclear incident was limited to $13.4 billion under the Price-Anderson amendment to the Atomic Energy Act. NSP-Minnesota had secured $375 million of coverage for its public liability exposure with a pool of insurance companies. The remaining $13.0 billion of exposure was funded by the Secondary Financial Protection Program, available from assessments by the federal government in case of a nuclear accident. On Jan. 1, 2017, the available insurance limit was increased from $375 million to $450 million. This increase in limit occurs periodically and the Price-Anderson amendment to the Atomic Energy Act requires purchasing the full available limit. On Jan. 1, 2017 this $450 million limit was secured from the insurance pool. NSP-Minnesota is subject to assessments of up to $127.3 million per reactor per accident for each of its three licensed reactors, to be applied for public liability arising from a nuclear incident at any licensed nuclear facility in the United States. The maximum funding requirement is $19.0 million per reactor per incident during any one year. These maximum assessment amounts are both subject to inflation adjustment by the NRC and state premium taxes. The NRC’s last adjustment was effective September 2013.

NSP-Minnesota purchases insurance for property damage and site decontamination cleanup costs from Nuclear Electric Insurance Ltd. (NEIL). The coverage limits are $2.3 billion for each of NSP-Minnesota’s two nuclear plant sites. NEIL also provides business interruption insurance coverage, including the cost of replacement power obtained during certain prolonged accidental outages of nuclear generating units. Premiums are expensed over the policy term. All companies insured with NEIL are subject to retroactive premium adjustments if losses exceed accumulated reserve funds. Capital has been accumulated in the reserve funds of NEIL to the extent that NSP-Minnesota would have no exposure for retroactive premium assessments in case of a single incident under the business interruption and the property damage insurance coverage. However, in each calendar year, NSP-Minnesota could be subject to maximum assessments of approximately $19.8 million for business interruption insurance and $43.0 million for property damage insurance if losses exceed accumulated reserve funds.

Legal Contingencies

Xcel Energy is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss. For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on Xcel Energy’s financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.

Employment, Tort and Commercial Litigation

Pacific Northwest FERC Refund Proceeding — A complaint with the FERC posed that sales made in the Pacific Northwest in 2000 and 2001 through bilateral contracts were unjust and unreasonable under the Federal Power Act. The City of Seattle (the City) alleged between $34 million to $50 million in sales with PSCo were subject to refund. In 2003, the FERC terminated the proceeding, although it was later remanded back to the FERC in 2007 by the U.S. Court of Appeals for the Ninth Circuit (Ninth Circuit).

In May 2015, the FERC rejected the City’s claim that any of the sales made resulted in an excessive burden and concluded that the City failed to establish a causal link between any contracts and any claimed unlawful market activity. In February 2016, the City appealed this decision to the Ninth Circuit.

In October 2016, a settlement was reached that resolved all outstanding claims between and among the City and the respondents, including PSCo. Settlement terms required PSCo to pay the City $15,000 and the City to withdraw its pending appeal with the Ninth Circuit. These terms have been met, bringing this matter to a close.

Gas Trading Litigation — e prime, inc. (e prime) is a wholly owned subsidiary of Xcel Energy. e prime was in the business of natural gas trading and marketing, but has not engaged in natural gas trading or marketing activities since 2003.  Thirteen lawsuits were commenced against e prime and Xcel Energy (and NSP-Wisconsin, in two instances) between 2003 and 2009 alleging fraud and anticompetitive activities in conspiring to restrain the trade of natural gas and manipulate natural gas prices.

The cases were consolidated in U.S. District Court in Nevada. Five of the cases have since been settled and seven have been dismissed. One multi-district litigation (MDL) matter remains and it consists of a Colorado class (Breckenridge), a Wisconsin class (NSP-Wisconsin), a Kansas class, and two other cases identified as “Sinclair Oil” and “Farmland.” In November 2016, the MDL judge dismissed e prime and Xcel Energy from the Farmland lawsuit. Motions for summary judgment have been filed by defendants, including e prime, in all of the remaining lawsuits. Defendants have also filed briefs opposing plaintiffs’ motion for class certification.

The majority of the motions filed were argued to the court in January 2017. It is uncertain when the court will render a decision concerning these motions. Xcel Energy, NSP-Wisconsin and e prime have concluded that a loss is remote.

Line Extension Disputes — In December 2015, Development Recovery Company (DRC) filed a lawsuit in Denver State Court, stating PSCo failed to award proper allowances and refunds for line extensions to new developments pursuant to the terms of electric service agreements entered into by PSCo and various developers. The dispute involves assigned interests in those claims by over fifty developers. In May 2016, the district court granted PSCo’s motion to dismiss the lawsuit, concluding that jurisdiction over this dispute resides with the CPUC. In June 2016, DRC filed a notice of appeal. The matter has been fully briefed and plaintiff has requested oral arguments. DRC also brought a proceeding before the CPUC as assignee on behalf of two developers, Ryland Homes and Richmond Homes of Colorado. In March 2016, the ALJ issued an order rejecting DRC’s claims for additional allowances and refunds. In June 2016, the ALJ’s determination was approved by the CPUC. DRC did not file a request for reconsideration before the CPUC contesting the decision, but filed an appeal in Denver District Court in August 2016. DRC filed its brief in February 2017 and PSCo’s answer brief will be due March 2017.

PSCo has concluded that a loss is remote with respect to this matter as the service agreements were developed to implement CPUC approved tariffs and PSCo has complied with the tariff provisions. Also, if a loss were sustained, PSCo believes it would be allowed to recover these costs through traditional regulatory mechanisms. The amount or range in dispute is presently unknown and no accrual has been recorded for this matter.

Other Contingencies

See Note 12 for further discussion.