Tasiast Project

Mauritania

National Instrument 43-101 Technical Report

 

 

 

 

 

 

 

 

 

 

 

 

 

Prepared for:

Kinross Gold Corporation

 

Prepared by:

John Sims, AIPG Certified Professional Geologist

 

Effective Date: 30 March 2016

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

C o n t e n t s

 

       
1. SUMMARY 1
  1.1 Executive Summary 1
  1.2 Technical Summary 2
     
2. INTRODUCTION 10
  2.1 Qualified Persons 12
  2.2 Information Sources 12
  2.3 Effective Dates 12
  2.4 Previous Technical Report 12
  2.5 List of Abbreviations 13
     
3. RELIANCE ON OTHER EXPERTS 14
     
4. PROPERTY DESCRIPTION AND LOCATION 15
  4.1 Location 15
  4.2 Mineral Tenure 15
  4.3 Fees, Royalties, Duties and Taxes 19
     
5. ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 22
  5.1 Accessibility 22
  5.2 Climate 22
  5.3 Local Resources and Infrastructure 23
  5.4 Physiography and Environment 25
     
6. HISTORY 26
  6.1 Tenure History 26
  6.2 Project History 26
     
7. GEOLOGICAL SETTING 29
  7.1 Regional Geology 29
  7.2 Property Geology 33
  7.3 Structural Geology 40
  7.4 Mineralization and Alteration 45
     
8. DEPOSIT TYPES 48
     
9. EXPLORATION 49
  9.1 Grids and Surveys 49
  9.2 Geological and Regolith Mapping 49
  9.3 Geochemistry 49
  9.4 Geophysics 49
  9.5 Pits and Trenches 50
  9.6 Drilling 50
  9.7 Bulk Density 50
  9.8 Petrology, Mineralogy and Other Research Studies 50
  9.9 Exploration Potential 51
     
10. DRILLING 53
  10.1 Drilling Methods and Equipment 53

 

 
TOC i

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

  10.2 Collar Surveys 56
  10.3 Down-hole Surveys 57
  10.4 Recovery 57
  10.5 Deposit Drilling 57
  10.6 Geotechnical, Hydrological and Metallurgical Drilling 58
  10.7 Comment on Drill Programs 59
     
11. SAMPLE COLLECTION, PREPARATION, ANALYSES, AND SECURITY 61
  11.1 Sampling Method and Approach 61
  11.2 Analytical Laboratories 66
  11.3 Sample Preparation 67
  11.4 Sample Analysis 68
  11.5 Quality Assurance and Quality Control 69
  11.6 Sample Storage 72
  11.7 Sample Security 72
  11.8 Comment on Sample Collection, Preparation, Analysis and Security 72
     
12. DATA VERIFICATION 74
  12.1 Verification in Support of Technical Reports 74
  12.2 TMLSA QA/QC 76
  12.3 Comment on Data Verification 84
     
13. MINERAL PROCESSING AND METALLURGICAL TESTING 85
  13.1 Mineralogy 85
  13.2 Metallurgical Test Work 85
     
14. MINERAL RESOURCE ESTIMATE 91
  14.1 Database 91
  14.2 Wireframes 93
  14.3 Exploratory Data Analysis 97
  14.4 Variography 102
  14.5 Grade Interpolation 105
  14.6 Bulk Density Modelling 105
  14.7 Mineral Resource Classification 108
  14.8 Block Model Validation 110
  14.9 Mineral Resource Statement 118
  14.10 Comment on Mineral Resources 121
     
15. MINERAL RESERVE ESTIMATE 122
  15.1 Basis of Reserve Estimate and Pit Optimization 122
  15.2 Comment on Mineral Reserves 125
     
16. MINING METHODS 127
     
17. RECOVERY METHODS 141
  17.1 Current Waste Rock Facility 141
  17.2 Current Water Management 141
  17.3 Current Process Plant 141
  17.4 Recovery Methods (30 kt/d) 147
     
18. PROJECT INFRASTRUCTURE 170
     
19. MARKET STUDIES AND CONTRACTS 173
     
20. ENVIRONMENTAL STUDIES, PERMITTING, AND SOCIAL OR COMMUNITY IMPACT 174

 

 
TOC ii

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

  20.1 Environmental Studies 174
  20.2 Permitting 175
  20.3 Socio-Economics 176
     
21. CAPITAL AND OPERATING COSTS 178
  21.1 Capital Costs (Two-phased Expansion) 178
  21.2 Phase One Capital Costs - Basis of Estimate 179
  21.3 Phase Two Capital Costs – Basis of Estimate 182
  21.4 Capitalized Stripping and Sustaining Capital 185
  21.5 Operating Costs 187
     
22. ECONOMIC ANALYSIS 190
  22.1 Key Assumptions 190
  22.2 Presentation of Results (30 kt/d) 194
  22.3 Sensitivity Analysis – Phase One only 197
     
23. ADJACENT PROPERTIES 199
     
24. OTHER RELEVANT DATA AND INFORMATION 200
     
25. INTERPRETATION AND CONCLUSIONS 201
     
26. RECOMMENDATIONS 202
     
27. REFERENCES 203
     
28. DATE AND SIGNATURE PAGE 207

 

 
TOC iii

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

T a b l e s

 

 

Table 1-1: 2015 Tasiast Mineral Resource Statement Exclusive of Reserves 6
Table 1-2: 30 kt/d Reserve Estimate Effective December 31, 2015 7
Table 1-3: Operating Cost Estimates (Expansion Case) 8
Table 1-4: Financial analysis results and sensitivities 9
Table 4-1: Mineral Tenure Summary – Tasiast Property 16
Table 4-2: Permit Boundary Coordinates 17
Table 4-3: Permit Durations in Mauritania 19
Table 4-4: Fees, Royalties, Duties and Taxes 21
Table 6-1: Production Summary 28
Table 10-1: Global and Resource Drill Hole Summary 54
Table 12-1: QA/QC Samples by Laboratory 77
Table 12-2: 2011 QA/QC Samples Analysed by Laboratory 78
Table 12-3: 2011 Resource QA/QC Results 79
Table 13-1: Mine Plan by Lithology 86
Table 13-2: Comminution Characteristics by Lithology 87
Table 14-1: Summary of Drill Hole Database 91
Table 14-2: Lithology codes 94
Table 14-3: Mineralization Domains 94
Table 14-4: Oxide Codes 97
Table 14-5: WB Au Capping Analysis 99
Table 14-6: PP Au Capping Analysis 99
Table 14-7: WB Uncapped Gold Composite Grade Statistics by Domain 100
Table 14-8: WB Capped Gold Composite Grade Statistics by Domain 100
Table 14-9: PP Uncapped Gold Composite Grade Statistics by Domain 101
Table 14-10: PP Capped Gold Composite Grade Statistics by Domain 101
Table 14-11: Summary of Domain Contact Relationship, WB 102
Table 14-12: WB Gold Grade Correlogram Models 104
Table 14-13: PP Gold Grade Correlogram Models 105
Table 14-14: Density Values Assigned to Models - g/cm3 107
Table 14-15: Comparison of Mean Au Grade for OK, ID2 and NN Interpolations 110
Table 14-16: Comparison of WB Statistics for Capped Composites and Model Grades 110
Table 14-17: Comparison of PP Statistics for Capped Composites and Model Grades 111
Table 14-18: Mineral Resource Statement by Area Inclusive of Reserves 119
Table 14-19: Mineral Resource Statement by Material Type Inclusive of Reserves 120
Table 14-20: Cut-Off Grades (Au g/t) 120
Table 14-21: 2015 Tasiast Mineral Resource Statement Exclusive of Reserves 121
Table 15-1: Reserve Estimate Effective December 31, 2015 122
Table 15-2: LG Optimization Parameters 124
Table 15-3: Overall Slope Angles Used in Pit Optimization 125
Table 15-4: Process Recoveries 125
Table 16-1: Material Routing 129
Table 16-2: 30 kt/d Total Mobile Equipment Schedule 130
Table 16-3: Geotechnical Design Parameters, Piment Zone 132
Table 16-4: Geotechnical Design Parameters - West Branch Zone 132

 

 
TOC iv

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 16-5: 30 kt/d Case Mine Production Schedule 137
Table 16-6: 30 kt/d Case Process Plant Feed Schedule 138
Table 16-7: Expansion Mining Personnel by Function by Year 140
Table 16-8: Expansion Expatriate and National Mining Personnel by Year 140
Table 17-1: Metallurgical Recovery by Process 147
Table 17-2: Key Process Design Criteria 149
Table 20-1: Key Operating Permits and Environmental Assessments 176
Table 21-1: Capital Cost Estimate – Phases One and Two 179
Table 21-2: Basis of Estimate – Capital Costs (Phase One) 180
Table 21-3: Basis of Estimate – Capital Costs (Phase Two) 183
Table 21-4: Annual Non-sustaining Capitalized Stripping 186
Table 21-5: Annual Sustaining Capital 186
Table 21-6: Basis of Estimate – Operating Costs 187
Table 21-7: Operating Cost Estimates (January 1, 2016 forward) 189
Table 22-1: Financial model key assumptions 190
Table 22-2: Financial analysis results and sensitivities (April 1, 2016 forward) 194
Table 22-3: Life of Mine Cash Flows 195
Table 22-4: Cash Cost per ounce and All-in Sustaining Cost per ounce 195
Table 22-5: Project Economics Sensitivity to Oil Price 196
Table 22-6: NPV Sensitivity to Dilution 196
Table 22-7: Financial analysis results and sensitivities (Phase One only, April 1, 2016 forward) 197
Table 22-8: Life of Mine Cost and Production Summary (Phase One only, January 1, 2016 forward) 198

 

F i g u r e s

 

 

Figure 2-1: Project Location Plan 11
Figure 4-1: Tenure Location Plan 16
Figure 5-1: Mine Site Infrastructure Layout Plan 24
Figure 7-1: Geology of the West African Craton. Modified from Fabre (2005) 31
Figure 7-2: Tasiast Geology Overlain on Worldview-2 Satellite Imagery 32
Figure 7-3: Precambrian Stratigraphy of the Aouéouat Greenstone Belt 33
Figure 7-4: Plan Map of the Main Structural Features 35
Figure 7-5: Geological Plan View of West Branch and Piment 36
Figure 7-6: Interpreted Structural Profile at 72,000N 37
Figure 7-7: Profiles through the Greenschist Zone at West Branch at 71,411N 42
Figure 7-8: Profiles through the Greenschist Zone at West Branch at 71,811N 43
Figure 7-9: Profiles through the Greenschist Zone at West Branch at 71,061N 44
Figure 9-1: Levelled Gold in Soil Grid 52
Figure 12-1: Standard Control Plot for Standard G305-2 Results from SGS Kayes 80
Figure 12-2: Blank control plot for Blank results from SGS Kayes 81
Figure 13-1: Gold Recovery as a Function of Grind and Leach Retention 88
Figure 13-2: Gold Grade vs. Recovery Relationship 89
Figure 14-1: Tasiast Satellite Deposits 92
Figure 14-2: West Branch Mineralization Plan and Section Views 95
Figure 14-3: Piment Mineralization Plan and Section Views 96

 

