XML 26 R9.htm IDEA: XBRL DOCUMENT v3.5.0.2
Note 4 - Commitments, Contingencies and Obligations
9 Months Ended
Sep. 30, 2016
Notes to Financial Statements  
Commitments and Contingencies Disclosure [Text Block]
Note 4.    Commitments, Contingencies and Obligations
 
General
 
We follow the Financial Accounting Standards Board ("FASB") Accounting Standards Codification ("ASC") guidance in determining our accruals and disclosures with respect to loss contingencies, and evaluate such accruals and contingencies for each reporting period. Accordingly, estimated losses from loss contingencies are accrued by a charge to income when information available prior to issuance of the financial statements indicates that it is probable that a liability could be incurred and the amount of the loss can be reasonably estimated. Legal expenses associated with the contingency are expensed as incurred. If a loss contingency is not probable or reasonably estimable, disclosure of the loss contingency is made in the financial statements when it is at least reasonably possible that a material loss could be incurred.
 
Rio Grande Silver Guaranty
 
Our wholly-owned subsidiary, Rio Grande Silver Inc. (“Rio”), is party to a joint venture with Emerald Mining & Leasing, LLC (“EML”) and certain other parties with respect to a land package in the Creede Mining District of Colorado that is adjacent to other land held by Rio. Rio holds a 70% interest in the joint venture. In connection with the joint venture, we are required to guarantee certain environmental remediation-related obligations of EML to a third party up to a maximum liability to us of $2.5 million. As of September 30, 2016, we have not been required to make any payments pursuant to the guaranty. We may be required to make payments in the future, limited to the $2.5 million maximum liability, should EML fail to meet its obligations to the third party. However, to the extent that any payments are made by us under the guaranty, EML, in addition to other parties, has jointly and severally agreed to reimburse and indemnify us for any such payments. We have not recorded a liability relating to the guaranty as of September 30, 2016.
 
Lucky Friday Water Permit Matters
 
Over the last several years, the Lucky Friday unit has experienced several regulatory issues relating to its water discharge permits and water management more generally. In December 2013, the EPA issued to Hecla Limited a notice of violation (“2013 NOV”) alleging certain storm water reporting violations under Lucky Friday’s Clean Water Act Multi-Sector General Stormwater Permit for Industrial Activities. The alleged violations were resolved. The 2013 NOV also contained a request for information under Section 308 of the Clean Water Act directing Hecla Limited to undertake a comprehensive groundwater investigation of Lucky Friday’s tailings pond no. 3 to evaluate whether the pond is causing the discharge of pollutants via seepage to groundwater that is discharging to surface water.
 
We completed the investigation mandated by the EPA and submitted a draft report to the agency in December 2015. We are waiting for the EPA’s response, and until such time as the process is complete, we cannot predict what the impact of the investigation will be.
 
Hecla Limited strives to maintain its water discharges at the Lucky Friday unit in full compliance with its permits and applicable laws, however, we cannot provide assurance that in the future it will be able to fully comply with the permit limits and other regulatory requirements regarding water management.
 
Johnny M Mine Area near San Mateo, McKinley County, New Mexico
 
In May 2011, the EPA made a formal request to Hecla Mining Company for information regarding the Johnny M Mine Area near San Mateo, McKinley County, New Mexico, and asserted that Hecla Mining Company may be responsible under CERCLA for environmental remediation and past costs the EPA has incurred at the site. Mining at the Johnny M was conducted for a limited period of time by a predecessor of our subsidiary, Hecla Limited. In August 2012, Hecla Limited and the EPA entered into a Settlement Agreement and Administrative Order on Consent for Removal Action (“Consent Order”), pursuant to which Hecla Limited agreed to pay (i) $1.1 million to the EPA for its past response costs at the site and (ii) any future response costs at the site under the Consent Order, in exchange for a covenant not to sue by the EPA. Hecla Limited paid the approximately $1.1 million to the EPA for its past response costs and in December 2014, submitted to EPA the Engineering Evaluation and Cost Analysis (“EE/CA”) for the site. The EE/CA evaluates three alternative response actions: 1) no action, 2) off-site disposal, and 3) on-site disposal. The range in estimated costs of these alternatives is $0 to $221 million. In the EE/CA, Hecla Limited recommended that EPA approve on-site disposal, which is currently estimated to cost $5.6 million, on the basis that it is the most appropriate response action under CERCLA. In June 2015, the EPA approved the EE/CA, with a few minor conditions. The EPA still needs to publish the EE/CA for public notice and comment, and the agency will not make a final decision on the appropriate response action until the public comment process is complete. It is anticipated that Hecla Limited will implement the response action selected by the EPA pursuant to an amendment to the Consent Order or a new order. Based on the foregoing, we believe it is probable that Hecla Limited will incur a liability for remediation at the site, and our best estimate of that liability as of the date of this report is $5.6 million, and we have accrued that amount. There can be no assurance that Hecla Limited’s liability will not be more than $5.6 million, or that its ultimate liability will not have a material adverse effect on Hecla Limited’s or our results of operations or financial position.
 
