The Company leases equipment and office facilities under operating leases that expire through 2014.  Aggregate rental expense under all operating leases was approximately $338,000, $371,000 and $375,000 in the years ended December 31, 2011, 2010 and 2009, respectively.  At December 31, 2011, the future minimum rental commitments under existing non-cancelable operating leases are as follows:

Year
 
$
000’s
 
         
2012
   
302
 
2013
   
55
 
2014
   
16
 
   
$
373
 

In the normal course of its agricultural operations, the Company handles, stores, transports and dispenses products identified as hazardous materials.  Regulatory agencies periodically conduct inspections and, currently, there are no pending claims with respect to hazardous materials.

The Company entered into a Services and Exclusivity Agreement with Layne Christensen Company (“Layne”) on November 2, 2009.  The agreement provides that the Company will contract exclusively with Layne for certain water related services, including drilling of boreholes, drilling of monitoring wells, completion of test wells, completion of production wells, and completion of aquifer, storage and recovery wells.  In exchange for the Services and Exclusivity Agreement, Layne has agreed to forego $923,000 for work performed as of December 31, 2011.

Alternatively, if (a) the Company elects by December 31, 2012, not to proceed with the Water Project, then it will pay Layne 100% of the $923,000 balance due for work performed as of December 31, 2011, or (b) the Company elects by December 31, 2012, to proceed with the Water Project and in its reasonable discretion decides not to use Layne as the exclusive provider of services for the well field the Company will pay Layne 125% of the $923,000 balance due for work performed as of December 31, 2011.

As previously reported, the Company has a potential obligation to pay an amount of up to 1% of the net present value of the Water Project in consideration of certain legal and advisory services to be provided to the Company by Brownstein Hyatt Farber Schreck LLP.  The primary services being provided are advising the Company as to Water Project design and implementation, permit approvals, environmental compliance, negotiation and drafting of agreements related to the Water Project.  This fee would be payable upon receipt of all environmental approvals and permits and the completion of binding agreements for at least 51% of the Water Project’s annual capacity.  A portion of this fee may be payable in stock.  Interim payments of $1.5 million, to be credited to the final total, would be made upon the achievement of certain specified milestones.  $500 thousand of these interim payments was earned in June 2009 in consideration for the legal and advisory services previously provided.  No further milestones have been met as of December 31, 2011.  This arrangement may be terminated by either party upon 60 days notice, with any compensation earned but unpaid prior to termination payable following termination.

                Pursuant to cost sharing agreements that have been entered into by participants in the Company’s Water Project, $670 thousand in funds have offset costs incurred in the environmental analysis of the Water Project.  These funds may either be reimbursed or credited to participants participation in the Water Project and, accordingly, are fully reflected as deferred revenue as of December 31, 2011.

The Company is involved in other legal and administrative proceedings and claims.  In the opinion of management, the ultimate outcome of each proceeding, individually and in the aggregate, will not have a material adverse impact on the Company's financial statements.