XML 53 R13.htm IDEA: XBRL DOCUMENT v3.3.0.814
PLANT, PIPELINE AND EQUIPMENT
9 Months Ended
Sep. 30, 2015
PLANT, PIPELINE AND EQUIPMENT [Abstract]  
PLANT, PIPELINE AND EQUIPMENT
5. PLANT, PIPELINE AND EQUIPMENT

Plant, pipeline and equipment consisted of the following:

   
September 30, 2015
  
December 31, 2014
 
   
(thousands of dollars)
 
Platinum catalyst
 $1,612  $1,612 
Land
  4,577   4,577 
Plant, pipeline and equipment
  103,297   95,351 
Construction in progress
  26,808   11,590 
Total plant, pipeline and equipment
  136,294   113,130 
  Less accumulated depreciation
  (44,924)  (39,319)
Net plant, pipeline and equipment
 $91,370  $73,811 

Plant, pipeline, and equipment serve as collateral for our amended and restated loan agreement. See Note 8.

Interest capitalized for construction was approximately $27,000 and $122,000 for the three and nine months ended September 30, 2015.  No amounts were capitalized during 2014.

Construction in progress during the first nine months of 2015 included petrochemical construction on the D-Train expansion, purchase of additional manufacturing equipment such as towers and tanks, additions to the tank farm, and upgrades to the electrical and flaring systems at SHR, as well as equipment for construction on the hydrogenation/distillation project at TC.

Amortization relating to the platinum catalyst which is included in cost of sales was $21,067 for the three months and $63,202 for the nine months ended September 30, 2015, and 2014.