In September 2016, Hecla Limited was served with a lawsuit filed by an individual in state court in New Mexico alleging personal injury claims arising from alleged exposure to contaminants as a result of allegedly living on land adjacent to the Johnny M Mine site.  We do not yet have enough information to conclude if Hecla Limited has any liability or to estimate any loss that it may incur.
 
Carpenter Snow Creek Site, Cascade County, Montana
 
In July 2010, the EPA made a formal request to Hecla Mining Company for information regarding the Carpenter Snow Creek Superfund Site located in Cascade County, Montana. The Carpenter Snow Creek Site is located in a historic mining district, and in the early 1980s Hecla Limited leased 6 mining claims and performed limited exploration activities at the site. Hecla Limited terminated the mining lease in 1988.
 
In June 2011, the EPA informed Hecla Limited that it believes Hecla Limited, among several other viable companies, may be liable for cleanup of the site or for costs incurred by the EPA in cleaning up the site. The EPA stated in the June 2011 letter that it has incurred approximately $4.5 million in response costs and estimated that total remediation costs may exceed $100 million. Hecla Limited cannot with reasonable certainty estimate the amount or range of liability, if any, relating to this matter because of, among other reasons, the lack of information concerning the site.
 
South Dakota and Colorado Superfund Sites Related to CoCa Mines, Inc.
 
In 1991, Hecla Limited acquired all of the outstanding common stock of CoCa Mines, Inc. (“CoCa”).  CoCa is alleged to have held prior property interests and undertaken exploration activities at the Gilt Edge Mine Superfund site in Lawrence County, South Dakota, and to have been engaged in exploration and mining activities at or near the Nelson Tunnel/Commodore Waste Rock Pile Superfund site in Creede, Colorado.  The United States and the State of South Dakota alleged that CoCa, along with other parties, is a potentially responsible party (“PRP”) under CERCLA at the Gilt Edge site.  In addition, the United States and the State of Colorado alleged that CoCa is a PRP at the Nelson Tunnel/Commodore site. The United States, South Dakota and Colorado based their claims of liability on allegations of CoCa’s historical relationship to each site, and that CoCa succeeded to the liabilities of one or more predecessor entities that may have held certain property interests at the sites or undertaken certain activities.
 
The United States alleged that it had incurred $118 million, plus interest, in response costs at the Gilt Edge site. At the Nelson Tunnel/Commodore site, the EPA alleges that it had incurred $10 million, plus interest, in response costs.
 
As a result of settlement discussions, in the second quarter of 2015 we accrued $9.9 million by recording a liability for the total amount that would be paid by CoCa to settle the Gilt Edge and Nelson Tunnel/Commodore Waste Rock Pile matters, and an asset for the estimated amount that would be recovered by CoCa from insurers and the other settling PRP with respect to the Gilt Edge site.
 
CoCa reached final terms of settlement on each of the matters in April 2016 in the form of Consent Decrees agreed to by CoCa and (i) the United States and the State of South Dakota with respect to the Gilt Edge site and (ii) the United States and the State of Colorado with respect to Nelson Tunnel/Commodore Waste Rock Pile site.
 