 
TOC v

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-4: WB Resource Classification, 95 m Elevation 109
Figure 14-5: PP Resource Classification, 95 m Elevation 109
Figure 14-6: 3D View of DOM6_1 and Swath Plot by Easting 112
Figure 14-7: DOM6_1 Swath Plots by Northing and Elevation 113
Figure 14-8: 3D View of DOM6_2 and Swath Plot by Easting 114
Figure 14-9: DOM6_2 Swath Plots by Northing and Elevation 115
Figure 14-10: WB DOM6_1 Herco Grade-Tonnage Curves 117
Figure 16-1: Excavators and Haul Trucks Working in West Branch Pit 127
Figure 16-2: Plan View of Tasiast pits 131
Figure 16-3: Comparison of Designed Ultimate Pit versus LG Pit Shell 134
Figure 16-4: Piment and West Branch Mining Limits and Infrastructure Layout 136
Figure 17-1: 8 kt/d Plant Process Flowsheet 144
Figure 17-2: West Branch Solution Ponds and ADR Plant 146
Figure 17-3: Phase One CIL Plant Layout (12 kt/d) 150
Figure 17-4: Phase Two CIL Plant Layout (30 kt/d) 151
Figure 17-5: Phase One, 12 kt/d Plant Flowsheet 153
Figure 17-6: Phase Two, 30 kt/d Plant Flowsheet 154
Figure 17-7: Conceptual Ore Stockpile 156
Figure 17-8: Conceptual Cyanide Destruction Layout 160
Figure 17-9: Conceptual Cyanide Handling Area 165
Figure 17-10: Conceptual Flocculant Preparation System 166
Figure 17-11: Commissioning Schedule 169

 

 
TOC vi

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

1.summary

 

1.1Executive Summary

 

Kinross has prepared a Technical Report for the wholly-owned Tasiast gold deposit (the Project) located in the Islamic Republic of Mauritania (Mauritania), Africa. Kinross is using this Technical Report to support disclosure of mineral resources and mineral reserves at the Project. The Technical Report conforms to National Instrument 43-101 Standards of Disclosure for Mineral Projects (NI 43-101) and has an effective date of March 30, 2016. Kinross will be using this Technical Report to support disclosure of mineral resources and mineral reserves at the Project.

 

In March 2014, Kinross completed a feasibility study to expand Tasiast operation to 38 kt/d. Due to the lower gold prices in 2015, Kinross suspended the expansion to 38 kt/d and initiated a Tasiast optimization study to explore alternatives for Tasiast’s growth potential in the current gold price environment. The Tasiast optimization study recommended a two-phased expansion that leverages the existing mill infrastructure. Phase One of the expansion increases the mill throughput from the current 8 kt/d to 12 kt/d. Phase Two increases the mill throughput from 12 kt/d to 30 kt/d with the installation of additional milling, leaching, thickening and refinery capacity.

 

In 2015, Kinross initiated a feasibility study to assess the economic viability of Phase One and a pre-feasibility to assess the economic viability of Phase Two. The studies concluded with a recommendation to progress with Phase One into execution and advance Phase Two into a feasibility study. The mine plan, production schedule and reserves statement in this report are based on the 30 kt/d (Phase Two) pre-feasibility study.

 

The Project is located in north-western Mauritania and contains several gold deposits. The Tasiast mine and the mining permit are owned by Tasiast Mauritanie Limited S.A. (TMLSA). Two sister companies of TMLSA hold adjacent permits. Société d’Extraction du Nord de l’Inchiri S.A. (SENISA) holds two recently converted mining permits (for the Tmeimichat and Imkebdene areas) and Tasiast Mauritanie Limited (TML) holds two exploration permits (Tasiast Sud and N’Daouas-Est areas). All four are contiguous to the Tasiast mining permit lands (collectively, the Tasiast Lands). As part of the recently completed conversion process, Kinross has undertaken to transfer to the Government of Mauritania a 10% carried interest in SENISA. Other than SENISA, all permit-holding affiliates of Kinross, including TMLSA, are wholly-owned indirect subsidiaries of Kinross. Kinross acquired TMLSA, including the Tasiast operation and exploration permits and lands, through its acquisition of Red Back in September 2010.

 

There are exploration prospects in the 312 km2 El Ghaîcha Mining permit and in the surrounding permits. Commercial production of gold at Tasiast began in January 2008, and a total of 1,613,724 oz. was produced by the end of 2015.

 

 
Page 1

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

1.2Technical Summary

 

Property Description, Location and Land Tenure

 

The Project is located in northwestern Mauritania, approximately 300 km north of the capital Nouakchott and 250 km southeast of the major city of Nouadhibou. The Tasiast Lands are accessed from Nouakchott by using the paved Nouakchott to Nouadhibou highway for 370 km and then via 66 km of graded mine access road, which is maintained by TMLSA. There is an airstrip at the mine site that is used for light aircraft travelling to and from Nouakchott.

 

Mining operations commenced in 2007, with commercial production reached in January 2008. Infrastructure on site supports an open pit mining operation and associated processing facilities consisting of a 3 Mt/a carbon-in-leach (CIL) mill and a run of mine (ROM) dump leach.

 

TMLSA holds a valid mining permit, PE 229 (El Ghaîcha), covering 312 km2 granted in January 2004 and valid for a period of 30 years. The mining operations and infrastructure lie entirely within the lands subject to the mining permit. There are also four additional contiguous permits (3,118 km2), each of which is in good standing. The Tasiast Lands fall within the administrative purview of the Inchiri and Dakhlet Nouadhibou Districts, with PE 229 within the Inchiri District only.

 

Surface and Water Rights

 

Surface rights are granted along with permit PE 229 and are paid annually as determined by decree under the Mauritanian Mining Code. Surface rights for the permit are in good standing.

 

Three iron ore exploration permits overlap mining permit PE 229, entitling their holders to do exploration works, as long as they do not interfere with TMLSA’s operations. TMLSA does not have any obligation to accommodate the holders of these permits.

 

These holders are not entitled to transform these explorations permits into mining permits on the overlapping area without TMLSA’s prior written approval, and they are not entitled to any compensation from TMLSA.

 

The operation’s water supply is located 64 km west of the mine and consists of a bore field of 47 wells in a semi-saline aquifer. Water is pumped from the bore field to the mine.

 

Royalties

 

A royalty equal to 3% of the gross revenue of TMLSA is payable to the government. In addition, Franco-Nevada Corporation (Franco-Nevada) holds a 2% net smelter return royalty on gold production in excess of 600,000 ounces. Production at Tasiast reached 600,000 ounces in July 2011 and the first royalty payment to Franco-Nevada was made in October 2011.

 

 
Page 2

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Permits

 

Exploration, development and mining activities to date have been performed under the appropriate permits, laws and regulations.

 

Environment

 

An environmental impact statement (EIS) was completed for the Project in 2004 and subsequently approved by the Director of Mines and Geology on 12 April 2005. To meet revised legislation, additional reporting was requested, which was completed in 2008. In 2009, an additional environment assessment was conducted for a second tailings storage facility, a dump leach facility and an expansion of the water bore field. The West Branch expansion was assessed in 2010, and subsequently approved in 2011.

 

Since acquiring Tasiast, in support of the expansion project, TMLSA has completed significant permitting activities including Phase 1 (two Environmental Impact Notices (EINs) and one Environmental Impact Assessment (EIA)) in 2011 and Phase 2 (EIA for all on-site proposed expansion activities) in 2012. A Phase 3 EIA for “off-site” sea water supply was approved following submission of a Phase 3 addendum. A subsequent EIA was approved to allow receipt of pre-assembled equipment at a beach landing and transportation to site. In addition, following discussion with the government, an addendum to the Phase 2 EIA was submitted and approved that described the project optimization through incremental increases in production and relocation of certain infrastructure. This addendum was approved by the Ministry of Environment in February 2016 and subsequent approval by the Ministry of Mines is pending.

 

Current environmental liabilities are those that would be expected from a mining operation, and include the mine, crushing and CIL processing plant, dump leach facilities, power plant, tailings and waste rock facilities, power grids, roads, accommodation camp, ancillary facilities and drill pads established to support mining and exploration activities.

 

Geology and Mineralization

 

The Tasiast Lands consist of three main Precambrian greenstone belts located in the western compartment of the Reguibat Shield. The Reguibat Shield consists of a series of west to east accreted, north-south trending Archaean and Lower Proterozoic metavolcano-sedimentary belts and domal basement gneiss complexes.

 

The Tasiast Lands are underlain by the Aouéouat greenstone belt, a north-south trending belt that is continuous for 75 km strike length on the Tasiast Lands and that may continue further to the north and south. The mine geology is characterized by a mafic to felsic metavolcano-sedimentary succession that is overlain by an iron stone formation and epiclastic units. The rocks have undergone deformation, were metamorphosed to greenschist and lower amphibolite grades and were cut by volumetrically minor younger mafic dikes. Three main prospective trends are recognized at the property with all known

 

 
Page 3

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

deposits spatially associated with the Tasiast trend. Other trends also contain gold occurrences but have been significantly under-explored relative to the Tasiast trend.

 

Known deposits are aligned along a north-trending corridor with a strike length of approximately 30 km, with the Piment deposits at the northern half of the mine area and West Branch deposits at the southern half. At West Branch, first-order structural controls on mineralization include several subparallel anastomosing faults and several generations of veins developed predominantly in altered mafic meta-igneous and metavolcanic units locally called the Greenschist Zone. Mineralization at Piment is principally controlled by several anastomosing faults developed within the hanging wall block of iron formation, felsic metavolcanic and epiclastic rocks. Veins are spatially associated with mineralization over horizontal widths of up to 20 m.

 

Gold mineralization has been defined to vertical depths of at least 740 m. All of the significant mineralized bodies defined to date dip moderately (45º to 60º) to the east and have a south-southeasterly plunge. Most of the gold mineralization at West Branch is hosted in hydrothermally altered meta-igneous rocks (Greenschist zone) containing quartz-carbonate veins. The meta-igneous rocks are enveloped by felsic units known as felsites that occur on the footwall and hanging wall sides of the Greenschist zone. The Greenschist zone is characterized by consistently thick intervals of mineralization averaging 40 m to 100 m thick. Individual shoots are continuous over a strike length of at least 1,000 m. Mineralogy within the Greenschist package is dominated by pyrrhotite, pyrite and native gold that occur as vein infill or alteration spots commonly in and around the foliation. Pyrrhotite and pyrite occur together in many places but in variable ratios. Zones of pyrite-only and pyrrhotite-only sulphide facies are rare.

 

Piment mineralization is largely hosted along fault splays and within the adjacent altered and veined iron formation and epiclastic units. Individual mineralized shoots are continuous over 300 m and to vertical depths of at least 260 m. The minerals associated with gold at Piment are pyrrhotite and pyrite.

 

History and Exploration

 

Exploration programs have included geological and regolith mapping, satellite image interpretation, airborne and ground magnetic geophysical surveys, soil, rock chip, and grab geochemical sampling, trenching, reverse circulation (RC) and core drilling, engineering studies, metallurgical test work, and specialist geological studies such as ore and alteration petrography. Work was completed by the Office Mauritanien de Recherches Géologiques (OMRG), Normandy LaSource Development Ltd. (NLSD), Midas Gold plc. (Midas), Geomaque Explorations Inc. (Geomaque), Defiance Mining Corporation (Defiance), Rio Narcea Gold Mines Ltd. (Rio Narcea), Red Back and Kinross.

