XML 64 R15.htm IDEA: XBRL DOCUMENT v2.4.0.8
Rate Matters
9 Months Ended
Sep. 30, 2014
Public Utilities, General Disclosures [Abstract]  
Rate Matters
Rate Matters

Except to the extent noted below, the circumstances set forth in Note 12 to the consolidated financial statements included in Xcel Energy Inc.’s Annual Report on Form 10-K for the year ended Dec. 31, 2013 appropriately represent, in all material respects, the current status of other rate matters, and are incorporated herein by reference.

NSP-Minnesota

Pending Regulatory Proceedings — Minnesota Public Utilities Commission (MPUC)

NSP Minnesota – Minnesota 2014 Multi-Year Electric Rate Case  In November 2013, NSP-Minnesota filed a two-year electric rate case with the MPUC. The rate case is based on a requested return on equity (ROE) of 10.25 percent, a 52.5 percent equity ratio, a 2014 average electric rate base of $6.67 billion and an additional average rate base of $412 million in 2015.

The NSP-Minnesota electric rate case initially reflected a requested increase in revenues of approximately $193 million or 6.9 percent in 2014 and an additional $98 million or 3.5 percent in 2015. The request includes a proposed rate moderation plan for 2014 and 2015. After reflecting interim rate adjustments, NSP-Minnesota requested a rate increase of $127 million or 4.6 percent in 2014 and an incremental rate increase of $164 million or 5.6 percent in 2015.

NSP-Minnesota’s moderation plan includes the acceleration of the eight-year amortization of the excess depreciation reserve and the use of expected funds from the U.S. Department of Energy (DOE) for settlement of certain claims. These DOE refunds would be in excess of amounts needed to fund NSP-Minnesota’s decommissioning expense. The interim rate adjustments are primarily associated with ROE, Monticello life cycle management (LCM)/extended power uprate (EPU) project costs and NSP-Minnesota’s request to amortize amounts associated with the canceled Prairie Island (PI) EPU project.

In December 2013, the MPUC approved interim rates of $127 million, effective Jan. 3, 2014, subject to refund. The MPUC determined that the costs of Sherco Unit 3 would be allowed in interim rates, and that NSP-Minnesota’s request to accelerate the depreciation reserve amortization was a permissible adjustment to its interim rate request.

In August 2014, the evidentiary hearing was completed. As a result of discussions between NSP-Minnesota and intervening parties, the outstanding issues were further narrowed and the following were agreed upon:
NSP-Minnesota and the Minnesota Department of Commerce (DOC) have agreed to true-up the sales forecast to 12 months of actual weather normalized sales for 2014.
NSP-Minnesota and the DOC agreed to a property tax adjustment of $9 million, based on an assumed 2014 property tax forecast of $141 million. The parties also agreed to a limited true-up mechanism in which NSP-Minnesota would recover actual 2014 property taxes up to $145 million.
NSP-Minnesota agreed with the Minnesota Chamber of Commerce recommendation regarding deferral of the 2014 Monticello EPU depreciation expense and amortization of the depreciation over the remaining life of the plant.

NSP-Minnesota revised its requested rate increase to $142.2 million for 2014 and to $106.0 million for 2015, for a total combined increase of $248.2 million.

The following table summarizes the DOC’s and NSP-Minnesota’s recommendations and includes the estimated impact of certain agreed-upon true-up adjustments:
2014 Rate Request (Millions of Dollars)
 
DOC
 
NSP-Minnesota
NSP-Minnesotas filed rate request
 
$
192.7

 
$
192.7

Sales forecast
 
(43.2
)
 
(15.8
)
ROE
 
(36.2
)
 

Monticello EPU cost recovery
 
(33.9
)
 

Monticello EPU depreciation deferral
 

 
(12.2
)
Property taxes
 
(9.0
)
 
(9.0
)
PI EPU
 
(5.1
)
 
(5.1
)
Health care, pension and other benefits
 
(11.4
)
 
(1.9
)
Other, net
 
(8.0
)
 
(6.5
)
Total recommendation 2014 unadjusted
 
$
45.9

 
$
142.2

Estimated true-up adjustments:
 
 
 
