XML 122 R105.htm IDEA: XBRL DOCUMENT v3.6.0.2
Commitments and Contingencies, Environmental Contingencies - Site Contingencies (Details)
$ in Millions
1 Months Ended 12 Months Ended
Feb. 28, 2017
Dec. 31, 2016
USD ($)
Site
Dec. 31, 2016
USD ($)
Site
Dec. 31, 2015
USD ($)
Ashland MGP Site | NSP-Wisconsin        
Manufactured Gas Plant (MGP) Site [Abstract]        
Number of Properties Not Owned Included in Superfund Site | Site   2 2  
Accrual for Environmental Loss Contingencies, Gross   $ 64.3 $ 64.3 $ 94.4
Approved Amortization Period for Recovery of Remediation Costs in Natural Gas Rates     10 years  
Carrying Cost Percentage to be Applied to Unamortized Regulatory Asset     3.00%  
Ashland MGP Site Phase I Project Area [Member] | NSP-Wisconsin        
Manufactured Gas Plant (MGP) Site [Abstract]        
Accrual for Environmental Loss Contingencies, Gross   72.4 $ 72.4  
Estimated Amount Spent on Cleanup   56.7 56.7  
Fargo MGP Site | NSP-Minnesota        
Manufactured Gas Plant (MGP) Site [Abstract]        
Accrual for Environmental Loss Contingencies, Gross   11.3 $ 11.3 2.7
Percentage of Response Costs Allocable to the Minnesota Jurisdiction     12.00%  
Other MGP Sites        
Manufactured Gas Plant (MGP) Site [Abstract]        
Accrual for Environmental Loss Contingencies, Gross   $ 2.0 $ 2.0 $ 2.1
Number of Identified MGP Sites Under Current Investigation and/or Remediation   7 7  
PSCW Proceeding - Electric and Gas Rate Case 2016 - Gas Rates 2016 [Member] | Ashland MGP Site | NSP-Wisconsin        
Manufactured Gas Plant (MGP) Site [Abstract]        
Public Utilities, Approved Annual Recovery, For 2016, Collected Through Base Rates     $ 7.6  
PSCW Proceeding - Gas Rate Case 2017 - Gas Rates 2017 | Ashland MGP Site | NSP-Wisconsin        
Manufactured Gas Plant (MGP) Site [Abstract]        
Public Utilities, Approved Annual Recovery Collected Through Base Rates   $ 12.4    
Subsequent Event | Ashland MGP Site Phase II Project Area [Member] | NSP-Wisconsin        
Manufactured Gas Plant (MGP) Site [Abstract]        
Length of Public Comment Period that Lapsed 30 days