 

Exploration Potential

 

Mineralization remains open both laterally and vertically at the Tasiast deposits. Shallow reconnaissance RC drilling across district targets has detected gold mineralization that

 

 
Page 4

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

requires follow-up exploration. The potential to delineate additional resources both at the Tasiast mine and the district targets is considered good. Some of these district targets are described below.

 

Drilling uncovered encouraging gold results at the C67-Fennec sector and Tasiast Sud (previously named Charlize) targets, located 5 km north and 15 km south of Tasiast. Drilling has also intersected encouraging gold grades at the Tmeimichat and Imkebdene permitted areas, situated approximately 10 km north of the mine site.

 

At the Tasiast Sud targets, mineralization occurs near the surface in banded iron/magnetite (BIM) rocks that are part of the same mineralized BIM sequence further north at Tasiast. Mineralization has also been identified in sheared amphibolites that host quartz-carbonate veins where they are thrust over younger metasedimentary rocks. Gold mineralization at C67 is hosted by sheared and veined mafic metavolcanic rocks and by quartz diorites that may be intrusive into the metavolcanics. The gold is associated with quartz-carbonate veins that formed during the late stages of shearing. Besides quartz and carbonates, the vein mineralogy consists of pyrrhotite, pyrite, biotite and locally tourmaline. Pyrrhotite is generally more abundant than pyrite where significant gold grades are present. The structures controlling mineralization are moderately to steeply west-dipping shear zones that define a trend that is parallel to, but to the east of the Tasiast trend.

 

The Project area has considerable additional exploration potential as illustrated by the extensive gold anomalies in soil maps. Several areas have been identified by TMLSA on the current Tasiast permits for near term drill testing. Targeting incorporates all available data sets including satellite imagery (Worldview-2), regional gold-in-soil data, airborne geophysical data (high resolution aeromagnetics and VTEM), regional scale geological maps of two generations, several generations of target scale geological maps, multi-element geochemical data derived from RC drill chips, assay results derived from historical and recent property scale drilling and trenching, reconnaissance geological observations and prospecting.

 

Drilling

 

The total number of drill holes completed on the Project totals 15,141 holes (43 rotary air blast (RAB), 14,133 RC and 762 core) for an aggregate total of 1,622,722 m. Resource drilling campaigns completed between 1999 and 2013 comprise 3,890 RC (620,106 m) and 473 core holes (207,803 m) for a total of approximately 827,909 m.

 

Drill programs were completed primarily by contract drill crews, supervised by geological staff of the Project operator. Where programs are referred to by company name, that company was the Project manager at the time of drilling and was responsible for the collection of data. Collar locations were surveyed by site surveyors using DGPS instruments. Down-hole surveys were mostly (+65%) completed using single shot reflex and north seeking gyroscope instruments. Core recoveries are typically greater than 93%.

 

 
Page 5

 

 
 

 

(KINROSS LOGO)

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Mineral Resource

 

The Tasiast mineral resource statement, as of year-end 2015, comprises Measured, Indicated and Inferred resources. Mineral resources were classified in accordance with the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves, incorporated by reference into NI 43-101. Mineral resources have an effective date of December 31, 2015.

 

Mineral Resources are stated at variable cut-off grades, dependent on the metallurgical type, mining operating cost and variable process recoveries. The cut off grades were determined using a gold price of $1,400/oz.

 

The mineral resources were reported below the projected December 31, 2015 mined surface and are constrained using the Lerchs-Grossman (LG) 30 kt/d pit shell designed by Kinross Technical Services. Kinross cautions that mineral resources that are not mineral reserves do not have demonstrated economic viability.

 

Table 1-1 shows the classified mineral resources, exclusive of reserves.

 

Table 1-1: 2015 Tasiast Mineral Resource Statement Exclusive of Reserves

 

Classification

Tonnes 

(000’s) 

Grade  

(Au g/t)

Ounces

(000’s)

Measured 8,611 0.83 230
Indicated 66,236 1.40 2,980
Subtotal M&I 74,847 1.33 3,210
Resource Stockpile 293 0.63 6
       
Inferred 5,596 1.92 346

 

1.Mineral Resources that are not Mineral Reserves are not required to demonstrate economic viability.

2.Mineral Resources are reported below the 31 December 2015 mined surface and are constrained using an optimized Lerchs-Grossman pit shell.

3.Mineral Resources are reported to cut-off grades ranging from 0.55 g/t to 0.60 g/t Au for CIL and from 0.37 g/t to 0.49 g/t Au for dump leach based on a gold price of US$1,400/oz.

4.Stockpile balance above 0.7 g/t cut-off grade is considered as reserve, while below 0.7 g/t is considered as resource. Measured Resource includes the Resource Stockpile.

5.The above mineral resource estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

Estimation of the Tasiast mineral resources was based on a combination of development alternatives that assumed two potential processing options. These included CIL milling of fresh and high grade oxide resource and dump leaching for lower grade oxide material. The various processing recoveries and associated operating conditions were used to generate an optimized pit shell using an LG optimization algorithm.

 

 
Page 6

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Mineral Reserve

 

Mineral reserves for the Project incorporate appropriate allowances for mining dilution and mining recovery for the selected mining method. Mineral reserves have an effective date of December 31, 2015 and are summarized in Table 1-2.

 

Table 1-2: 30 kt/d Reserve Estimate Effective December 31, 2015.

 

Classification

Tonnes 

(000’s)

Grade 

(Au g/t)

Ounces  

(000’s)

Proven 30,467 1.44 1,406
Probable 101,711 2.08 6,813
TOTAL 132,178 1.93 8,219
Reserve Stockpile  8,045 1.02 264

  

1.Mineral Reserves are reported to a cut-off grade of 0.7 g/t Au for CIL and 0.40 g/t Au for dump leach based on a gold price of US$1,200/oz less 5% gross royalty.

2.Stockpile balance above 0.7 g/t cut-off grade is considered as reserve, while below 0.7 g/t is considered as resource. Proven Reserve includes the Reserve Stockpile.

3.The Reserves Estimate assumes expansion to a 30 kt/d mill.

4.The above mineral reserve estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

Mining Operations

 

The Tasiast mine is a conventional open pit truck-and-shovel operation that would move up to approximately 100 Mt/a over a 12 year mine life. The current mining operation sustains a 3 Mt/a ore feed to the existing carbon-in-leach (CIL) process plant, plus low-grade oxide ore feed to a dump leach process. Reclaiming stockpiles adds an additional two years of production through the CIL plant after mining is finished. The introduction of larger mining equipment has shifted the mining strategy from a highly selective mining practice to a combination of both bulk and selective mining. The design operating bench height is 10 m in West Branch and 5 m in the Piment pits. If required, sections of the footwall zone in West Branch may be mined on 5 m benches to improve ore selectivity.

 

Recovery Methods

 

Kinross will transition from the existing Tasiast 8 kt/d CIL plant through the start-up of the Phase One, 12 kt/d process plant optimization front end, finishing with the Phase Two, 30 kt/d full facility. The 30 kt/d plant will be in the same area and will incorporate the 12 kt/d plant.

 

In Phase One, a new front end gyratory crusher and a 40ft x 25ft, 26.5 MW Gearless Mill Drive (GMD) Semi-Autogenous Grinding (SAG) mill will be incorporated with additional leaching capacity to the existing 8 kt/d plant to increase capacity to 12 kt/d.

 

Phase Two will consist of the addition of: a 27 ft x 46 ft, 20.5 MW GMD ball mill, larger pebble crusher, pre-leach and tailings thickeners, leach tanks, CIL (carbon in leach) tanks, gravity circuit consisting of centrifugal concentrators and intensive leach cyanidation, elution circuit, gold room, cyanide destruction system, and reagent mixing

 

 
Page 7

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

storage and distribution. Phase Two will include the necessary upgrades to consumable storage and utilities to facilitate full operation. The plant design life is 15 years.

 

Market Studies and Contracts

 

Kinross typically establishes refining agreements with third-parties for refining of doré. Kinross’s bullion is sold on the spot market, by marketing experts retained in-house by Kinross. The terms contained within the sales contracts are typical and consistent with standard industry practice, and are similar to contracts for the supply of doré elsewhere in the world.

 

Capital and Operating Costs

 

For the 30 kt/d case, the total going forward capital cost estimate is $920 million. The scope for this expansion capital cost estimate includes a new front end gyratory crusher, a SAG mill, a new ball mill, expanded leaching, power generation and tailings capacity, additional mining equipment, upgraded water supply infrastructure, and investment in ancillary facilities. This sum is in addition to $547 million of capital stripping in the 2016 to 2019 time frame.

 

Operating cost estimates are shown in Table 1-3. The operating costs for each area include allocations for power plant operating costs.

 

Table 1-3: Operating Cost Estimates (Expansion Case)

 

Operating Cost Unit

Phase One in operation 

2018-20191

Phase Two in operation 

2020-2030

Life-of-
Mine
Average
2016-2030

Mining (incl. stripping) US$/t mined2 1.98 2.37 2.25
Processing (Mill) US$/t processed 18.59 15.16 15.77
Processing (Dump Leach) US$/t processed3 N/A N/A 33.34
Site Admin million US$/a 61 48 55
Other US$/oz sold 70 69 70

 

1. Includes the 6-month Phase Two ramp-up (July 2019 to December 2019)

2. Excludes capitalized maintenance.

3. Limited tonnes placed on dump leach in 2016. Dump leach is decommissioned at the end of 2016. 

 

 
Page 8

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Economic Analysis

 

The economics of the Tasiast Expansion Project were evaluated using a real (non-escalated), after-tax discounted cash flow (DCF) model on a 100% project equity (unlevered) basis. Production, revenues, operating costs, capital costs and taxes were considered in the financial model. The main economic assumptions are a US$1,200/oz gold price and a 5% discount rate.

 

The valuation date for the financial analysis was set for April 1, 2016. All cash flows assumed for the purposes of this study are from this date onward. The cash flow analysis was used to estimate the economics of the 30 kt/d plant expansion.

 

The results of the financial analysis, with sensitivities to gold price and discount rate assumptions, are shown in Table 1-4, based on $1,200/oz gold, a real discount rate of 5%, and an oil price of $45/bbl except as stated in the last row. The project is economic using these assumptions.

 

Table 1-4: Financial analysis results and sensitivities

 


Financial metric
Unit Gold Price (US$/oz)
1,100 1,200 1,300 1,500
NPV at 0% discount rate US$ billion 1.05 1.61 2.16 3.25
NPV at 5% discount rate US$ billion 0.48 0.89 1.27 2.06
NPV at 10% discount rate US$ billion 0.10 0.40 0.69 1.28
Internal rate of return % 12 17 22 33
Payback year (undiscounted) Year 2024 2022 2022 2021
NPV at 5% discount rate; $65/bbl (WTI) Oil US$ billion 0.34 0.74 1.14 1.91

  

Conclusions

 

The project economics, as stated at a 5% discount rate and a $1,200 base case gold price, are robust and offer significant potential.

  

Recommendations

 

It is recommended that Kinross proceed with the Phase One expansion to a 12 kt/d plant and conduct a Feasibility Study of the 30 kt/d plant, to further refine the design that was summarized in this report based on the 30 kt/d Pre-feasibility Study.

