XML 43 R22.htm IDEA: XBRL DOCUMENT v3.3.0.814
Commitments and Contingencies
9 Months Ended
Sep. 30, 2015
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
 Commitments and Contingencies  
CONSOL Carried Cost Obligation In accordance with our Marcellus Shale joint venture arrangement with a subsidiary of CONSOL Energy Inc. (CONSOL), we agreed to fund one-third of CONSOL's 50% working interest share of future drilling and completion costs, capped at $400 million each year (CONSOL Carried Cost Obligation). The remaining obligation totaled approximately $1.6 billion at September 30, 2015.
The CONSOL Carried Cost Obligation is suspended if average Henry Hub natural gas prices fall and remain below $4.00 per MMBtu in any three consecutive month period and remain suspended until average Henry Hub natural gas prices equal or exceed $4.00 per MMBtu for three consecutive months. The CONSOL Carried Cost Obligation is currently suspended due to current natural gas prices. Based on the September 30, 2015 NYMEX Henry Hub natural gas price curve, we expect that the CONSOL Carried Cost Obligation will be suspended for the next 12 months.
Legal Proceedings  We are involved in various legal proceedings in the ordinary course of business.  These proceedings are subject to the uncertainties inherent in any litigation.  We are defending ourselves vigorously in all such matters and we believe that the ultimate disposition of such proceedings will not have a material adverse effect on our financial position, results of operations or cash flows.
Colorado Air Matter  In April 2015, we entered into a joint consent decree (Consent Decree) with the US Environmental Protection Agency, US Department of Justice, and State of Colorado to improve emission control systems at a number of our condensate storage tanks that are part of our upstream oil and natural gas operations within the Non-Attainment Area of the DJ Basin. The Consent Decree was entered by the Court on June 2, 2015.   
The Consent Decree, which alleges violations of the Colorado Air Pollution Prevention and Control Act and Colorado’s federal approved State Implementation Plan, specifically Colorado Air Quality Control Commission Regulation Number 7, requires us to perform certain injunctive relief activities to complete mitigation projects and supplemental environmental projects (SEP), and pay a civil penalty. Costs associated with the settlement consist of $4.95 million in civil penalties, $4.5 million in mitigation projects, and $4 million in SEPs. Costs associated with the injunctive relief are not yet precisely quantifiable as they will be determined in accordance with the outcome of evaluations on the adequate design, operation, and maintenance of certain aspects of tank systems to handle potential peak instantaneous vapor flow rates between now and mid-2017.
Compliance with the Consent Decree could result in the temporary shut in or permanent plugging and abandonment of certain wells and associated tank batteries. The Consent Decree sets forth a detailed compliance schedule with deadlines for achievement of milestones through early 2019. The Consent Decree contains additional obligations for ongoing inspection and monitoring beyond that which is required under existing Colorado regulations.  Inspection and monitoring findings may influence decisions to temporarily shut in or permanently plug and abandon wells and associated tank batteries.     
We have concluded that the penalties, injunctive relief, and mitigation expenditures that resulted from this settlement did not have, and based on currently available information will not have, a material adverse effect on our financial position, results of operations or cash flows.