5. PLANT, PIPELINE AND EQUIPMENT

Plant, pipeline and equipment at March 31, 2014, and December 31, 2013, consisted of the following:

   
March 31, 2014
  
December 31, 2013
 
   
(thousands of dollars)
 
Platinum catalyst
 $1,612  $1,612 
Land
  1,577   1,577 
Plant, pipeline and equipment
  72,533   71,115 
Construction in progress
  1,123   824 
Total plant, pipeline and equipment
  76,845   75,128 
  Less accumulated depreciation and amortization
  (34,616)  (33,203)
Plant, pipeline and equipment, net
 $42,229  $41,925 

Plant, pipeline, and equipment serve as collateral for a $14.0 million term loan with a domestic bank (see Note 7).

Construction in progress during the first three months of 2014 included preparation for penhex unit expansion, construction of additional warehousing, installation of additional truck loading stations, and upgrades to various processing equipment.

Amortization relating to the platinum catalyst which is included in cost of sales was $21,067 and $9,558 for the three months ended March 31, 2014, and 2013, respectively.