 
Sales forecast
 
$
18.3

 
$
(9.1
)
Property taxes
 
3.9

 
3.9

Total recommendation 2014 adjusted
 
$
68.1

 
$
137.0

2015 Rate Request (Millions of Dollars)
 
DOC
 
NSP-Minnesota
NSP-Minnesota’s filed rate request
 
$
98.5

 
$
98.5

Monticello EPU cost recovery
 
29.1

 

Monticello EPU cost disallowance (a)
 
(10.2
)
 

Excess depreciation reserve adjustment (b)
 
(22.7
)
 

Depreciation
 
(17.5
)
 

Monticello EPU depreciation deferral
 

 
1.6

Monticello EPU step increase
 

 
10.1

Property taxes
 
(3.3
)
 
(3.3
)
Production tax credits to be included in base rates
 
(11.1
)
 
(11.1
)
DOE settlement proceeds
 
10.1

 
10.1

Emission chemicals
 
(1.6
)
 
(1.6
)
Other, net
 
(4.8
)
 
1.7

Total recommendation 2015 step increase
 
$
66.5

 
$
106.0

 
 
 
 
 
Unadjusted cumulative total for 2014 and 2015 step increase
 
$
112.4

 
$
248.2

 
 
 
 
 
Estimated adjusted cumulative total for 2014 and 2015 step increase
 
$
134.6

 
$
243.0


(a) 
In July 2014, the DOC recommended a disallowance of recovery of approximately $71.5 million of project costs on a Minnesota jurisdictional basis. This equates to a total NSP System disallowance of approximately $94 million. This would reduce NSP-Minnesota’s revenue requirement by approximately $10.2 million in 2015.
(b) 
Adjustment is due to timing differences and/or methodology of accelerating amortization of the excess depreciation reserve over three years.

NSP-Minnesota’s revised rate request, moderation plan, interim rate adjustments and impacts on expenses are detailed below:
(Millions of Dollars)
 
2014
 
Percentage
Increase
 
2015
 
Percentage
Increase
Rebuttal pre-moderation deficiency
 
$
250.6

 
 
 
$
67.8

 
 
Evidentiary hearing adjustments
 
(27.3
)
 
 
 
11.0

 
 
Revised pre-moderation deficiency
 
223.3

 
 
 
78.8

 
 
Moderation plan:
 
 
 
 
 
 
 
 
  Excess depreciation reserve
 
(81.1
)
 
 
 
52.9

 
 
  DOE settlement proceeds
 

 
 
 
(25.7
)
 
 
Revised rate request
 
142.2

 
5.1%
 
106.0

 
3.8%
Interim rate adjustments
 
(65.3
)
 
 
 
65.3

 
 
PI EPU
 
4.8

 
 
 
(4.8
)
 
 
Revenue impact (a)
 
81.7

 
 
 
166.5

 
 
Excess depreciation reserve
 
81.1

 
 
 
(45.7
)
 
 
Sales forecast (b)
 
(9.1
)
 
 
 

 
 
DOE settlement proceeds
 

 
 
 
25.7

 
 
Estimated impact of request on operating income
 
$
153.7

 
 
 
$
146.5

 
 

(a) 
NSP-Minnesota’s total revenue for 2014 is capped at the interim rate level of $127 million and pre-tax operating income is capped at $208 million. This table demonstrates the impact of reducing NSP-Minnesota’s rebuttal request.
(b) 
NSP-Minnesota and the DOC have agreed to a sales true-up based on weather normalized sales for 2014, using standard weather coefficients. NSP-Minnesota periodically adjusts the coefficients in periods of extreme weather conditions to enhance weather impact estimates. As a result of the difference in the two methodologies, currently, approximately $9.1 million of revenue that NSP-Minnesota attributed to weather would be considered normal sales growth using the standard weather coefficients. The refund for the full year could vary from the estimate as of Sept. 30, 2014, depending on weather conditions.

NSP-Minnesota recorded a current regulatory liability representing the current best estimate of a refund obligation associated with interim rates as of Sept. 30, 2014.

