XML 37 R100.htm IDEA: XBRL DOCUMENT v3.19.3
Regulatory Matters (Narrative) (Detail)
ft³ in Millions, customer in Millions, $ in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Nov. 01, 2019
USD ($)
May 03, 2019
USD ($)
May 31, 2019
USD ($)
Apr. 30, 2019
ft³
Mar. 31, 2019
USD ($)
Feb. 28, 2019
USD ($)
Jan. 31, 2019
USD ($)
Oct. 31, 2018
USD ($)
Jul. 31, 2018
USD ($)
Nov. 30, 2013
kV
mi
Mar. 31, 2019
USD ($)
Dec. 31, 2017
customer
Dec. 31, 2011
Dec. 31, 2018
USD ($)
SCE&G [Member]                            
Public Utilities General Disclosures [Line Items]                            
Recover of cost and net lost revenue with incentive             $ 30              
Virginia Electric and Power Company                            
Public Utilities General Disclosures [Line Items]                            
Submitted and approved decrease in base rate revenue               $ 14            
Regulatory liabilities one time bill credit amount               13            
Virginia Electric and Power Company | Virginia Regulation                            
Public Utilities General Disclosures [Line Items]                            
Proposed annual revenue reduction amount             $ 171              
Interim rate reduction amount                 $ 125          
Annual revenue reduction amount         $ 183                  
Estimated annual revenue reduction on one-time customer credit         $ 135                  
Return of equity percentage         10.75%                  
Virginia Electric and Power Company | Virginia Regulation | Surry Switching Station Transmission Line                            
Public Utilities General Disclosures [Line Items]                            
Length of transmission line (miles) | mi                   7        
Capacity of transmission line (kV) | kV                   500        
Virginia Electric and Power Company | Virginia Regulation | Transmission Line from Skiffes Creek Switching Station to Wheaton Substation                            
Public Utilities General Disclosures [Line Items]                            
Length of transmission line (miles) | mi                   20        
Capacity of transmission line (kV) | kV                   230        
Virginia Electric and Power Company | Virginia Regulation | Rider U                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement         $ 52                  
Projected capital investment                     $ 123      
Virginia Electric and Power Company | Virginia Regulation | DSM Programs                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement               49            
Projected capital investment               262            
Increase (decrease) in revenue requirement               $ 18            
Virginia Electric and Power Company | Virginia Regulation | Rider C3A                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement     $ 49                      
Virginia Electric and Power Company | Virginia Regulation | Solar Development Project | Rider US-3 | Operating Segments                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement                 $ 10          
Virginia Electric and Power Company | North Carolina Regulation                            
Public Utilities General Disclosures [Line Items]                            
Return of equity percentage         10.75%                  
Percentage of earned return         7.52%                  
Authorized return percentage         9.90%                  
Virginia Electric and Power Company | North Carolina Regulation | Annual Base Fuel Revenues                            
Public Utilities General Disclosures [Line Items]                            
Increase (decrease) in revenue requirement $ 27                          
East Ohio | Ohio Regulation | Pipeline Infrastructure Replacement Program                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement           $ 190                
Percentage replacement of pipeline system           25.00%                
Total estimated cost           $ 1,600               $ 202
East Ohio | Ohio Regulation | Automated Meter Reading Program                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement         $ 4                  
Number of customers with automated meter reading technology | customer                       1.2    
East Ohio | Ohio Regulation | CEP Program                            
Public Utilities General Disclosures [Line Items]                            
Proposed revenue requirement   $ 83                        
Total estimated cost   $ 723                        
Percentage to defer expenses on capital investments                         6.50%  
Questar Gas | Utah And Wyoming Regulation                            
Public Utilities General Disclosures [Line Items]                            
LNG storage facility, liquefaction rate per day | ft³       8.2                    
Number of days to make prudency determination       180 days                    
Cove Point | Federal Energy Regulatory Commission                            
Public Utilities General Disclosures [Line Items]                            
Annual transportation cost rate adjustment, approval amount requested to recover amount           $ 24