XML 104 R84.htm IDEA: XBRL DOCUMENT v3.8.0.1
Regulatory Matters (Narrative) (Detail)
customer in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Apr. 30, 2018
USD ($)
customer
Feb. 28, 2018
USD ($)
Jun. 30, 2016
USD ($)
Apr. 30, 2016
Aug. 31, 2009
kV
Apr. 30, 2008
Apr. 30, 2007
kV
Mar. 31, 2018
USD ($)
kV
power_station
mi
Dec. 31, 2017
USD ($)
Public Utilities General Disclosures [Line Items]                  
Regulatory assets-noncurrent               $ 2,698,000,000 $ 2,480,000,000 [1]
Regulatory asset recovered through retail rates                  
Public Utilities General Disclosures [Line Items]                  
Regulatory assets-noncurrent [2]               229,000,000 222,000,000
Virginia Regulation | Operating Segments                  
Public Utilities General Disclosures [Line Items]                  
Charge associated with legislation               215,000,000  
Charge associated with legislation, after tax               160,000,000  
Virginia Electric and Power Company                  
Public Utilities General Disclosures [Line Items]                  
ROE (percentage)           11.40%      
Regulatory assets-noncurrent               1,009,000,000 810,000,000 [3]
Virginia Electric and Power Company | Regulatory asset recovered through retail rates                  
Public Utilities General Disclosures [Line Items]                  
Regulatory assets-noncurrent [2]               $ 229,000,000 222,000,000
Virginia Electric and Power Company | Virginia Regulation                  
Public Utilities General Disclosures [Line Items]                  
Earnings above authorized return on equity (basis points)               0.70%  
One-time bill credit, provisions for current customers               $ 200,000,000  
Virginia Electric and Power Company | Virginia Regulation | Double Circuit Transmission Line Between Near Gainesville Substation And Haymarket Substation                  
Public Utilities General Disclosures [Line Items]                  
Capacity of transmission line (kV) | kV               230  
Length of kV line (miles) | mi               5  
Virginia Electric and Power Company | Virginia Regulation | Operating Segments                  
Public Utilities General Disclosures [Line Items]                  
Charge associated with legislation               $ 215,000,000  
Charge associated with legislation, after tax               160,000,000  
Reduction in base rate on annual basis               $ 125,000,000  
Virginia Electric and Power Company | Virginia Regulation | Rider B                  
Public Utilities General Disclosures [Line Items]                  
ROE (percentage)               11.20%  
Number of power stations converted to biomass | power_station               3  
Approved revenue required   $ 47,000,000              
Proposed revenue requirement               $ 42,000,000  
Virginia Electric and Power Company | Virginia Regulation | Rider U                  
Public Utilities General Disclosures [Line Items]                  
Approved revenue required               73,000,000  
Phase of conversions               179,000,000  
Phase of conversions not previously approved for recovery               65,000,000  
Virginia Electric and Power Company | Settled Litigation | Federal Energy Regulatory Commission | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action                  
Public Utilities General Disclosures [Line Items]                  
Amount required to pay under settlement agreement (in excess of $200 million)     $ 200,000,000            
Duration of payment under settlement agreement     10 years            
Amount of contingent liability               239,000,000  
Virginia Electric and Power Company | Settled Litigation | Federal Energy Regulatory Commission | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action | Regulatory asset recovered through retail rates                  
Public Utilities General Disclosures [Line Items]                  
Regulatory assets-noncurrent               229,000,000  
Virginia Electric and Power Company | Minimum                  
Public Utilities General Disclosures [Line Items]                  
Facility operating capacity (kV) | kV             500    
Virginia Electric and Power Company | Minimum | Judicial Ruling                  
Public Utilities General Disclosures [Line Items]                  
Facility operating capacity (kV) | kV         500        
DETI | Federal Energy Regulatory Commission | Other operations and maintenance | Preliminary recommendation one                  
Public Utilities General Disclosures [Line Items]                  
Audit compliance charge recognized in connection with preliminary recommendation                 15,000,000
Audit compliance after-tax charge recognized in connection with preliminary recommendation                 9,000,000
DETI | Federal Energy Regulatory Commission | Other operations and maintenance | Other preliminary recommendation                  
Public Utilities General Disclosures [Line Items]                  
Audit compliance charge recognized in connection with preliminary recommendation                 0
Audit compliance after-tax charge recognized in connection with preliminary recommendation                 0
East Ohio | Ohio Regulation | Pipeline Infrastructure Replacement Program                  
Public Utilities General Disclosures [Line Items]                  
Proposed revenue requirement               165,000,000  
Percentage replacement of pipeline system       25.00%          
Total estimated cost               $ 1,400,000,000 $ 204,000,000
East Ohio | Ohio Regulation | Automated Meter Reading Program                  
Public Utilities General Disclosures [Line Items]                  
Proposed revenue requirement $ 5,000,000                
Number of customers with automated meter reading technology | customer 1.2                
[1] Dominion Energy’s Consolidated Balance Sheet at December 31, 2017 has been derived from the audited Consolidated Balance Sheet at that date.
[2] Reflects amounts related to the PJM transmission cost allocation matter. See Note 13 for more information.
[3] Virginia Power’s Consolidated Balance Sheet at December 31, 2017 has been derived from the audited Consolidated Balance Sheet at that date.