Regulatory Matters (Tables)
12 Months Ended
Dec. 31, 2024
Public Utilities General Disclosures [Line Items]  
Summary of Significant Virginia Power Electric Transmission Projects Applied

Electric Transmission Projects

Significant Virginia Power electric transmission projects approved or applied for are as follows:

Description and Location
of Project

 

Application
Date

 

Approval
Date

 

Type of
Line

 

Miles of
Lines

 

Cost Estimate
(millions)
(1)

 

Construct new Germanna substation, transmission
  line and related projects in Culpeper County,
  Virginia

 

November 2023

 

August 2024

 

230 kV

 

2

 

$

55

 

Construct Daves Store transmission line extension
  in Prince William County, Virginia

 

February 2024

 

October 2024

 

230 kV

 

3

 

 

70

 

Construct new Aspen and Golden substations,
  transmission lines and related projects in Loudoun
  County, Virginia

 

March 2024

 

February 2025

 

500-
230 kV

 

10

 

 

705

 

Partial rebuild Fredericksburg-Aquia Harbour
  transmission lines and related projects in Stafford
  County and the City of Fredericksburg, Virginia

 

March 2024

 

February 2025

 

230-
115 kV

 

24

 

 

135

 

Construct new Apollo-Twin Creek transmission lines,
  new substations and related projects in Loudoun
  County, Virginia

 

March 2024

 

February 2025

 

230 kV

 

2

 

 

285

 

Rebuild Dooms-Harrisonburg transmission lines
  and related projects in the Counties of Augusta
  and Rockingham and the Town of Grottoes, Virginia

 

April 2024

 

February 2025

 

230 kV

 

22

 

 

60

 

Rebuild and construct new Fentress-Yadkin
  transmission lines and related projects in the
  City of Chesapeake, Virginia

 

June 2024

 

Pending

 

500 kV

 

14

 

 

205

 

Partial rebuild, reconductor and construct new
  Network Takeoff transmission lines and related
  projects in the Counties of Fairfax and Loudoun,
  Virginia

 

July 2024

 

Pending

 

230 kV

 

6

 

 

170

 

Rebuild Aquia Harbor-Possum Point transmission
  lines and related projects in the Counties of
  Stafford and Prince William and the City of
  Fredericksburg, Virginia

 

August 2024

 

Pending

 

500-
230 kV

 

32

 

 

210

 

Partial rebuild, reconductor and construct new
  New Post transmission lines and related projects
  in the Counties of Caroline and Spotsylvania,
  Virginia

 

August 2024

 

Pending

 

230 kV

 

38

 

 

120

 

Construct new Centreport transmission line,
  substation and related projects in Stafford County,
  Virginia

 

September 2024

 

Pending

 

230 kV

 

3

 

 

55

 

Partial rebuild and construct new Meadowville
  transmission lines, substations and related projects
  in Chesterfield County, Virginia

 

October 2024

 

Pending

 

230 kV

 

11

 

 

190

 

Construct new Carmel Church and Ruther Glen
  transmission lines, substations and related projects
  in Caroline County, Virginia

 

December 2024

 

Pending

 

230 kV

 

7

 

 

85

 

Construct new Nebula transmission lines,
  substation and related projects in Mecklenburg
  County, Virginia

 

January 2025

 

Pending

 

230 kV

 

15

 

 

130

 

Construct new Culpeper Technology transmission
  lines, substations and related projects in the Counties
  of Culpeper, Orange and Fauquier and the Town of
  Culpeper, Virginia

 

February 2025

 

Pending

 

230 kV

 

13

 

 

255

 

(1)
Represents the cost estimate included in the application except as updated in the approval if applicable. In addition, Virginia Power had various other transmission projects approved during 2024 and early 2025 or applied for and currently pending approval with aggregate cost estimates of approximately $145 million and $65 million, respectively.
Virginia Electric and Power Company  
Public Utilities General Disclosures [Line Items]  
Significant Riders Associated With Virginia Power Projects

Significant riders associated with various Virginia Power projects are as follows:

Rider Name

 

Application Date

 

Approval Date

 

Rate Year
Beginning

 

Total Revenue Requirement (millions)(1)

 

 

Increase (Decrease) Over Previous Year (millions)

 

Rider BW(2)

 

October 2021

 

May 2022

 

September 2023

 

$

120

 

 

$

(25

)

Rider CCR

 

March 2024

 

November 2024

 

December 2024

 

 

103

 

 

 

(91

)

Rider CE(3)

 

October 2023

 

March 2024

 

May 2024

 

 