The next step in the procedural schedule is expected to be the Administrative Law Judge (ALJ) Report on Dec. 26, 2014. The MPUC is expected to deliberate on March 26, 2015. A final MPUC order is anticipated in the second quarter of 2015.

NSP-Minnesota – Nuclear Project Prudence Investigation — In 2013, NSP-Minnesota completed the Monticello LCM/EPU project. The multi-year project extended the life of the facility and increased the capacity from 600 to 671 megawatts (MW). Monticello LCM/EPU project expenditures were approximately $665 million. Total capitalized costs were approximately $748 million, which includes allowance for funds used during construction (AFUDC). Project expenditures were initially estimated in 2008 at approximately $320 million, excluding AFUDC.

In 2013, the MPUC initiated an investigation to determine whether the final costs for the Monticello LCM/EPU project were prudent.

NSP-Minnesota filed a report to support the change and prudence of the incurred costs. The filing indicated the increase in costs was primarily attributable to three factors: (1) the original estimate was based on a high level conceptual design and the project scope increased as the actual conditions of the plant were incorporated into the design; (2) implementation difficulties, including the amount of work that occurred in confined and radioactive or electrically sensitive spaces and NSP-Minnesota’s and its vendors’ ability to attract and retain experienced workers; and (3) additional Nuclear Regulatory Commission (NRC) licensing related requests over the five-plus year application process.

The cost deviation is in line with similar nuclear upgrade projects undertaken by other utilities. In addition, the project remains economically beneficial to customers. NSP-Minnesota has received all necessary licenses from the NRC for the Monticello EPU, and has begun the process to comply with the license requirements for higher power levels, subject to NRC oversight and review. As part of the review process, in October 2014 NSP-Minnesota received approval for ascension to higher EPU levels which is expected to recommence during the fourth quarter.

In July 2014, the DOC filed testimony and recommended a disallowance of recovery of approximately $71.5 million of project costs on a Minnesota jurisdictional basis. This equates to a total NSP System disallowance of approximately $94 million.

The DOC’s recommendation indicated that although the combined LCM/EPU project is cost effective, NSP-Minnesota should have done a better job of estimating initial project costs of the investments required to achieve 71 MW of additional capacity (i.e., EPU costs) as opposed to investments required to extend the life of the plant. They asserted that approximately 85 percent of the total $665 million in costs were associated with project components required solely to achieve the EPU.

In August 2014, the Office of Attorney General (OAG) filed rebuttal testimony and recommended a disallowance of recovery of $321 million for the entire NSP System (based on a total capitalized cost of $748 million), and no return on $107 million. The recommended disallowance is primarily based on criticism of NSP-Minnesota’s management of the project.

NSP-Minnesota believes the costs of the project were prudent and its decisions and actions do not warrant a disallowance. NSP-Minnesota’s testimony is summarized as follows:
The plant is cost-effective for customers;
The project benefits include providing carbon-free generation through a life extension and uprate of the plant for an installed capacity of about $1,000 per kilowatt;
The DOC was incorrect in its analysis that 85 percent of the expenditures were associated with the uprate; and
NSP-Minnesota made prudent decisions based on the information available at the time the decisions were made.

The next steps in the procedural schedule are expected to be as follows:
Initial Briefs — Oct. 31, 2014;
Reply Briefs — Nov. 21, 2014;
ALJ Report — Dec. 31, 2014; and
MPUC Deliberation — March 6, 2015.

A final MPUC order is anticipated in the second quarter of 2015. The MPUC decision for the Monticello prudence review is expected to be reflected in the final results of NSP-Minnesota’s pending Minnesota 2014 Multi-Year electric rate case.

Electric, Purchased Gas and Resource Adjustment Clauses

NSP-Minnesota – Gas Utility Infrastructure Cost (GUIC) Rider — In August 2014, NSP-Minnesota filed a GUIC rider with the MPUC for approval to recover the cost of natural gas infrastructure investments in Minnesota to improve safety and reliability. Costs include funding for pipeline assessment and system upgrades in 2015 and beyond, as well as deferred costs from NSP-Minnesota’s existing sewer separation and pipeline integrity management programs. Sewer separation costs stem from the inspection of sewer lines and the redirection of gas pipes in the event their paths are in conflict. NSP-Minnesota is requesting recovery of approximately $14.9 million from Minnesota gas utility customers beginning Jan. 1, 2015, including $4.8 million of deferred sewer separation and integrity management costs which is the 2015 portion of a five year amortization. In October 2014, the DOC recommended approval of NSP-Minnesota’s request for recovery of the GUIC rider, using the capital structure and cost of capital proposed in the current electric case and a five year amortization period for the deferred costs. An MPUC decision is anticipated by the end of 2014.