The Consent Decrees were approved and entered by the Courts on June 15, 2016 in the case of the Nelson Tunnel/Commodore Waste Rock Pile, and on September 19, 2016 in the case of Gilt Edge. As a result, CoCa paid an aggregate of $6 million in August 2016 to the United States and the State of Colorado, and an aggregate of $3.9 million in November 2016 to the United States and the State of South Dakota (insurers and another PRP paid an additional $6.4 million to settle the Gilt Edge matter). As a result, CoCa has resolved the claims of (i) the United States and the State of South Dakota with respect to the Gilt Edge site, and (ii) the United States and the State of Colorado with respect to the Nelson Tunnel site, in each case under CERCLA and certain relevant state statutes, for all past and future response costs at each site.
 
Senior Notes
 
On April 12, 2013, we completed an offering of $500 million aggregate principal amount of 6.875% Senior Notes due 2021.
The net proceeds from the offering of the Senior Notes were used to partially fund the acquisition of Aurizon Mines Ltd. ("Aurizon") and for general corporate purposes, including expenses related to the Aurizon acquisition. In 2014, we completed additional issuances of our Senior Notes in the aggregate principal amount of $6.5 million, which were contributed to one of our pension plans to satisfy the funding requirement for 2014. Interest on the Senior Notes is payable on May 1 and November 1 of each year, commencing November 1, 2013. See
Note 9
for more information.
 
Other Commitments
 
Our contractual obligations as of September 30, 2016 included approximately $0.8 million for various costs. In addition, our open purchase orders at September 30, 2016 included approximately $1.4 million, $1.6 million and $8.3 million, respectively, for various capital items at the Lucky Friday, Casa Berardi and Greens Creek units, and approximately $0.6 million, $1.1 million, and $2.4 million, respectively, for various non-capital costs at the Lucky Friday, Casa Berardi and Greens Creek units. We also have total commitments of approximately $14.2 million relating to scheduled payments on capital leases, including interest, primarily for equipment at our Greens Creek, Lucky Friday and Casa Berardi units (see
Note 9
for more information). As part of our ongoing business and operations, we are required to provide surety bonds, bank letters of credit, and restricted deposits for various purposes, including financial support for environmental reclamation obligations and workers compensation programs. As of September 30, 2016, we had surety bonds totaling $105.3 million in place as financial support for future reclamation and closure costs, self insurance, and employee benefit plans. The obligations associated with these instruments are generally related to performance requirements that we address through ongoing operations. As the requirements are met, the beneficiary of the associated instruments cancels or returns the instrument to the issuing entity. Certain of these instruments are associated with operating sites with long-lived assets and will remain outstanding until closure of the sites. We believe we are in compliance with all applicable bonding requirements and will be able to satisfy future bonding requirements as they arise.
 
Other Contingencies
 
On April 12, 2013, the family of Larry Marek, an employee of Hecla Limited who was fatally injured in an April 2011 accident, filed a lawsuit against us and certain of our officers and employees seeking damages for, among other claims, wrongful death and infliction of emotional distress. No dollar amount of damages is specified in the complaint, which was filed in state court in Idaho (Kootenai County District Court). On April 21, 2015, the judge hearing the case granted Hecla’s motion for summary judgment and dismissed the case. The plaintiffs appealed the decision to the Idaho Supreme Court which heard arguments on August 30, 2016. No decision has yet been issued, and we cannot predict the outcome of this matter.
 
On December 11, 2013, four employees of Hecla Limited who were injured in a December 2011 rock burst filed a lawsuit against us and certain of our employees seeking damages for, among other claims, intentional and willful injury and infliction of emotional distress. The plaintiffs seek damages in excess of $1,000,000, as claimed in the complaint, which was filed in state court in Idaho (Kootenai County District Court). On August 28, 2015, the judge hearing the case granted Hecla’s motion for summary judgment and dismissed the case. The plaintiffs appealed the decision to the Idaho Supreme Court which heard arguments on August 30, 2016. No decision has yet been issued, and we cannot predict the outcome of this matter.
 
We also have certain other contingencies resulting from litigation, claims, EPA investigations, and other commitments and are subject to a variety of environmental and safety laws and regulations incident to the ordinary course of business. We currently expect that the resolution of such contingencies will not materially affect our financial position, results of operations or cash flows. However, in the future, there may be changes to these contingencies, or additional contingencies may occur, any of which might result in an accrual or a change in the estimated accruals recorded by us, and there can be no assurance that their ultimate disposition will not have a material adverse effect on our financial position, results of operations or cash flows.