 

 
Page 9

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

2.Introduction

 

Kinross has prepared a Technical Report for the wholly-owned Tasiast gold deposit (the Project) located in the Islamic Republic of Mauritania (Mauritania), Africa (Figure 2-1). Kinross is using this Technical Report to support disclosure of mineral resources and mineral reserves at the Project. The Technical Report conforms to National Instrument 43-101 Standards of Disclosure for Mineral Projects (NI 43-101) and has an effective date of March 30, 2016.

 

In March 2014, Kinross completed a feasibility study to expand Tasiast operation to 38 kt/d. Due to the lower gold prices in 2015, Kinross suspended the expansion to 38 kt/d and initiated a Tasiast optimization study to explore alternatives for Tasiast’s growth potential in the current gold price environment.

 

The Tasiast optimization study recommended a two-phased expansion that leverages the existing mill infrastructure. Phase One of the expansion increases the mill throughput from the current 8,000 t/d to 12,000 t/d. Phase Two increases the mill throughput from 12,000 t/d to 30,000 t/d with the installation of additional milling, leaching, thickening and refinery capacity.

 

In 2015, Kinross initiated a feasibility study to assess the economic viability of Phase One and a pre-feasibility to assess the economic viability of Phase Two. The studies concluded with a recommendation to progress with Phase One into execution and advance Phase Two into a feasibility study. The mine plan, production schedule and reserves statement in this report are based on the 30,000 t/d (Phase Two) pre-feasibility study.

 

All measurement units used in this Technical Report are metric, and currency is expressed in US dollars unless stated otherwise. Mauritania uses the Ouguiya (MRO) as its currency.

 

Information used to support this Technical Report has been derived from the reports and documents listed in the References section of this Technical Report.

 

The use of the terms “we”, “us”, “our” or “Kinross” in this Technical Report refer to Kinross Gold Corporation.

 

 
Page 10

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 2-1: Project Location Plan

 

(MAP)

 

 
Page 11

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

2.1Qualified Persons

 

The Qualified Person (QP) for this Technical Report is John Sims, AIPG Certified Professional Geologist and Vice President, Technical Services for Kinross.

 

Mr. Sims visited the site most recently in June 2012. During the site visit, Mr. Sims inspected core and surface outcrops, drill platforms and sample cutting and logging areas; discussed geology and mineralization with Project staff; reviewed geological interpretations with staff; and inspected the major infrastructure and current mining operations. There have been no material changes in site conditions since Mr. Sims’ most recent site visit. All sections in this Technical Report have been prepared under the supervision of Mr. Sims.

 

2.2Information Sources

 

Information used to support this Technical Report was derived from previous technical reports on the property, and from the reports and documents listed in the References section of this Technical Report.

 

Mineral Resources: The mineral resource estimates included in this report were prepared by Tim Maunula of T. Maunula & Associates Consulting Inc., an independent consulting firm. Mr. Maunula is a registered Professional Geoscientist in Ontario. Mr. Maunula visited the site in November and December of 2013.

 

Mineral Reserves / Mining: The mineral reserve estimate included in this report was prepared under the supervision of Todd Carstensen, Director, Mine Planning, Kinross Technical Services. Mr. Carstensen is a Society for Mining, Metallurgy & Exploration (SME) Registered Member. Mr. Carstensen visited the site in June 2014.

 

2.3Effective Dates

 

The effective date of this Technical Report is March 30, 2016, and for the Tasiast expansion mineral resources and mineral reserves the effective date is December 31, 2015.

 

There were no material changes to the information on the Project between the effective date and the signature date of the Technical Report.

 

2.4Previous Technical Report

 

Sims, J., 2014: Tasiast Mine, Mauritania 43-101F1 Technical Report, effective date March 31, 2014.

 

 
Page 12

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

2.5List of Abbreviations

 

m micron km2 square kilometre
°C degree Celsius kt/d thousand tonnes per day
°F degree Fahrenheit kPa kilopascal
a annum kWh/t kilowatt-hour per tonne
Ai Abrasion index kW kilowatt
Au gold kWh kilowatt-hour
bbl barrels L liter
Btu British thermal units LFO light fuel oil
BV/h bed volumes per hour L/s liters per second
BWI Bond ball mill work index m metre
C$ Canadian dollars M mega (million)
CIL carbon-in-leach m2 square metre
cm centimetre m3 cubic metre
cm2 square centimetre Ma Mega-annum (millions of years before present)
CNWAD Cyanide Weak Acid Dissociable mbgl metres below ground level
CWI crusher work index min minute
d day masl metres above sea level
dia. diameter mm millimetre
DWI drop weight index Mt/a million tonne per year
EPC Engineering, Procurement and Construction MTO material take-off
EPCM Engineering, Procurement and Construction Management MW megawatt
ft foot MWe megawatt-electrical
ft/s foot per second m3/h cubic metres per hour
ft2 square foot opt ounce per short ton
ft3 cubic foot oz Troy ounce (31.1035 g)
g gram P&ID Piping and Instrumentation Diagram
G giga (billion) ppm part per million
g/L gram per liter psig pound per square inch gauge
g/t gram per tonne RL relative elevation
Gal Imperial gallon RWI rod mill work index
Ga Giga-annum (billions of years before present) s second
GMD gearless mill drive SG specific gravity
Gpm Imperial gallons per minute st short ton
gr/ft3 grain per cubic foot t metric tonne
gr/m3 grain per cubic metre t/a metric tonne per year
Ha hectare t/d metric tonne per day
HFO heavy fuel oil US$ United States dollar
hp horsepower USg United States gallon
in inch USgpm US gallon per minute
in2 square inch V volt
J joule WBS work breakdown structure
k thousand (kilo) wmt wet metric tonne
kg kilogram yd3 cubic yard
km kilometre yr year
km/h kilometres per hour    

 

 
Page 13

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

3.RELIANCE ON OTHER EXPERTS

 

In the preparation of the Technical Report, the Qualified Person relied on information provided by internal Kinross legal counsel for the discussion of legal matters in Sections 4, 19, and 20.

 

Except for the purposes legislated under provincial securities law, any other use of this report by any third parties is at this party’s sole risk.

 

 
Page 14

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

4.property description and location

 

4.1Location

 

The Tasiast Lands are located in northwestern Mauritania, approximately 300 km north of the capital Nouakchott and 250 km southeast of the major city of Nouadhibou. The Tasiast Lands fall within the Inchiri and Dakhlet Nouadhibou Districts. The Tasiast mine is located at 446600E, 2275600N (UTM, WGS84, Zone 28N).

 

4.2Mineral Tenure

 

The Tasiast mine is owned and operated by Tasiast Mauritanie Ltd. S.A. (TMLSA), a wholly owned subsidiary of Kinross, under exploitation Permit No. 229.

 

The Tasiast mine is located within the 312 km2 Tasiast exploitation permit of El Ghaîcha. The mining operations and infrastructure are located entirely within the lands subject to the mining/exploitation permit (permis d’exploitation or PE). Exploitation permit No. 229 is located centrally within a surrounding permit block of four contiguous exploitation and exploration permits, totalling 3,118 km2, as listed in Table 4-1 and shown in Figure 4-1. All these permits are in good standing. The table also indicates tenure expiry dates. The Tasiast mine and the exploitation permit are owned by TMLSA.

 

The adjacent four permits, the underlying lands of which are contiguous to the Tasiast exploitation permit lands, are held by two sister companies of TMLSA. Société d’Extraction du Nord de l’Inchiri S.A. (SENISA) holds two recently converted mining permits (for the Tmeimichat and Imkebdene areas) and Tasiast Mauritanie Limited (TML) holds two exploration permits (Tasiast Sud and N’Daouas-Est areas). As part of the recently completed conversion process of two exploration permits, Kinross has undertaken to transfer to the Government of Mauritania a 10% carried interest in SENISA. Other than SENISA, all permit-holding affiliates of Kinross, including TMLSA, are wholly-owned indirect subsidiaries of Kinross. Kinross acquired TMLSA, including the Tasiast operation and exploration permits and lands, through its acquisition of Red Back Mining Inc. (Red Back) in September 2010.

 

Tenure coordinates are shown in Table 4-2. A permit boundary is defined by a list of the coordinates of its corners or pillar points. The boundaries are not physically marked on the ground, and have not been surveyed. However, extensive surveying has been conducted within both the exploitation permit No. 229 and adjoining exploration permits. To date, approximately 30,000 points have been located via formal surveying by qualified surveyors using Electronic Distance Meter total station instruments, and many additional points have been picked up by differential global positioning system (GPS) and GPS methods. All the known gold deposits are well inside the boundaries, and the

 

 
Page 15

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

size and shape of the exploitation permit are adequate for the intended exploration, mining and processing activities.

 

Table 4-1: Mineral Tenure Summary – Tasiast Property

 

Name   District   Type   No.   km2   Granted   Expiry

Tasiast

(El Ghaîcha)

  Wilaya de l’Inchiri   Mining Permit   PE 229   312   January 19, 2004   January 9, 2034
                         
Imkebdene   Wilayas Dakhlet Nouadhibou et Inchiri   Mining Permit   PE 2018C2   539   December 1, 2014   December 1, 2044
                         
Tmeimichat   Wilaya de l’Inchiri   Mining Permit   PE 2019C2   746   December 1, 2014   December 1, 2044
                         
Tasiast Sud   Wilayas Dakhlet Nouadhibou et Inchiri   Exploration Permit   PRM 428 B2   355   April 2, 2008   October 14, 2017
                         
N’Daouas   Wilaya de l’Inchiri   Exploration Permit   PRM 437 B2   1,478   April 2, 2008   October 14, 2017

 

Figure 4-1: Tenure Location Plan

 

(Map) 

 

 
Page 16

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 4-2: Permit Boundary Coordinates

 

Name Permit Number for Group 2 Minerals Point Coordinates Coordinates
UTM (E) UTM (N)
El Ghaîcha PE 229 C2 A 441000 2287000
    B 454000 2287000
    C 454000 2263000
    D 441000 2263000
Imkebdene PE 2018 C2 A 435000 2311000
    B 446000 2311000
    C 446000 2287000
    D 441000 2287000
    E 441000 2263000
    F 445000 2263000
    G 445000 2258000
    H 432000 2258000
    I 432000 2285000
    J 435000 2285000
Tmeimichat PE 2019 C2 A 446000 2330000
    B 460000 2330000
    C 460000 2263000
    D 454000 2263000
    E 454000 2287000
    F 446000 2287000
Tasiast Sud PRM 428 A 460000 2263000
  B 460000 2248000
  C 432000 2248000
  D 432000 2258000
  E 445000 2258000
  F 445000 2263000
N’Daouas PRM 437 B2 A 460000 2322000
  B 500000 2322000
  C 500000 2303000
  D 495000 2303000
  E 495000 2300000
  F 488000 2300000
  G 488000 2293000
  H 484000 2293000
  I 484000 2280000
  J 490000 2280000
  K 490000 2270000
  L 480000 2270000
  M 480000 2260000
  N 473000 2260000
  O 473000 2264000
  P 476000 2264000
  Q 476000 2268000
  R 477000 2268000
  S 477000 2271000
  T 479000 2271000
  U 479000 2283000
  V 460000 2283000

 

 
Page 17

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Surface rights are granted along with Permit No. 229, and applicable fees are paid annually, as determined by decree under the Mining Code. Surface rights for the permit are in good standing, and there are no competing mining rights in the area, except for three iron-ore explorations permits that overlap mining permit PE 229. These permits entitle their holders to do exploration work, as long they do not interfere with TMLSA’s operations. TMLSA does not have any obligation to accommodate the holders of these permits.

