2026 $ 1,785.0
2027 1,869.7
2028 1,755.1
2029 1,588.6
2030 1,204.9
Thereafter 14,311.4
Total 22,514.7
Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 1,113.9
2027 1,235.1
2028 1,246.2
2029 1,115.5
2030 784.1
Thereafter 11,643.4
Total 17,138.2
Natural Gas Procurement  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 523.3
2027 487.9
2028 359.4
2029 320.1
2030 273.6
Thereafter 781.9
Total 2,746.2
NECEC Transmission Service Agreement  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 94.6
2027 96.5
2028 98.4
2029 100.4
2030 102.4
Thereafter 1,806.4
Total 2,298.7
Capacity and Purchased Power  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 2.9
2027 2.7
2028 2.7
2029 2.3
2030 1.8
Thereafter 0.5
Total 12.9
Peaker CfDs  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 30.2
2027 25.9
2028 25.8
2029 26.2
2030 18.9
Thereafter 55.1
Total 182.1
Transmission Support Commitments  
Transmission Support Commitments  
2026 20.1
2027 21.6
2028 22.6
2029 24.1
2030 24.1
Thereafter 24.1
Total 136.6
CL&P  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 720.0
2027 809.0
2028 815.1
2029 675.7
2030 328.8
Thereafter 3,667.8
Total 7,016.4
CL&P | Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 681.8
2027 774.6
2028 780.4
2029 640.0
2030 300.4
Thereafter 3,603.2
Total 6,780.4
CL&P | Capacity and Purchased Power  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 0.1
2027 0.0
2028 0.0
2029 0.0
2030 0.0
Thereafter 0.0
Total 0.1
CL&P | Peaker CfDs  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 30.2
2027 25.9
2028 25.8
2029 26.2
2030 18.9
Thereafter 55.1
Total 182.1
CL&P | Transmission Support Commitments  
Transmission Support Commitments  
2026 7.9
2027 8.5
2028 8.9
2029 9.5
2030 9.5
Thereafter 9.5
Total 53.8
NSTAR Electric  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 537.4
2027 568.2
2028 575.8
2029 587.7
2030 597.4
Thereafter 9,856.6
Total 12,723.1
NSTAR Electric | Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 432.1
2027 460.5
2028 465.8
2029 475.5
2030 483.7
Thereafter 8,040.2
Total 10,357.8
NSTAR Electric | NECEC Transmission Service Agreement  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 94.6
2027 96.5
2028 98.4
2029 100.4
2030 102.4
Thereafter 1,806.4
Total 2,298.7
NSTAR Electric | Capacity and Purchased Power  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2026 2.8
2027 2.7
2028 2.7
2029 2.3
2030 1.8
Thereafter 0.5
Total 12.8
NSTAR Electric | Transmission Support Commitments  
Transmission Support Commitments  
2026 7.9
2027 8.5
2028 8.9
2029 9.5
2030 9.5
Thereafter 9.5
Total 53.8
PSNH | Transmission Support Commitments  
Transmission Support Commitments  
2026 4.3
2027 4.6
2028 4.8
2029 5.1
2030 5.1
Thereafter 5.1
Total $ 29.0