Property, Plant and Equipment Note D – Property, Plant and Equipment
Exploratory Wells
Under FASB guidance, exploratory well costs should continue to be capitalized when the well has found a sufficient quantity of reserves to justify its completion as a producing well and the company is making sufficient progress assessing the reserves and the economic and operating viability of the project.
As of June 30, 2024, the Company had total capitalized drilling costs pending the determination of proved reserves of $43.0 million. The following table reflects the net changes in capitalized exploratory well costs during the six-month periods ended June 30, 2024 and 2023.
(Thousands of dollars)20242023
Beginning balance at January 1$49,118 $171,860 
  Additions pending the determination of proved reserves20,391 47,733 
  Capitalized exploratory well costs charged to expense(26,471)(26,188)
Balance at June 30$43,038 $193,405 
Capitalized well costs charged to dry hole expense of $26.5 million for the six months ended June 30, 2024 was related to the Hoffe Park #1 (Mississippi Canyon 166) exploratory well in the Gulf of Mexico. Capital additions are mainly for Ocotillo #1 (Mississippi Canyon 40) exploratory well in the Gulf of Mexico. The preceding table excludes well costs of $31.8 million and $70.3 million incurred and expensed directly to dry hole for the six months ended June 30, 2024 and 2023, respectively. In 2024 the amount includes $25.5 million for the Orange #1 (Mississippi Canyon 216) exploration well in the Gulf of Mexico and in 2023 the amount includes $69.2 million related to the Chinook #7 exploration well in the Gulf of Mexico.
The following table provides an aging of capitalized exploratory well costs based on the date the drilling was completed for each individual well and the number of projects for which exploratory well costs have been capitalized. The projects are aged based on the last well drilled in the project.
June 30,
20242023
(Thousands of dollars)AmountNo. of WellsNo. of ProjectsAmountNo. of WellsNo. of Projects
Aging of capitalized well costs:
Zero to one year$20,545 3 3 $8,494 
One to two years   38,497 
Two to three years   2,698 
Three years or more22,493 3 3 143,716 
$43,038 6 6 $193,405 
Of the $22.5 million of exploratory well costs capitalized more than one year at June 30, 2024, $15.1 million was in Vietnam, $4.7 million was in Canada, and $2.7 million was in Brunei. In all geographical areas, either further appraisal or development drilling is planned and/or development studies/plans are in various stages of completion. 
Impairments
There were no impairments in the three months ended June 30, 2024. There were pre-tax impairments of $34.5 million in the six months ended June 30, 2024 related to Calliope field in Mississippi Canyon, in the Gulf of Mexico, where operational issues led to a reserve reduction. There were no impairments in the three and six months ended June 30, 2023.
Divestitures
On September 15, 2023, the Company completed the divestment of certain non-core operated Kaybob Duvernay assets and all of our non-operated Placid Montney assets, located in Alberta, Canada for net cash proceeds of C$139.0 million. No gain or loss was recorded related to this transaction, and the effective date of the transaction was March 1, 2023.