XML 21 R99.htm IDEA: XBRL DOCUMENT v3.20.1
Regulatory Matters (Narrative) (Detail)
$ in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Apr. 30, 2020
USD ($)
MW
GW
Mar. 31, 2020
USD ($)
Feb. 29, 2020
USD ($)
Jan. 31, 2020
USD ($)
Sep. 30, 2019
USD ($)
Jul. 31, 2019
USD ($)
Mar. 31, 2019
USD ($)
Jul. 31, 2018
USD ($)
Mar. 31, 2020
USD ($)
Dec. 31, 2019
USD ($)
Dec. 31, 2008
Jan. 31, 2019
USD ($)
Virginia Electric and Power Company | Rider US-3                        
Public Utilities General Disclosures [Line Items]                        
Approved cost of project                 $ 18      
Total annual revenue requirement                 $ 28      
East Ohio | Pipeline Infrastructure Replacement Program                        
Public Utilities General Disclosures [Line Items]                        
Percentage of pipeline system replaced                     25.00%  
Ohio Regulation                        
Public Utilities General Disclosures [Line Items]                        
Contract with customer credits tax reform                   $ 600    
Tax Reform Act's impact on its equity return                   $ 19    
Ohio Regulation | Subsequent Event | East Ohio | Pipeline Infrastructure Replacement Program                        
Public Utilities General Disclosures [Line Items]                        
Total annual revenue requirement $ 218                      
Total estimated cost 209                      
Total cumulative estimated cost $ 1,800                      
Virginia Regulation | Virginia Electric and Power Company                        
Public Utilities General Disclosures [Line Items]                        
Proposed revenue requirement     $ 1,200                  
Proposed revenue requirement recovered balance     81                  
Increase (decrease) in revenue requirement   $ (393)                    
Virginia Regulation | Virginia Electric and Power Company | GTSA                        
Public Utilities General Disclosures [Line Items]                        
Estimated cost of project               $ 816       $ 68
Operations and maintenance expenses         $ 78     $ 102        
Proposed cost of project         503              
Approved cost of project   212                    
Virginia Regulation | Virginia Electric and Power Company | Solar Development Project | Rider US-3 | Operating Segments                        
Public Utilities General Disclosures [Line Items]                        
Estimated cost of project           $ 146            
Proposed revenue requirement           $ 9            
Solar capacity factor when normalized for force majeure events       22.00%                
Approved annual revenue required   7                    
Virginia Regulation | Subsequent Event                        
Public Utilities General Disclosures [Line Items]                        
Percentage of electric energy excluding existing nuclear generation and certain new carbon resources 100.00%                      
Cap on revenue reductions in the first triennial $ 50                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Target to Reach by End of 2025                        
Public Utilities General Disclosures [Line Items]                        
Energy efficiency target percentage. based on energy savings from 2019 baseline 5.00%                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Solar and Onshore Wind | Target to Reach by End of 2035                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | GW 16.1                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Utility-scale Solar | Target to Reach by End of 2035 | Maximum                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | GW 15.0                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Utility-scale Solar | Target to Reach by End of 2024                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | GW 3.0                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Small-scale Solar | Target to Reach by End of 2035                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | GW 1.1                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Energy Storage | Target to Reach by End of 2035                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | MW 2,700                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Offshore Wind Facility | Target to Reach by End of 2035 | Maximum                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | MW 5,200                      
Constructed by utility capacity | MW 3,000                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Offshore Wind Facility | Target to Reach by End of 2035 | Minimum                        
Public Utilities General Disclosures [Line Items]                        
Constructed by utility capacity | MW 2,500                      
Virginia Regulation | Subsequent Event | Virginia Electric and Power Company | Pumped Storage | Target to Reach by End of 2035 | Maximum                        
Public Utilities General Disclosures [Line Items]                        
Targeted capacity provided by legislation | MW 800                      
North Carolina Regulation | Virginia Electric and Power Company                        
Public Utilities General Disclosures [Line Items]                        
Percentage of earned return             7.52%          
Authorized return percentage             9.90%          
Return of equity percentage             10.75%          
Approved return on equity percentage       9.75%                
North Carolina Regulation | Virginia Electric and Power Company | Annual Base Fuel Revenues                        
Public Utilities General Disclosures [Line Items]                        
Increase (decrease) in revenue requirement         $ 24   $ 27          
North Carolina Regulation | PSNC | Pipeline Integrity Tracker                        
Public Utilities General Disclosures [Line Items]                        
Increase (decrease) in revenue requirement     7                  
Total annual revenue requirement     28                  
South Carolina Regulation | Dominion Energy South Carolina Inc                        
Public Utilities General Disclosures [Line Items]                        
Annual transportation cost rate adjustment, approval amount requested to recover amount       $ 40                
Increase decrease in annual base fuel component recoveries     $ 44                  
Federal Energy Regulatory Commission | Cove Point | Atlantic Coast Pipeline                        
Public Utilities General Disclosures [Line Items]                        
Annual cost-of-service, amount       $ 182                
Federal Energy Regulatory Commission | Cove Point | Supply Header Project | Atlantic Coast Pipeline                        
Public Utilities General Disclosures [Line Items]                        
Annual transportation cost rate adjustment, approval amount requested to recover amount   $ 28