Pending Regulatory Proceedings — South Dakota Public Utilities Commission (SDPUC)

NSP-Minnesota – South Dakota 2015 Electric Rate Case In June 2014, NSP-Minnesota filed a request with the SDPUC to increase South Dakota electric rates by $15.6 million annually, or 8.0 percent, effective Jan. 1, 2015. The request is based on a 2013 historic test year (HTY) adjusted for certain known and measurable changes for 2014 and 2015, a requested ROE of 10.25 percent, an average rate base of $433.2 million and an equity ratio of 53.86 percent. This request reflects NSP-Minnesota’s proposal to move recovery of approximately $9.0 million for certain Transmission Cost Recovery (TCR) rider and Infrastructure rider projects to base rates.

The major components of the request are as follows:
(Millions of Dollars)
 
Request
Nuclear investments and operating costs
 
$
13.4

Other production, transmission and distribution
 
5.0

Technology improvements
 
2.1

Pension and operating and maintenance (O&M) expenses
 
1.6

Wind generation facilities
 
1.4

Capital structure
 
1.1

Incremental increase to base rates
 
$
24.6

 
 
 
Infrastructure rider to be included in base rates
 
$
(8.4
)
TCR rider to be included in base rates
 
(0.6
)
Net request
 
$
15.6



At this time, the case is in the discovery phase and further procedure scheduling may be established during the fourth quarter of 2014. In November 2014, NSP-Minnesota plans to file a request with the SDPUC for interim rates, effective Jan. 1, 2015. Final rates are anticipated to be effective in the first quarter of 2015.

NSP-Wisconsin

Pending Regulatory Proceedings — Public Service Commission of Wisconsin (PSCW)

NSP-Wisconsin – Wisconsin 2015 Electric Rate Case — In May 2014, NSP-Wisconsin filed a request with the PSCW to increase electric rates by $20.6 million, or 3.2 percent, effective Jan. 1, 2015. The request is for the limited purpose of updating 2015 electric rates to reflect anticipated increases in the production and transmission fixed charges and the fuel and purchased power components of the interchange agreement with NSP-Minnesota. No changes are being requested to the capital structure or the 10.2 percent ROE authorized by the PSCW in the 2014 rate case. As part of an agreement with stakeholders to limit the size and scope of the case, NSP-Wisconsin also agreed to an earnings cap for 2015 only, in which 100 percent of the earnings above the authorized ROE would be refunded to customers.

In October 2014, the PSCW Staff filed their direct testimony and recommended an electric rate increase of $16.1 million, or 2.5 percent. The majority of the PSCW Staff’s adjustments are related to the fuel cost forecast, and are primarily the result of more recent data than was available at the time the initial filing was prepared last spring.

In October 2014, NSP-Wisconsin, the PSCW Staff and other parties reached an agreement that resolved all contested issues in the case and accepted the PSCW staff recommendation to increase NSP-Wisconsin’s electric rates by approximately $16.1 million, effective January 2015.

The major cost components of the requested increase and the PSCW Staff recommendation are summarized below:
(Millions of Dollars)
 
NSP-Wisconsin
Request
 
PSCW Staff Recommendation
Production and transmission fixed charges
 
$
28.1

 
$
26.4

Fuel and purchased power
 
13.9

 
11.1

Sub-Total
 
$
42.0

 
$
37.5

 
 
 
 
 
NSP-Minnesota transmission depreciation reserve
 
$
(16.2
)
 
$
(16.2
)
Monticello EPU deferral
 
(5.2
)
 
(5.2
)
Total
 
$
20.6

 
$
16.1



A final PSCW decision is anticipated by the end of 2014.

