Commitments And Contingencies
6 Months Ended
Jun. 30, 2021
Commitments and Contingencies Disclosure [Abstract]  
Commitments And Contingencies COMMITMENTS AND CONTINGENCIES
 
Legal Loss Contingencies
 
IPALCO and AES Indiana are involved in litigation arising in the normal course of business. We accrue for litigation and claims when it is probable that a liability has been incurred and the amount of loss can be reasonably estimated. As of June 30, 2021 and December 31, 2020, total legal loss contingencies accrued were $13.4 million and $13.4 million, respectively, which were included in "Other Non-Current Liabilities," on the accompanying Unaudited Condensed Consolidated Balance Sheets. A significant portion of these accrued liabilities relate to a personal injury judgement that is currently under appeal and involved injuries to a contractor. We maintain an amount of insurance protection for such litigation that we believe is adequate. While the ultimate outcome of outstanding litigation cannot be predicted with certainty, management believes that final outcomes will not have a material adverse effect on IPALCO’s results of operations, financial condition and cash flows.

Environmental Loss Contingencies
 
We are subject to various federal, state, regional and local environmental protection and health and safety laws and regulations governing, among other things, the generation, storage, handling, use, disposal and transportation of regulated materials, including ash; the use and discharge of water used in generation boilers and for cooling purposes; the emission and discharge of hazardous and other materials into the environment; and the health and safety of our employees. These laws and regulations often require a lengthy and complex process of obtaining and renewing permits and other governmental authorizations from federal, state and local agencies. Violation of these laws, regulations or permits can result in substantial fines, other sanctions, permit revocation and/or facility shutdowns. We cannot assure that we have been or will be at all times in full compliance with such laws, regulations and permits.

New Source Review and Other CAA NOVs
In October 2009, AES Indiana received a NOV and Finding of Violation from the EPA pursuant to the CAA Section 113(a). The NOV alleged violations of the CAA at AES Indiana’s three primarily coal-fired electric generating facilities at the time, dating back to 1986. The alleged violations primarily pertain to the PSD and non-attainment New Source Review (NSR) requirements under the CAA. In addition, on October 1, 2015, AES Indiana received a NOV from the EPA pursuant to CAA Section 113(a) alleging violations of the CAA, the Indiana SIP, and the Title V operating permit related to alleged particulate matter and opacity violations at AES Indiana Petersburg Unit 3. Also, on February 5, 2016, the EPA issued a NOV pursuant to CAA Section 113(a) alleging violations of PSD, non-attainment NSR and other CAA regulations, the Indiana SIP, and the Title V operating permit at Petersburg Generating Station. On August 31, 2020, AES Indiana reached a settlement with the EPA, the DOJ and IDEM resolving the purported violations of the CAA with respect to the four coal-fired generation units at AES Indiana's Petersburg location. The settlement agreement, in the form of a proposed judicial consent decree, was approved and entered by the U.S. District Court for the Southern District of Indiana on March 23, 2021, and includes, among other items, the following requirements: annual caps on NOx and SO2 emissions and more stringent emissions limits than AES Indiana's current Title V air permit; payment of civil penalties totaling $1.525 million (the payment of which was satisfied by AES Indiana in April 2021); a $5 million environmental mitigation project consisting of the construction and operation of a new, non-emitting source of generation at the site; expenditure of $0.325 million on a state-only environmentally beneficial project to preserve local, ecologically-significant lands; and retirement of Units 1 and 2 prior to July 1, 2023. If AES Indiana does not meet this retirement obligation, it must install a Selective Non-Catalytic Reduction System (SNCR) on Unit 4. AES Indiana had a contingent liability recorded related to these New Source Review and other CAA NOV matters.