 

The iron-ore exploration permit holders are not entitled to transform their overlapping exploration permits into exploitation permits on the overlapping area without TMLSA’s prior written approval, and they are not entitled to any compensation from TMLSA.

 

Exploration permits (Permis de Recherche Minière or PRM) grant exclusive exploration rights over a specific block (maximum 1,000 km2) and are granted for a three-year period, renewable twice for up to three years at each renewal. Exploitation permits are granted for 30 years, and are renewable for periods of 10 years each. A condition of each permit is that the holder is required to hire Mauritanian tradespersons to provide services, and to contract with national suppliers and businesses in preference to foreign service providers, where the national suppliers and businesses can offer at least the same terms, quality and pricing. Table 4-3 summarizes the durations of exploration and mining permits in Mauritania. Operating permits are discussed in Section 20.2.

 

Current environmental liabilities are those that would be expected from a mining operation, and include the mine, crushing and CIL processing plant, dump leach facilities, power plant, tailings and waste rock facilities, power grids, roads, accommodation camp, ancillary facilities and drill pads established to support mining and exploration activities.

 

 
Page 18

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 4-3: Permit Durations in Mauritania

 

Licence Type Duration Renewal Period Number of Permissible
Renewals
Rules and mechanisms
Exploration Permit 3 years 3 years

Two

 

After the two renewal periods lapse, the permit expires unless it is converted (in whole or in part) into an exploitation permit.

·     Surface Area:1,000 km2 blocks

·     Confers right to explore for resources to any depth within permit area

·     Number is limited to 20 exploration permits per holder; a holder must have the technical and financial capability to conduct the work

·     Permits taken under a joint venture are not taken into consideration for the calculation of the above limit, if the holder is not the controlling partner or the operator

·     Transferable under conditions established by the Decree on Mining Titles

Mining Permit

(Exploitation Permit)

 

30 years 10 years Several

·     Necessary for operating a mine

·     Within an area initially covered by an exploration permit, for the same commodities, and on the basis of a feasibility study

·     Granted only to a legal entity incorporated under Mauritanian law and created by the holder of the exploration permit

·     Transferable under conditions established by the Decree on Mining Titles

·     Personnel health and safety reports to be lodged with the Ministry every six months, and environmental and activity reports every year

·     Land needs to be rehabilitated after mining

 

4.3Fees, Royalties, Duties and Taxes

 

Mining activities in Mauritania are mainly governed by the Mining Code and its regulations, and by the Model Mining Convention Law, which provides the legal and tax framework for all mineral exploration and extraction activities.

 

The Mining Code establishes conditions and rules governing all phases of mining activity. The Model Mining Convention Law provides that each exploration permit (Permis de Recherche Minière or PRM) is subject to a mining convention with the State of Mauritania, which outlines the framework of customs, economic, financial, legal and tax terms and conditions under which the permit holder proceeds with its exploration or mining activities inside the perimeter of its permit. A Mining Convention is attached to a given permit. Table 4-4 summarizes provisions of the TMLSA Mining Convention relating to fees, royalties, duties and taxes.

 

The Mining Code is also complemented by the Decree on Mining Titles, which provides more details on the process governing the grant, renewal, expansion or reduction, division or merger, transfer, termination, suspension and cancellation of a permit for exploration or exploitation. It also governs the conversion of an exploration permit into an exploitation permit.

 

 
Page 19

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The conditions embodied in the Model Mining Convention (Law No. 2002/02) subsequently replaced by Law 2012-012 are designed to stimulate and encourage investment in both exploration and mining. The mining industry is seen as one of the main growth industries for the improvement of the country’s economy.

 

In addition to the 3% royalty payable to the government, Franco-Nevada Corporation holds a 2% net smelter return royalty on gold production at the Tasiast mine in excess of 600,000 ounces. Production at the Tasiast mine reached 600,000 ounces in July 2011, and the first royalty payment to Franco-Nevada was made in October 2011.

 

 
Page 20

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 4-4: Fees, Royalties, Duties and Taxes

 

Applicable Obligation Exploration Permit Mining Permit
Compensatory fees (for the issuance, extension or reduction, renewal, early termination and transfer of a permit) MRO 2,000,000 MRO 2,500,000
Annual surface fee

Initial period:

MRO 2,000-6,000/km2

First renewal period:

MRO 10,000-14,000/km2

Second renewal period:

MRO 20,000-24,000/km2

MRO 25,000/km2
Royalty   For gold, 3% of the sales value of the metal at the final stage of processing within Mauritania is deductible from taxable income.
Customs duties and other taxes Complete exemption on all equipment and supplies, including fuel Complete exemption on all imported equipment and supplies, including fuel, for five years after the start of production (ended August 2012). Customs duties of 5% thereafter on equipment and supplies imported, except fuel, lubricants, mine supplies and spares that will continue to be exempt from duty.
Tax on business profits   TMLSA was exempt from this tax for the first three years after its first production. After three years, the rate was fixed and stabilized at 25%. Articles 8 to 17 inclusively of the Mining Convention establish the relevant deductions to determine taxable profits.
Fixed minimum tax   Exemption until the end of the third year following the year the exploitation permit was granted. Since the end of this period, the standard rate of 2.5% applies at a reduced rate (1.25%) for TMLSA.
Tax on salaries, wages and annuities of expatriates employed by TMLSA   The standard rate of 40% reduced to half (20%) for TMLSA.
Income tax from capital   Customary applicable rate is 10%. Dividends reinvested on Mauritanian territory are exempt from this tax.
General income tax   Exemption for the duration of the Mining Convention
Value-added tax (VAT)   Customary applicable rate was increased from 14% to 16% in January 2015, except for exports by TMLSA, which is 0% (contingent on export of at least 80% of production).
Tax on sales - consumption tax   Exemption for the duration of the Mining Convention
Housing tax   Applies according to the CGI (General Tax Code), as from the first exploitation permit
Land income tax (on properties built)   Rules of application are those of the CGI. The rate, as voted by the town council, is 3% to 10% of the taxable value, which is the rental value of the property minus 20%.
Trading tax   Applicable from the date the first exploitation permit was granted according to the CGI. This tax is a fixed duty based on turnover
Registration and stamp duties   Exemption for the duration of the Mining Convention
Tax on motor vehicles   Applies according to the CGI as from the first exploitation permit. The rate of the tax is based on the use of the vehicle and its tax power
Apprenticeship tax   Exemption for the duration of the Mining Convention

 

 
Page 21

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

5.accessibility, climate, LOCAL RESOURCES, INFRASTRUCTURE and physiography

 

5.1Accessibility

 

The Tasiast Lands are accessed from Nouakchott by using the paved Nouakchott to Nouadhibou highway for 370 km and then via 66 km of graded mine access road which is maintained by TMLSA. An airstrip at the Mine Site is used for light aircraft primarily travelling to and from Nouakchott.

 

The principal ports of entry for goods and consumables are either Nouakchott or Nouadhibou. Materials are transported by road to the mine site.

 

Routine access within the country is provided by an 11,000 km long road network, comprising approximately 3,000 km of paved highways and approximately 8,000 km of unpaved highways as well as numerous desert tracks. A paved 470 km long, two-lane highway runs between the cities of Nouakchott and Nouadhibou.

 

A 717 km long rail line located along the border between Mauritania and Western Sahara is owned and operated by Société Nationale Industrielle et Minière de Mauritanie (SNIM). This rail line is primarily used to haul iron ore from SNIM’s iron ore mines in Zouérate to the port of Nouadhibou.

 

Access to the major urban centres of Mauritania is also possible via air. Nouakchott is accessible via international flights operated by numerous West and North African carriers; Air France also provides a direct connection to Paris.

 

5.2Climate

 

Mauritania has an arid desert climate, with an average annual high temperature of above 45°C between May and August. Minimum temperatures may go below 10°C in December and January. From January to March, sandstorms frequently occur in the country; this causes sand build up and dune formation. Sandstorms vary in intensity, and visibility can be reduced to several metres. There is a rainy season, usually between July and September; however, the amount of rainfall and length of season varies spatially and temporally in the various regions of the country. Annual rainfall varies from a few millimetres in the desert regions to as high as 450 mm in the south along the Senegal River. During the last 20 years, the country has recorded two periods of drought, namely 1984-85 and 1991-92.

 

 
Page 22

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Average annual precipitation at the mine site is approximately 90 mm, and usually occurs during July to September. The average recorded monthly evaporation is approximately 320 mm/month (3840 mm/a).

 

Mauritania is located along the northwestern coast of Africa and is bordered by the Atlantic Ocean to the west. The country’s land mass covers the western portion of the Sahara Desert. Mauritania’s land mass consists mainly of flat and barren desert landscape surfaces that are cross cut by three large NE-SW trending longitudinal dune fields. In the central part of the country, near Adrar and Tagant, several hills and mountains rise up to 915 masl. In the desert regions, vegetation is sparse, consisting of various species of trees (e.g., acacia) and grasses.

 

5.3Local Resources and Infrastructure

 

The mine is located in a remote area where there is no electric power grid. On-site power generation is discussed in Section 18.

 

The source of mine water supply is located 64 km west of the mine and consists of a semi-saline underground aquifer, which is exploited by 47 wells. Water is pumped from the bore field to the mine (see Section 18).

 

In 2016, the Tasiast mine employs approximately 1,140 employees, of whom approximately 1,010 are Mauritanian nationals. Staff accommodation is provided at the mine site (see Section 18).

 

The terrain surrounding the Tasiast deposit is flat, and is adequate for construction and operation of the camp, mine, plant, tailings, and waste rock disposal facilities. Figure 5-1 shows the mine site layout.

 

 
Page 23

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 5-1: Mine Site Infrastructure Layout Plan

 

(MAP)

 

 
Page 24

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

5.4Physiography and Environment

 

The topography of the Tasiast Lands consists mainly of flat, barren plains which are primarily covered by regolith and locally by sand dunes, or eroded paleo-lateritic profiles. Elevation ranges from approximately 130 masl to 150 masl.

 

The drainage pattern around the Tasiast Lands consists of several intermittent dendritic first- and second-order streams that generally flow in a southwesterly direction. There are no permanent watercourses in the area. However, there are numerous, intermittent watercourses, known as “wadis”, which flow for only a few days per year. The largest wadi is the Khatt Ataoui wadi, which is located approximately 6 km from the mine site.

 

The Tasiast mine is located in the arid Saharan zone, where plant life is very scarce, consisting mainly of the low shrubs Zygophyllum album, the small tree Maerua crassifolia (atil) and the grass Aristida pungens (sbot). Acacias are also present along many of the wadis. The bore field, water pipeline and road are almost exclusively colonized by Zygophyllum album.

 

Hares, hamsters and gerbils are the most common mammals at the mine site, and jackals, fennec fox and polecat can also be found in the well area. There are no protected species in the Project area. The eastern boundary of the Banc D’Arguin National Park is located about 2 km west of the bore field area and 60 km from the mine site.