Pending Regulatory Proceedings — Federal Energy Regulatory Commission (FERC)

Midcontinent Independent System Operator, Inc. (MISO) ROE Complaint — In November 2013, a group of customers filed a complaint at the FERC against MISO transmission owners, including NSP-Minnesota and NSP-Wisconsin. The complaint argues for a reduction in the ROE applicable to transmission formula rates in the MISO region from 12.38 percent to 9.15 percent, a prohibition on capital structures in excess of 50 percent equity, and the removal of ROE adders (including those for regional transmission organization (RTO) membership and being an independent transmission company), effective Nov. 12, 2013.

In January 2014, Xcel Energy filed an answer to the complaint asserting that the 9.15 percent ROE would be unreasonable and that the complainants failed to demonstrate the NSP System equity capital structure was unreasonable. The MISO transmission owners separately answered the complaint, arguing the complaint should be dismissed.

In June 2014, the FERC issued an order in a different ROE proceeding adopting a new ROE methodology for electric utilities. The new ROE methodology requires electric utilities to use a two-step discounted cash flow analysis to estimate cost of equity that incorporates both short-term and long-term growth projections.

In October 2014, the FERC upheld the determination of the long term growth rate to be used together with a short term growth rate in its new ROE methodology. The FERC separately set the ROE complaint against the MISO transmission owners for settlement judge and hearing procedures, which are expected to begin later this year. The FERC directed parties to apply this methodology, but denied the complaints related to equity capital structures and ROE adders. The FERC established a Nov. 12, 2013 refund effective date. NSP-Minnesota recorded a current regulatory liability representing the current best estimate of a refund obligation associated with the new ROE as of Sept. 30, 2014. The new FERC ROE methodology is estimated to reduce transmission revenue, net of expense, between $5 million and $7 million annually for NSP-Minnesota and NSP-Wisconsin.

PSCo

Pending and Recently Concluded Regulatory Proceedings — CPUC

PSCo – Colorado 2014 Electric Rate Case In 2014, PSCo filed an electric rate case with the CPUC requesting an increase in annual revenue of approximately $136.0 million, or 4.83 percent. The requested 2015 rate increase reflects approximately $100.9 million for recovery of costs associated with the CACJA project. The case also requests the initiation of a CACJA rider for 2016 and 2017, which is anticipated to increase revenue recovery by approximately $34.2 million in 2016 and then decline to approximately $29.9 million in 2017. PSCo’s objective is to establish a multi-year regulatory plan that provides certainty for PSCo and its customers.

The rate filing is based on a 2015 test year, a requested ROE of 10.35 percent, an electric rate base of $6.39 billion and an equity ratio of 56 percent. As part of the filing, PSCo will transfer approximately $19.9 million from the transmission rider to base rates, which will not impact customer bills. The CACJA rider is projected to recover incremental investment and expenses, based on a comprehensive plan to retire certain coal plants, add pollution control equipment to other existing coal units and add natural gas generation. The CACJA project investment is expected to be completed by 2017.

The next steps in the procedural schedule are expected to be as follows:
Answer Testimony — Nov. 7, 2014;
Rebuttal Testimony — Dec. 17, 2014;
Evidentiary Hearing — Jan. 26 - Feb. 4, 2015;
Interim rates are scheduled to be effective on Feb. 13, 2015, subject to refund; and
A decision as well as implementation of final rates are anticipated in the second quarter of 2015.

PSCo – Manufacturer’s Sales Tax Refund PSCo defers 2012-2014 annual property taxes in excess of $76.7 million as part of its multi-year rate plan with the CPUC. To the extent that PSCo was successful in the manufacturer’s sales tax refund lawsuit against the Colorado Department of Revenue, PSCo was to credit such refunds first against certain legal fees, and then against the unamortized deferred property tax balance at the end of 2014.

On June 30, 2014, the Colorado Supreme Court ruled against PSCo’s claim that it was due refunds for the payment of sales taxes on purchases of certain equipment from December 1998 to December 2001. As a result of the adverse ruling, PSCo is required to reduce its 2014 property tax deferral by $10 million, as this amount will not be recovered in electric rates. This impact is reflected in PSCo’s pending electric rate case before the CPUC.

