5. PLANT, PIPELINE AND EQUIPMENT

Plant, pipeline and equipment at June 30, 2014, and December 31, 2013, consisted of the following:

   
June 30, 2014
  
December 31, 2013
 
   
(thousands of dollars)
 
Platinum catalyst
 $1,612  $1,612 
Land
  1,577   1,577 
Plant, pipeline and equipment
  73,458   71,115 
Construction in progress
  2,606   824 
Total plant, pipeline and equipment
  79,253   75,128 
  Less accumulated depreciation and amortization
  (36,031)  (33,203)
Net plant, pipeline and equipment
 $43,222  $41,925 

Plant, pipeline, and equipment serve as collateral for a $14.0 million term loan with a domestic bank (see Note 7).

Construction in progress during the first six months of 2014 included preparation for the D-Train expansion, construction of additional warehousing, installation of additional truck loading stations, and various other improvements facility-wide.