Property, Plant and Equipment (Schedule of Nonregulated Solar Projects) (Detail)
$ in Millions
12 Months Ended
Dec. 31, 2024
USD ($)
MW
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Property Plant And Equipment [Line Items]      
Project Cost $ 229 $ 24 $ 167
Acquisition of Solar Project Hardin I in Ohio      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-08    
Date Agreement Closed [1] Terminated    
Acquisition of Solar Project Madison in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [2] 2020-07    
Date Agreement Closed [2] 2020-07    
Project Cost [2],[3] $ 165    
MW Capacity | MW [2] 62    
Acquisition Of Solar Project Atlanta Farms In Ohio      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2022-03    
Date Agreement Closed 2022-05    
Project Cost [3] $ 390    
Date of Commercial Operations [4] January 2025    
MW Capacity | MW 200    
Acquisition of Solar Project Foxhound in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2023-03    
Date Agreement Closed 2024-02    
Project Cost [3] $ 195    
Date of Commercial Operations [4] April 2024    
MW Capacity | MW 83    
Virginia Electric and Power Company      
Property Plant And Equipment [Line Items]      
Project Cost $ 40 $ 24 $ 77
Virginia Electric and Power Company | Acquisition of Solar Project Ft. Powhatan in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2019-06    
Date Agreement Closed 2019-06    
Project Cost [5] $ 267    
Date of Commercial Operations January 2022    
MW Capacity | MW 150    
Virginia Electric and Power Company | Acquisition of Solar Project Maplewood in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2019-10    
Date Agreement Closed 2019-10    
Project Cost [5] $ 210    
Date of Commercial Operations December 2022    
MW Capacity | MW 120    
Virginia Electric and Power Company | Acquisition of Solar Project Pumpkinseed in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-05    
Date Agreement Closed 2020-05    
Project Cost [5] $ 138    
Date of Commercial Operations September 2022    
MW Capacity | MW 60    
[1] In January 2023, Dominion Energy terminated its agreement, without penalty, to acquire Hardin II.
[2] Madison was reflected in the Corporate and Other segment before its sale 2024. See Note 3 for discussion.
[3] Includes acquisition costs.
[4] Dominion Energy expects to claim production tax credits on the energy generated and sold by these projects.
[5] Includes acquisition costs.