133

 

 

 

44

 

Rider CE(4)

 

October 2024

 

Pending

 

May 2025

 

 

182

 

 

 

49

 

Rider DIST(5)

 

August 2024

 

Pending

 

June 2025

 

 

269

 

 

N/A

 

Rider E

 

January 2024

 

September 2024

 

November 2024

 

 

72

 

 

 

(37

)

Rider E

 

January 2025

 

Pending

 

November 2025

 

 

37

 

 

 

(35

)

Rider GEN(2)

 

June 2024

 

Pending

 

April 2025

 

 

438

 

 

N/A

 

Rider GEN

 

June 2024

 

Pending

 

April 2026

 

 

311

 

 

 

(127

)

Rider GT(5)

 

August 2023

 

May 2024

 

June 2024

 

 

145

 

 

 

131

 

Rider GV(2)

 

June 2023

 

February 2024

 

April 2024

 

 

132

 

 

 

5

 

Rider GV(2)

 

June 2023

 

February 2024

 

April 2025

 

 

135

 

 

 

3

 

Rider OSW

 

November 2023

 

July 2024

 

September 2024

 

 

486

 

 

 

215

 

Rider OSW(6)

 

November 2024

 

Pending

 

September 2025

 

 

640

 

 

 

154

 

Rider RPS

 

December 2023(12)

 

August 2024

 

September 2024

 

 

358

 

 

 

262

 

Rider RPS

 

December 2024

 

Pending

 

September 2025

 

 

609

 

 

 

251

 

Rider SNA

 

October 2023

 

June 2024

 

September 2024

 

 

69

 

 

 

19

 

Rider SNA(7)

 

October 2024

 

Pending

 

September 2025

 

 

207

 

 

 

138

 

Rider T1(8)

 

May 2024

 

July 2024

 

September 2024

 

 

1,170

 

 

 

291

 

Rider U(5)(9)

 

October 2023

 

July 2024

 

August 2024

 

 

150

 

 

 

76

 

DSM Riders(10)

 

December 2023

 

July 2024

 

September 2024

 

 

86

 

 

 

(21

)

DSM Riders(11)

 

December 2024

 

Pending

 

September 2025

 

 

97

 

 

 

11

 

(1)
In addition, Virginia Power has various riders associated with other projects with an aggregate total annual revenue requirement of approximately $18 million as of December 31, 2024. There are various pending applications associated with such riders, which if approved, would result in a net increase of approximately $24 million.
(2)
Rider GEN includes $348 million in total revenue requirement related to the consolidation of Riders BW, GV and four other riders associated with generation facilities, ceasing the separate collection of rates under these riders effective April 1, 2025 and the extension of existing rates for Rider BW through March 2025. In addition, Virginia Power also requests approval to recover costs associated with the Virginia LNG Storage Facility described above.
(3)
The Virginia Commission approved four solar generation projects and 13 power purchase agreements in addition to previously approved Rider CE projects. In addition, the approved total revenue requirement includes amounts which had previously been collected under a separate rider.
(4)
Associated with two solar generation projects, two small-scale solar projects and 24 power purchase agreements in addition to previously approved Rider CE projects and power purchase agreements.
(5)
Rider DIST consists of $103 million in total revenue requirement for certain previously approved electric distribution grid transformation projects and $166 million for previously approved phases and proposed phase eight of certain new underground distribution facilities. If approved, would result in the consolidation of Riders GT and U and cease the separate collection of rates under these riders effective June 1, 2025.
(6)
Includes a proposal for Virginia Power to establish a decommissioning trust fund associated with the CVOW Commercial Project. If approved, the applicable amount included within the total revenue requirement would be allocated for such purposes.
(7)
Virginia Power also requested approval of cost recovery of approximately $1.7 billion through Rider SNA for the second phase of nuclear life extension program which includes investments for calendar years 2025 through 2027.
(8)
Consists of $532 million for the transmission component of Virginia Power’s base rates and $638 million for Rider T1.
(9)
Consists of $72 million for previously approved phases and $78 million for phase seven costs for Rider U. In addition, the Virginia Commission approved Virginia Power’s request to extend existing rates for Rider U through July 2024.
(10)
Associated with an additional three new energy efficiency programs and one new demand response program with a $102 million cost cap, with the ability to exceed the cost cap by no more than 15%.
(11)
Associated with three redesigned energy efficiency programs, one new and two redesigned demand response program and one demand response pilot with a $222 million cost cap, with the ability to exceed the cost cap by no more than 15%.
(12)
Virginia Power amended its application in February 2024.