PSCo – Annual Electric Earnings Test — As part of an annual earnings test, PSCo must share with customers a portion of any annual earnings that exceed PSCo’s authorized ROE threshold of 10 percent for 2012-2014. In April 2014, PSCo filed its 2013 earnings test with the CPUC proposing a refund obligation of $45.7 million to electric customers to be returned between August 2014 and July 2015. This tariff was approved by the CPUC in July 2014 and became effective Aug. 1, 2014. As of Sept. 30, 2014, PSCo has also recognized management’s best estimate of an accrual for the 2014 earnings test of $52.4 million.

Electric, Purchased Gas and Resource Adjustment Clauses

Renewable Energy Credit (REC) Sharing — In 2011, the CPUC approved margin sharing on stand-alone REC transactions at 10 percent to PSCo and 90 percent to customers for 2014. In 2012, the CPUC approved an annual margin sharing on the first $20 million of margins on hybrid REC trades of 80 percent to the customers and 20 percent to PSCo. Margins in excess of the $20 million are to be shared 90 percent to the customers and 10 percent to PSCo. The CPUC authorized PSCo to return to customers unspent carbon offset funds by crediting the renewable energy standard adjustment (RESA) regulatory asset balance. PSCo’s credit to the RESA regulatory asset balance was not material for the three months ended Sept. 30, 2014. For the three months ended Sept. 30, 2013, PSCo credited the RESA regulatory asset balance $6.1 million. The cumulative credit to the RESA regulatory asset balance was $104.7 million and $104.5 million at Sept. 30, 2014 and Dec. 31, 2013, respectively. The credits include the customers’ share of REC trading margins and the unspent share of carbon offset funds.

In May 2014, PSCo filed with the CPUC to continue this sharing mechanism for 2015 and beyond, but remove the step increase in the sharing allocation of hybrid REC trades on margins in excess of $20 million. In July 2014, the CPUC sent the proceeding to an ALJ. On Sept. 5, 2014, PSCo, the CPUC Staff, and intervenors filed a settlement agreement to extend the current sharing mechanism without modification through 2017. On Sept. 18, 2014 the ALJ issued a final decision approving the settlement agreement.

Recently Concluded Regulatory Proceedings — FERC

PSCo Transmission Formula Rate Cases — In April 2012, PSCo filed with the FERC to revise the wholesale transmission formula rates from an HTY formula rate to a forecast transmission formula rate and to establish formula ancillary services rates. PSCo proposed that the formula rates be updated annually to reflect changes in costs, subject to a true-up. The request would increase PSCo’s wholesale transmission and ancillary services revenue by approximately $2.0 million annually. Various transmission customers protested the filing. In June 2012, the FERC issued an order accepting the proposed transmission and ancillary services formula rates, suspending the increase to November 2012, subject to refund, and setting the case for settlement judge or hearing procedures.

In June 2012, several wholesale customers filed a complaint with the FERC seeking to have the transmission formula rate ROE reduced from 10.25 to 9.15 percent effective July 1, 2012. In October 2012, the FERC consolidated this complaint with the April 2012 formula rate change filing.

In December 2013, the FERC approved a partial settlement resolving all issues related to the April 2012 transmission rate filing and June 2012 complaint other than ROE. The settlement does not materially increase 2014 transmission revenues.

In June 2014, PSCo and its transmission customers reached a settlement in principle to resolve the ROE issue in the transmission rate filing and complaint. The settlement was filed in September 2014, and in October 2014, the FERC ALJ granted PSCo a motion to place interim rates into effect using the settlement ROE beginning Oct. 1, 2014. The FERC approved the settlement in October 2014, providing a 9.72 percent ROE effective retroactive to July 1, 2012 for the PSCo transmission formula rate. PSCo recorded a current liability for the refund obligation based on the settlement terms as of Sept. 30, 2014.