 

 
Page 25

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

6.history

 

6.1Tenure History

 

In 1996, the Office Mauritanien de Recherches Géologiques (OMRG) completed a regional reconnaissance exploration program within and around the lands hosting the Tasiast deposit and made this information available to third parties. As a result, NLSD (a subsidiary of Normandy Mining Ltd. of Australia) acquired the exploration rights to the Tasiast deposit.

 

In 2001, NLSD was acquired by Newmont Mining Corporation creating Newmont LaSource. Midas Gold PLC (Midas) was incorporated in England and Wales in 2002 for the purpose of acquiring Newmont LaSource’s assets in Mauritania including exploration permits over lands hosting the Tasiast deposit, as well as various other permit areas. Midas completed its acquisition of the Tasiast deposit from Newmont LaSource on April 1, 2003 and, in April 2003, Geomaque Explorations Inc. (Geomaque) announced the acquisition of Midas. The merger of Geomaque and Midas ultimately created a new entity - Defiance Mining Corporation (Defiance). In June 2004, Rio Narcea Gold Mines, Ltd. (Rio Narcea) acquired Defiance and took ownership of the Tasiast deposit.

 

Red Back acquired the Tasiast deposit from Lundin Mining Corporation (Lundin) in August, 2007 following Lundin’s acquisition of Rio Narcea. In September 2010, Kinross completed the acquisition of Red Back. Kinross, through TMLSA, holds 100% of the Project.

 

6.2Project History

 

From 1962 to 1993, the Tasiast region was the subject of three regional exploration programs for pegmatites, iron ore, and nickel sulphides which were carried out by the BRGM and SNIM.

 

Three exploration programs were carried out in the Tasiast region between 1993 and 1996 as a European Development Fund project. Work completed included regional-scale reconnaissance geological mapping and geochemical sampling. Traverse lines for the mapping and geochemical sampling programs were oriented east-west with samples collected at 500 m centres; this work identified the Tasiast area as being anomalous in gold. More detailed soil sampling of the Tasiast area on 250 m spaced centres, and trenching was conducted.

 

NLSD, in the period 1996-2001 completed geological and regolith mapping, interpretation of satellite imagery, airborne and ground magnetic geophysical surveys,

 

 
Page 26

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

specialist petrographical, mineralogical, and geological studies, metallurgical test work, and auger, reverse circulation (RC) and core drilling.

 

Midas undertook a full review of all existing information in 2003, and prepared mineral resource estimates for the West Branch and Piment areas. From 2003 to 2004, Defiance completed mineralogical and metallurgical test work, hydrogeological studies, a preliminary pit slope design study, RC and core drilling, a mineral resource estimate, and a feasibility study.

 

Rio Narcea completed additional RC and core drilling from 2005-2006. Red Back also undertook RC and core drilling, re-estimated mineral resources, and updated engineering studies. Mine construction was completed in 2007, with the mine formally opened in early 2008.

 

Between August 2007 and September 2010 Red Back completed several large exploration campaigns in the Piment and West Branch areas, as well as at several district targets. Early drilling campaigns were directed at testing the lateral and vertical extents of the mineralization at Piment and drilling oxide resources at West Branch. In October 2009, Red Back discovered the Greenschist Zone at West Branch and commenced drilling the deposit.

 

From September 2010 to date, TMLSA has aggressively ramped up exploration with the majority of activities directed towards delineating the extents of the Greenschist Zone.

 

Mining at Tasiast commenced in April 2007 and the mine was officially opened by the President of Mauritania, His Excellency Sidi Mohamed Ould Cheikh Abdallahi, on July 18, 2007. A summary of gold production at Tasiast is included in Table 6-1. There has been no historical gold production from other deposits in the Tasiast area.

 

 
Page 27

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 6-1: Production Summary

 

  Carbon In Leach Dump Leach Total
Year Tonnes Milled Grade Gold Produced Recovery Gold Produced Gold Produced
  (Mt) (g/t ) (‘000 oz.) (%)  (‘000 oz.)  (‘000 oz.)
2007 0.22 4.36 21 68.6% 0 20,812
2008 1.49 3.07 140 95.4% 0 140,052
2009 1.68 2.88 142 91.4% 16,400 158,660
2010 2.14 2.52 150 86.8% 35,617 185,982
2011 2.60 2.04 153 89.4% 47,910 200,619
2012 2.55 1.54 114 90.2% 71,356 185,334
2013 2.50 1.96 144 91.3% 103,883 247,816
2014 2.56 2.16 161 90.9% 93,505 254,510
2015 2.54 2.17 160 90.1% 59,826 219,938
Total/Average 18.28 2.24 1185 90.1% 428,496 1,613,724

 

 
Page 28

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

7.geological setting

 

7.1Regional Geology

 

The Tasiast Lands lie in the southwestern corner of the Réguibat Shield (Figure 7-1), which is a large area underlain by Precambrian crystalline rocks that comprise the northern part of the West African Craton. In general, the western half of the Reguibat Shield contains rocks of Mesoarchaean age (~3.1 to ~2.9 Ga), whereas those in the eastern half are Palaeoproterozoic (~2.6 Ga) (Key, 2008). Large granitic intrusions and moderate- to high-grade metamorphic rocks including gneisses, amphibolites, and schists typify the basement rocks. Metamorphic grade in the Reguibat Shield generally increases from mid-greenschist facies in the southwest through to granulite facies in the central parts. Several north-south elongate greenstone belts occur over a broad area of the western Reguibat Shield. The greenstone belts consist of metavolcanic, meta-plutonic and metasedimentary rocks ranging from ultramafic to felsic compositions. The metasedimentary rocks were deposited within rift basins that formed on top of the metavolcanic rocks that rest upon the crystalline basement. Gold was deposited during deformation that was associated with inversion of the rift basins. The Tasiast lands fall within a cluster of several greenstone belts. The Réguibat Shield was cratonized by the end of the 2,100 to 2,000 Ma Eburnean orogeny and has been stable since at least 1,700 Ma (Schofield et al., 2006). The Réguibat Shield is bounded on all sides by Pan African orogenic belts and covered in the south by the extensive intra-cratonic sediments of the Taoudeni Basin.

 

Three significant Archaean greenstone belts are exposed within the Tasiast Lands (LaSource-BRGM, 1997; Figure 7-2) and are termed, from east to west:

 

·N’Daouas (20 km long x 6 km wide);

 

·Aouéouat (+75 km long x 8 km wide); and

 

·Imkebdene-Kneffissat (+ 60 km long x 9 km wide).

 

The Aouéouat and Imkebdene-Kneiffissat greenstone belts are north-south trending linear belts, whereas the N’Daouas greenstone belt is arcuate in plan shape. The greenstone belts are surrounded by granitic intrusive rocks and gneissic domes of the types that comprise the bulk of the rocks within the southwest Réguibat Shield. The greenstone belts consist of ultramafic to felsic volcanic rocks and sedimentary packages that include ferruginous quartzite, greywacke, arkose, siltstone and turbidite sequences. Rock units within the belts have undergone mid-greenschist to lower amphibolite grade metamorphism and multiple deformation events. Two families of non-foliated mafic (gabbroic) dikes that strike predominantly north-northeast and east-west crosscut all

  

 
Page 29

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

other rocks in the district, including undeformed pegmatite units that might be Proterozoic in age. The two main thrust systems that control gold mineralization are labelled in Figure 7-2, and the names of the mining and exploration permits are also indicated.

 

The Aouéouat greenstone belt hosts all of the known Tasiast gold deposits and most of the currently explored prospects. Other belts in the district contain gold occurrences, but remain under-explored. Uranium-lead (U-Pb) dates obtained from gneiss, granodiorite and pegmatite intrusive rocks sampled in the southwest Réguibat Shield indicate a range of ages from 3,070 Ma to 2,600 Ma (LaSource-BRGM, 1997; Maurin et al, 1996).

 

The Precambrian lithostratigraphy established by Kinross for the Aouéouat belt is shown in Figure 7-3 along with several proprietary U-Pb dates for rocks of the Aouéouat and Tasiast assemblages and for granodiorite intrusions. The mafic to felsic volcanic and intrusive units that host the West Branch deposit belong to the Aouéouat assemblage that crystallized between 2,990 Ma and 3,000 Ma. Metasedimentary rocks of the Tasiast assemblage that overlay the mineralized West Branch units contain detrital zircons of similar ages and older populations derived from approximate 3,200 Ma orthogneiss basement. Granodiorites that crosscut the metavolcanic rocks are dated 2,960 Ma to 2,970 Ma. Although the gold deposition event has yet to be directly dated, it must have occurred following the intrusion and exhumation of some granodiorite plutons, as clasts of the granodiorites are identified within the metasedimentary rocks that are deformed and locally mineralized.

 

The principal north-south structural fabric in the greenstone belts is evident in satellite images (Worldview-2) and in geological maps over 70 km of the strike length. Steeply dipping foliations and isoclinals folds with north-south axial surface traces are common across the Aouéouat belt. Those structures formed through east-west transpressive shortening that occurred as a result of basin inversion. Strain was partitioned between tightly folded domains and north-south striking shear zones. Several families of cross-cutting faults with northeast and southwest strikes transect the folds and thrust structures.

 

Subtropical conditions in the tertiary formed a rather continuous laterite layer over the eroded Precambrian geology of the Aouéouat belt and other areas on the Tasiast lands. Locally, the duricrust has been stripped and re-deposited as a gravel lag or pavement that is locally referred to as reg. Depth of oxidation ranges from 10 m to 60 m, with an average of 40 m.

 

 
Page 30

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-1: Geology of the West African Craton. Modified from Fabre (2005).

 

(MAP) 

 

 
Page 31

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-2: Tasiast Geology Overlain on Worldview-2 Satellite Imagery

 

(MAP) 

 

 
Page 32

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-3: Precambrian Stratigraphy of the Aouéouat Greenstone Belt

 

(FLOW CHART) 

 

7.2Property Geology

 

The property geology (Figure 7-4 and Figure 7-5) is characterized by orthogneiss basement overlain by deformed north-striking metavolcanic and metasedimentary successions intruded by stocks and plutons of mafic to intermediate composition. All units are cut by unfoliated and post-mineral mafic (gabbroic) dikes. The orthogneiss occurs within the Tasiast lands, but is not present in the mine geology sequence.

 

The volcano-sedimentary stratigraphy has been tightly to isoclinally folded, and is cut longitudinally by sub-parallel shear systems that are also sub-parallel to the folds. The shear systems are oblique thrusts that are thought to be linked to a deeply rooted system of ductile faults, as illustrated by the structural profile in Figure 7-6. The deeply rooted faults are likely reactivated normal faults that were part of the architecture of the Tasiast rift basin. The most highly prospective gold trends are bounded by the Tasiast and Pantaloon zones (Figure 7-6).

 

 
Page 33

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The Tasiast gold trend includes the active Piment and West Branch pits. It is spatially associated with the west vergent Tasiast shear system that places mafic to felsic volcanic and intrusive rocks of the Aouéouat assemblage, including the host rocks of the West Branch deposit, on top of the younger metasedimentary rocks of the Tasiast assemblage. The Tasiast trend passes north-south through the El Ghaîcha mining permit and extends over tens of kilometres to the north and south.