PSCo – Production Formula Rate ROE Complaint — In August 2013, PSCo’s wholesale production customers filed a complaint with the FERC, and requested it reduce the stated ROEs ranging from 10.1 percent through 10.4 percent to 9.04 percent in the PSCo production sales formula rates effective Sept. 1, 2013. In June 2014, PSCo and its wholesale customers reached a settlement in principle to resolve the complaint along with the pending transmission formula rate ROE matters. The settlement was filed in September 2014, and in October 2014, the FERC ALJ granted PSCo a motion to place interim rates into effect using the settlement ROE beginning Oct. 1, 2014. The FERC approved the settlement in October 2014, providing a 9.72 percent ROE effective for the PSCo production formula rate. PSCo recorded a current liability for the refund obligation based on the settlement terms as Sept. 30, 2014.

SPS

Pending Regulatory Proceedings — Public Utility Commission of Texas (PUCT)

SPS – Texas 2014 Electric Rate Case — In January 2014, SPS filed a retail electric rate case in Texas with each of its Texas municipalities and the PUCT for a net increase in annual revenue of approximately $52.7 million, or 5.8 percent. The net increase reflected a base rate increase, revenue credits transferred from base rates to rate riders or the fuel clause, and resetting the Transmission Cost Recovery Factor (TCRF) to zero when the final base rates become effective. In April 2014, SPS revised its request to a net increase of $48.1 million.

The rate filing was based on a HTY ending June 2013, a requested ROE of 10.40 percent, an electric rate base of approximately $1.27 billion and an equity ratio of 53.89 percent. The requested rate increase reflected an increase in depreciation expense of approximately $16 million.

In September 2014, SPS, PUCT staff, and intervenors filed a non-unanimous settlement agreement, subject to PUCT approval, which would increase SPS’ rates by $37 million, or 3.5 percent, retroactive to June 1, 2014. Starting Oct. 1, 2014, SPS began collecting the rate increase through interim rates subject to refund. SPS expects to recover the rate increase for the months of June through September through a separate surcharge to be implemented by the first quarter of 2015. Based on the anticipated outcome of the rate case, SPS recognized approximately $13.3 million of revenue in the third quarter of 2014 for the surcharge.

The settlement includes an ROE of 9.7 percent solely for the purpose of calculating the AFUDC and determining baselines in future filings for the TCRF. In October 2014, the ALJs approved the stipulation and recommended that SPS file to implement the surcharge following the PUCT's final order. The PUCT is expected to rule on the settlement in 2014.

Although the parties to the settlement agreement have not prepared a calculation of the $37 million increase and do not agree about which specific costs are included, or not, in the agreed settlement revenue requirement, SPS’ reconciliation of its original request to the settlement increase is as follows:
(Millions of Dollars)
 
Settlement Agreement
Base rate increase request, January 2014
 
$
81.5

Revisions for updated information
 
(4.6
)
Revised request, April 2014
 
76.9

Remove proposed increase in depreciation
 
(16.0
)
Remove adjustment allocators for certain wholesale load reduction
 
(12.0
)
Revised amortizations (rate case expenses, pension and other post-employment benefits expense and gain on sale to Lubbock)
 
(9.0
)
Non-specified settlement adjustments
 
(2.9
)
Settlement base rate increase
 
$
37.0



Electric, Purchased Gas and Resource Adjustment Clauses

TCRF Rider — In November 2013, SPS filed with the PUCT to implement the TCRF for Texas retail customers. The requested increase in revenues was $13 million. The PUCT issued an order allowing the TCRF to go into effect on an interim basis effective Jan. 1, 2014. In May 2014, the ALJ terminated the interim TCRF due to a settlement in principle being reached with intervenors and the PUCT staff in the pending Texas electric rate case. In July 2014, the PUCT approved the settlement agreement between the parties allowing SPS to recover $4 million annually through the TCRF. In September 2014, SPS filed a proposal with the PUCT to refund approximately $3.7 million during November 2014 for interim rates collected in excess of the final rates approved. PUCT approval of the refund is pending. As of Sept. 30, 2014, SPS had recorded an accrual for the proposed refund.

Recently Concluded Regulatory Proceedings — New Mexico Public Regulation Commission (NMPRC)

SPS – New Mexico 2014 Electric Rate Case — In December 2012, SPS filed an electric rate case in New Mexico with the NMPRC for an increase in annual revenue of approximately $45.9 million effective in 2014. The rate filing was based on a 2014 forecast test year, a requested ROE of 10.65 percent, an electric rate base of $479.8 million and an equity ratio of 53.89 percent.

In September 2013, SPS filed rebuttal testimony, revising its requested rate increase to $32.5 million, based on updated information and an ROE of 10.25 percent. The request reflected a base and fuel increase of $20.9 million, an increase of rider revenue of $12.1 million and a decrease to other of $0.5 million.

In March 2014, the NMPRC approved an overall increase of approximately $33.1 million. The increase reflects a base rate increase of $12.7 million and rider recovery of $18.1 million for renewable energy costs, both based on an ROE of 9.96 percent and an equity ratio of 53.89 percent. Final rates were effective April 5, 2014. In April 2014, the New Mexico Attorney General (NMAG) filed a request for rehearing. The rehearing request was denied by the NMPRC. In June 2014, the NMAG filed an appeal of the NMPRC’s denial to the New Mexico Supreme Court. A decision is expected by the second quarter of 2016.

Pending Regulatory Proceedings — FERC

SPS – Wholesale Rate Complaints — In April 2012, Golden Spread Electric Cooperative, Inc. (Golden Spread), a wholesale cooperative customer, filed a rate complaint alleging that the base ROE included in the SPS production formula rate of 10.25 percent, and the SPS transmission base formula rate ROE of 10.77 percent, are unjust and unreasonable. In July 2013, Golden Spread filed a second complaint, again asking that the base ROE in the SPS production and transmission formula rates be reduced to 9.15 and 9.65 percent, respectively.

In addition to the FERC order issued for the MISO ROE complaint previously mentioned, the FERC issued orders in June 2014 consolidating the Golden Spread ROE complaints and setting them for settlement judge procedures and hearings and indicated the parties should apply the new ROE methodology to the proceedings. The FERC established effective dates for the refunds as April 20, 2012 and July 19, 2013. The complaints remain in settlement judge proceedings.

Golden Spread, along with certain New Mexico cooperatives and the West Texas Municipal Power Agency, filed a third rate complaint on Oct. 20, 2014, requesting that the base ROE in the SPS production and transmission formula rates be reduced to 8.61 percent and 9.11 percent, respectively. The complainants requested a refund effective date of Oct. 20, 2014, and that the new complaint be consolidated with the two prior complaints. FERC action is pending.

SPS – 2004 FERC Complaint Case Orders  In August 2013, the FERC issued an order on rehearing related to a 2004 complaint case brought by Golden Spread and Public Service Company of New Mexico (PNM) and an Order on Initial Decision in a subsequent 2006 production rate case filed by SPS.

The original complaint included two key components: 1) PNM’s claim regarding inappropriate allocation of fuel costs and 2) a base rate complaint, including the appropriate demand-related cost allocator. The FERC previously determined that the allocation of fuel costs and the demand-related cost allocator utilized by SPS was appropriate.

In the August 2013 Orders, the FERC clarified its previous ruling on the allocation of fuel costs and reaffirmed that the refunds in question should only apply to firm requirements customers and not PNM’s contractual load. The FERC also reversed its prior demand-related cost allocator decision. The FERC stated that it had erred in its initial analysis and concluded that the SPS system was a 3 coincident peak (CP) rather than a 12CP system.

In September 2013, SPS filed a request for rehearing of the FERC ruling on the CP allocation and refund decisions. SPS asserted that the FERC applied an improper burden of proof and that precedent did not support retroactive refunds. PNM also requested rehearing of the FERC decision not to reverse its prior ruling.

In October 2013, the FERC issued orders further considering the requests for rehearing. These matters are currently pending the FERC’s action. If unsuccessful in its rehearing request, SPS will have the opportunity to file rate cases with the FERC and its retail jurisdictions seeking to change all customers to a 3CP allocation method.

As of Dec. 31, 2013, SPS had accrued $44.5 million related to the August 2013 Orders and an additional $4.0 million of principal and interest was accrued during the first nine months of 2014. Pending the timing and resolution of this matter, the annual impact to revenues through 2014 could be up to $6 million and decreasing to $4 million on June 1, 2015.