 

The Pantaloon gold trend is located about 3 km to the east of the Tasiast trend. It is spatially associated with the north to north-northwest striking Pantaloon shear system. Mineralization is hosted by quartz-carbonate veins within sheared metasedimentary rocks of the Tasiast assemblage in the hanging wall of the thrust, and sheared ultramafic schist in the footwall of the thrust. The Pantaloon trend is the locus of several exploration prospects on the El Ghaîcha mining permit and also on the Tmeimichat exploration permit to the north.

 

Figure 7-6 shows an interpreted structural profile at 72,000N, based on mapped geology and on modelled gravity data.

 

The profiles display the geology (top panel) and main alteration assemblages (bottom panel). The principal shear zones are indicated by dashed lines. The view is looking to the north.

 

Some gold prospects lie between the Tasiast and Pantaloon shear systems and also to the east of the Pantaloon system where they might be aligned parallel to rift-related structures preserved in the underlying basement rocks.

 

Mineralization at the Piment deposits (South-South, South-North, Central, North, Mars, Prolongation (Figure 7-4) is hosted by iron-rich metasedimentary formations that belong to the Tasiast assemblage and that have been metamorphosed to upper Greenschist and lower amphibolite peak grades. Gold is mainly associated with the sulphide replacement of Fe-oxide minerals, such as magnetite. At the West Branch deposit, the mineralization is hosted by quartz-carbonate veins within strongly sheared, fine- to medium-grained intrusive rocks of diorite and quartz diorite compositions that belong to the Aouéouat assemblage.

 

 
Page 34

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-4: Plan Map of the Main Structural Features

 

(MAP)

 

 
Page 35

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-5: Geological Plan View of West Branch and Piment

 

(MAP) 

 

 
Page 36

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-6: Interpreted Structural Profile at 72,000N

 

(MAP) 

 

 
Page 37

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Lithologies

 

Greenschist Zone – Diorites and Basalts of the Aouéouat Assemblage

 

Granodiorite Intrusive (GDI) hosts the economic mineralization at West Branch. Historically, this unit was referred to as the Greenschist Zone (GST). It includes two units logged as mafic metavolcanic and meta-intrusive rock types. The contact between the two units ranges from sharp to gradational. At West Branch, the GDI consistently averages 50 m to 100 m in thickness over a strike length that exceeds 2,000 m. The thicknesses of the main lithological units range from 5 m to 50 m for the meta-intrusive (average 35 to 40 m) and 20 m to 80 m for the mafic metavolcanic rocks. The GDI rock units have been intersected by deep drilling at Piment, but are generally thinner there (<20 m) than at West Branch. Between Piment Central and Piment North, the GDI is up to 80 m thick and dominated by mafic metavolcanic rocks.

 

Mafic Metavolcanic Rocks – Basalt

 

Mafic metavolcanic rock is interpreted to be the oldest rock unit within the mine stratigraphy. It is a dark green to brown, mafic, very fine to fine-grained rock that is composed of varying amounts of actinolite, biotite and plagioclase. It is locally garnet bearing. The rock preserves a moderately strong to strong foliation defined mainly by the alignment of biotite crystals. Previously, the unit was logged as an intermediate volcanic; it is now logged as basalt, which is the most likely protolith.

 

Mafic to Intermediate Meta-intrusive rocks – Diorite, Quartz Diorite

 

This light to medium grey, medium to fine-grained rock is dominantly composed of plagioclase, quartz and biotite with potassium feldspar present in amounts up to half of the plagioclase content. The unit typically has a distinctive penetrative foliation that is most strongly expressed by the alignment of biotite crystals. It was previously referred to as plagioclase-biotite schist and was logged as schist (SHT) and biotite schist (BST). The logging terms GDI (diorite) and GDQ (quartz diorite) have now been adopted. For geological modelling purposes, the GDI and GDQ can be grouped together. Limited geochemical data suggest the rocks are fractionated derivatives of basaltic magmas.

 

Felsite of the Aouéouat Assemblage

 

Stratigraphically overlying the Greenschist Zone is a cream coloured, microcrystalline quartzo-feldspathic rock that locally preserves quartz and/or plagioclase phenocrysts. This siliceous unit is logged as felsite (FVC) and occurs discontinuously throughout most of the Piment and West Branch deposits. At West Branch, the FVC unit is present both structurally above and below the Greenschist Zone. The unit is strongly sheared and preserves a well-developed phyllosilicate foliation. The rock is interpreted to represent pyroclastic formations and possibly flows of dacitic to rhyolitic compositions. Within the FVC, near to its contacts with other units, a cream coloured rock locally occurs that hosts

 

 
Page 38

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

fuchsitic (chromium rich) mica. That rock is considered to represent bleached, highly altered mafic metavolcanics possibly derived from the basalt unit of the Greenschist Zone.

 

Banded Iron and Magnetite Formation of the Tasiast Assemblage

 

The banded iron and magnetite formation (BIM) unit is composed of alternating layers of dark greenish magnetite-grunerite and light gray quartz-feldspathic compositions. The rocks are generally strongly magnetic and they are interpreted to represent metamorphosed iron-rich siltstones and argilites that are the upper parts of complete or partial Bouma (turbidite) sequences. The rocks are logged as BIM, and they belong to the lower stratigraphic levels of the Tasiast assemblage.

 

Layers within the BIM vary in thickness from 0.2 cm to a few centimetres and typically have sharp contacts. Mesoscopic folds within the unit are typically very tight to isoclinal. The BIM unit has a thickness up to 200 m in the hanging wall of the Tasiast deposits and it is also intersected in drill holes in the footwall of the Tasiast thrust system where it is less than 15 m in thickness.

 

The contact between the hanging wall BIM and the FVC units is locally defined by the presence of a discontinuous conglomerate that contains abundant clasts derived from the FVC unit and a subordinate proportion of clasts derived from mafic metavolcanic units. Locally, the conglomerate presents a laminated texture where it is strongly sheared. The presence of the conglomerate at the base of the Tasiast assemblage suggests the presence of an erosional unconformity.

 

Siliciclastic Metasedimentary Rocks of the Tasiast Assemblage

 

The bulk of the Tasiast assemblage rocks that overlie the FVC in the Tasiast mine area are siliciclastic metasedimentary rocks (SVC), including several facies of which greywacke and siltstone are the most abundant. Conglomerate, microconglomerate, arkose and some feldspathic sandstone are also present. Numerous turbidite and partial turbidite sequences composed of the previous rock types are identified. Locally, the BIM type metasedimentary rocks are finely interbedded with these facies and can be seen to form the upper parts of turbidite sequences. The logging code SVC is inherited from early days of exploration when the rocks were interpreted to be volcaniclastic sediments.

 

Mafic Dikes

 

Mafic dikes that are post schistosity and post mineralization are dark olive green, fine to medium-grained and are locally plagioclase phyric. Dikes are typically less than 5 m wide, weakly magnetic and have locally developed hornfelsed and brecciated margins with a carbonate-chlorite assemblage. The dikes are dominantly barren and crosscut mineralized units.

 

 
Page 39

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

7.3Structural Geology

 

The West Branch and Piment deposits are hosted within a package of strongly folded and sheared rocks in the hanging wall block of the Tasiast thrust system. The Tasiast thrust is the master (lowermost) structure, and higher level shear zones are interpreted to be splays. Modelling and interpretation of high-resolution gravity data gathered by Fugro Ground Geophysics for Kinross in 2013 shows the deep geometry of the thrust system underlying the Aouéouat belt. It is very likely that the Tasiast thrust is linked to a system of deeply rooted ductile faults (Figure 7-6). The deeply rooted faults would have formed as normal faults during the basin forming rift event that led to the deposition of the Tasiast assemblage. The deep-seated faults served to channel mineralizing fluids from the deep crust and lithosphere to West Branch and Piment.

 

Fold repetition is evident within the Tasiast thrust system and to the east of it. The dominant foliation in the mine sequence is moderately to steeply east-dipping (40° to 65°). Overall, the dip angle of the thrusts and of the foliation steepens from the southern part of West Branch toward the north where it is subvertical near Prolongation.

 

The Tasiast thrust and its splays are typically 0.5 m to 10 m thick and are characterized by a laminated foliation with locally preserved mylonitic textures. The fault splays are commonly situated at the contacts of lithologic units. Hydrothermal alteration assemblages, sulphides and quartz veins are commonly spatially associated with the principal thrusts and splays.

 

Previous structural interpretations of the mine area suggested either a thrust system developed with a ramp-flat geometry (Davies, 2011a,b) or shear zones developed along fold limbs (Goodman, 2011). In fact the two interpretations are not mutually exclusive. Kinross interprets that the vast bulk of thrust displacement on the Tasiast thrust system was accommodated by the main (basal) thrust and that some of the recognized splays represent shears that developed on the limbs of isoclinal folds in the hanging wall block of the main thrust.

 

At West Branch, first-order controls on the ore bodies include an interpreted periclinal antiformal fold in the hanging wall of the Tasiast thrust where the core of the antiform would be occupied by the Aouéouat assemblage rocks. The culmination of the interpreted antiform is located around Section 71,811N. The other principal structural controls on mineralization are the Tasiast thrust and its splays. The splays are second-order thrusts that served to channel fluids from the main thrust.

 

Lithological-structural profiles through the West Branch deposit at 71,411N, 71,811N and 71,061N are provided in the upper panels of Figure 7-7 to Figure 7-9. The profile lines are located in Figure 7-5. The profiles display the geology (top panel) and main

 

 
Page 40

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

alteration assemblages (bottom panel). The principal shear zones are indicated by dashed lines. The view is looking to the north.

 

The thrusts dip consistently eastward at moderate (45° to 55°) angles and are identified as zones of intense foliation, often situated on contacts between lithological units. This suggests the thrusts are the result of strain localization at the lithological contacts. Quartz-carbonate veins sets occur sub-parallel and oblique to foliation and range in style from boudinaged, buckled, folded to planar. The veins certainly formed in extensional and/or Riedel shear orientations and were progressively folded, rotated, locally boudinaged and partially or wholly transposed parallel to the foliation. In the core of the West Branch Greenschist Zone vein, densities are typically higher in the meta-intrusive dioritic unit (averaging between 2% to 5%) than in the meta-basalt (<2%). This higher density suggests the coarser-grained feldspar-rich dioritic facies focused stresses and readily developed brittle-ductile shears, as expected for quartzo-feldspathic rocks under retrograde Greenschist metamorphic conditions. Along the margins of the West Branch deposit, both the dioritic and meta-mafic volcanic units have a low vein density (<1%). Quartz-carbonate veins also developed locally within FVC that envelops the Greenschist Zone and within the footwall meta-sedimentary units.

 

 
Page 41

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-7: Profiles through the Greenschist Zone at West Branch at 71,411N

 

(GRAPHIC) 

 

 
Page 42

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-8: Profiles through the Greenschist Zone at West Branch at 71,811N

 

(GRAPHIC) 

 

 
Page 43

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 7-9: Profiles through the Greenschist Zone at West Branch at 71,061N

 

(GRAPHIC) 

 

 
Page 44

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

7.4Mineralization and Alteration

 

Gold mineralization and alteration assemblages at the Tasiast deposits have been defined over a strike length of approximately 30 km and to vertical depths of at least 740 m. Alteration profiles through the West Branch deposit at 71,411N, 71,811N and 71,061N are provided in the lower panels of Figure 7-7 to Figure 7-9. Alteration mineral associations within the Greenschist Zone at West Branch include a central core of biotite-carbonate-quartz-pyrrhotite-pyrite ± magnetite ± garnet ± tourmaline ± leucoxene (coded as BST alteration zone) that is mainly developed within the mafic to intermediate intrusive rocks (Pollard, 2011). Intense silicification is also locally well developed in the same rocks where it is associated with sheeted quartz veins. A strong correlation exists between the +2 g/t Au grade shell and quartz vein densities of 1% to 5%, sulphide volume of 0.5% to 2.0% (pyrrhotite dominated) and a medium abundance of carbonate in both the veins and groundmass.

 

The BST alteration grades outward to a biotite-amphibole-carbonate-quartz-pyrite-pyrrhotite ± magnetite ± garnet alteration assemblage that itself grades into an amphibole-biotite-garnet ± carbonate ± quartz ± pyrite ± pyrrhotite assemblage. These two alteration assemblages are respectively coded as GST2 and GST1 and are hosted mainly in the mafic meta-volcanic unit, and to a lesser degree in the mafic to intermediate intrusive rocks.

 

Volumetrically minor mineral alteration associations include sericite-zoisite ± quartz ± carbonate detected on the margins of the GST2 and GST1 and a late overprinting albite-sericite-carbonate assemblage observed locally throughout the West Branch deposit. The FVC units have been variably altered by albite, biotite, muscovite, pyrite and quartz, and contain variable quartz vein densities.

 

At West Branch, several types of veins are recognized within the Greenschist package and include the following (in order of paragenesis):

 

i.Early milky white quartz that are commonly folded and boudinaged and oriented close to the foliation plane.

 

ii.Quartz-albite-tourmaline veins that are boudinaged, attenuated and oriented close to the foliation plane.

 

iii.Greenish gray to translucent quartz ± native gold veins with a silica selvedge that are oriented at low to moderate angles to the foliation plane.

 

iv.Quartz-amphibole-biotite-carbonate-pyrite-garnet veins that are oriented at low to moderate angles to the foliation plane.

 

 
Page 45

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

v.Quartz-carbonate-biotite ± actinolite ± pyrite ± pyrrhotite ± tourmaline ± magnetite ± garnet veins that crosscut foliation at a high-angle.

 

vi.At Piment, the main mineral associations comprise magnetite-quartz-pyrrhotite ± actinolite ± garnet ± biotite. Sulphide replacement of magnetite is best observed within the banded iron magnetite units. The assemblage is spatially associated with the main shear zone as well as splays.

 

The deposits can be approximated as slightly flattened prolate ellipsoidal shoots that have moderate dips to the east and a shallow to moderate (approximately 30°) southerly plunge. Notable variations between the West Branch and Piment deposits are the rocks hosting mineralization and the continuity of individual mineralized shoots. The majority of mineralization at West Branch is hosted in the altered and veined Greenschist Zone that is bound by footwall and hanging wall FVC.

 

A strong correlation is established between the BST altered Greenschist Zone rocks and a continuous +2 g/t Au shell at West Branch. The +1 g/t Au grade shell correlates with the portions of the mafic meta-volcanic rocks, whereas the 0.6 g/t Au shell extends locally into the FVC. The low-grade halo (ranging from 0.25 g/t Au to 0.60 g/t Au) extends further into the FVC and is also developed over approximately 100 m horizontal widths in the SVC footwall.

 

At West Branch, individual shoots that define +2 g/t Au grade shells are continuous over a strike length of at least 1,000 m and have a down dip extent between 100 m and 400 m. In comparison, Piment mineralization is largely hosted along faults and within the adjacent altered rocks. Individual mineralized shoots at Piment have been continuously defined over a 300 m strike and range in thickness from 5 m to 40 m.

 

Metallic minerals within the Greenschist Zone are dominated by pyrrhotite, pyrite and native gold that occur as vein infill and alteration spots commonly in and around the foliation planes in proximity to veins. Pyrrhotite and pyrite occur together in many places, but in variable ratios. Zones of pyrite-only and pyrrhotite-only are rare.

 

Blake (2011a, b) studied the nature, grain size and mode of occurrence of native gold grains in seven composites from two drill holes that intersected Greenschist Zone mineralization. Results from the study concluded that the volume of coarse (>100 µm) gold grains account for the majority of contained gold and greater than 60% of grains occur in the liberated form and a subordinate portion associated with gangue minerals and micrometre grains detected in slimes. At Piment, the metallic minerals include native gold, pyrrhotite and pyrite. Other sulphide minerals recognized at both deposits in minor to trace abundances include electrum, chalcopyrite, arsenopyrite, sphalerite, covellite, pentlandite and petzite.

 

 
Page 46

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The oxide zone is characterized by leaching of quartz-carbonate veins and sulphides, and precipitation of calcrete and iron hydroxides in voids and fractures. No well-defined transition zone was identified as the strongly weathered upper portion of the deposits grades into fresh rock at depth. The depth of oxidation is in the order of 30 m to 60 m, at an average of 40 m. No supergene enrichment of gold is apparent in the upper profile.

 

 
Page 47

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

8.deposit types

 

The Tasiast deposits are hosted in Archaean volcanic-sedimentary sequences that have been deformed and metamorphosed to lower amphibolite peak metamorphic grade. Mineralization is both structurally and lithologically controlled, epigenetic in style and was coincident with early stages of post-peak metamorphic retrograde Greenschist P-T conditions.

 

The regional geological setting and deposit features at Tasiast are similar to other well-known Archaean cratons and greenstone belts that host major gold camps. Examples of analogue terranes of similar ages to the Aouéouat belt include the Kaapvaal craton in South Africa, the Pilbara craton in Australia and the Wyoming craton in the USA. The Aouéouat belt also shares some similarities with gold-rich Late Archaean terranes, such as the Yilgarn in Australia and the Abitibi in Canada.

 

 
Page 48

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

9.exploration

 

Exploration has been undertaken by TMLSA, its precursor companies (e.g. gold exploration by NLSD), or by contractors (e.g. geophysical surveys).

 

9.1Grids and Surveys

 

The Coordinate System used on site is UTM (WGS84) 28 North, however a translation constant is used (Easting of 400 000 and Northing of 2 200 000). The Original Control has been set out by IPH Engineering and ten control points are set out across the mine. Surveyors use a differential GPS for surveying at the mine.

 

9.2Geological and Regolith Mapping

 

Numerous phases of geological and regolith mapping have been undertaken during the life of the project, and range from regional (1:150,000) to prospect (1:12,500) scale. Work was completed by the BRGM, SNIM, NLSD, Defiance Mining Corporation, Red Back and Kinross. Mapping was facilitated by good outcrop, RC drilling chips, high resolution satellite imagery and detailed airborne geophysical data. Results were used to identify areas of alteration, structural complexity, quartz-carbonate veining, and sulphide outcrop that warranted additional work.

 

9.3Geochemistry

 

Soil, grab and rock sampling were used to evaluate mineralization potential and generate drill targets. Approximately 47,700 surface samples, including mostly soil and rock chip, have been taken over the life of the project area. From 2011 to date, TMLSA expanded the extent of the historical surveys and collected an additional 12,800 soil samples for both gold and multi-element analyses, and approximately 5,000 rock chip samples. Surface sampling was used as a first-pass exploration tool to identify areas of geochemical anomalism; some of these anomalies remain to be studied further.

 

9.4Geophysics

 

Ground and airborne magnetic surveys were completed by NLSD and Red Back and used to delineate intrusive rocks, banded iron-formations, fault structures, and sulphide-rich zones at depth. Red Back also completed an electromagnetic survey (VTEM EM) in 2008. TMLSA completed a detailed airborne magnetic and radiometric survey across the mining permit and exploration permits in 2011. A small ground induced polarization (IP) survey was also conducted across a portion of the West Branch deposit, with subsequent IP surveys completed on near mine and district targets in 2013. In 2013,

 

 
Page 49

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

TMLSA also completed a ground gravity survey across the mining permit and exploration permits.

 

9.5Pits and Trenches

 

Excavation of trenches as an exploration technique has been very successful and was extensively used during the NLSD phase of exploration, when 55 trenches (26,593 m) were excavated, and an additional 27 trenches (1,309 m) were hand-dug. Significant gold intersections in trenches typically overlay sub-surface zones of similar grade and width, as defined by subsequent drilling. TMLSA completed 18 trenches from 2011 to the end of 2013, for a total of 3,942 m.

 

9.6Drilling

 

Drilling completed on the Project is discussed in Section 10.0.

 

9.7Bulk Density

 

Bulk density determinations are discussed in Section 11.0.

 

9.8Petrology, Mineralogy and Other Research Studies

 

In 1999, NLSD collected and carried out a petrographic and mineralogical study of 10 core samples selected from five drill holes that intersected Piment Central mineralization. The mineralogical and petrographic study noted the following (Bailly et al., 1999):

 

·Opaque minerals of the surrounding rocks consist of abundant magnetite crystals frequently associated with graphite;

 

·The mineralization assemblage consists of pyrrhotite with minor chalcopyrite and electrum ± arsenopyrite;

 

·Mineralization occurs as veinlets with carbonate, biotite and, locally, blue tourmaline impregnated along bedding planes within the host rock.

 

In 2010, Red Back submitted 10 core samples from West Branch for a petrological and mineralogical study. Results from the work indicated significant pyrrhotite mineralization developed along foliation planes and associated with accessory magnetite, chalcopyrite and pyrite (Strashimirov, 2010).

 

Further petrological studies were carried out for TMLSA in 2010 including work by Leitch (2010) and Larson (2011), followed by a gold characterization study in 2011 (Blake,

 

 
Page 50

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

2011a, b). Transmitting and reflecting microscopes were acquired for the Project in 2011 and selected slabs are submitted for thin sections. From 2011 to date, approximately 220 thin sections have been generated by TMLSA for mineral and rock identification purposes.

 

9.9Exploration Potential

 

Mineralization remains open both laterally and vertically at the Tasiast deposits. Shallow reconnaissance RC drilling across district targets has detected gold mineralization that requires follow-up exploration. The potential to delineate additional resources both at the Tasiast mine and the district targets is considered good. Some of these district targets are described below.

 

Drilling uncovered encouraging gold results at the C67-Fennec sector and Tasiast Sud (previously named Charlize) targets, located 5 km north and 15 km south of Tasiast. Drilling has also intersected encouraging gold grades within the Tmeimichat and Imkebdene permitted areas, situated approximately 10 km north of the mine site.

 

At the Tasiast Sud targets, mineralization occurs near the surface in BIM rocks that are part of the same mineralized BIM sequence further north at Tasiast. Mineralization has also been identified in sheared amphibolites that host quartz-carbonate veins where they are thrust over younger metasedimentary rocks. Gold mineralization at C67 is hosted by sheared and veined mafic metavolcanic rocks and by quartz diorites that may be intrusive into the metavolcanics. The gold is associated with quartz-carbonate veins that formed during the late stages of shearing. Besides quartz and carbonates, the vein mineralogy consists of pyrrhotite, pyrite, biotite and locally tourmaline. Pyrrhotite is generally more abundant than pyrite where significant gold grades are present. The structures controlling mineralization are moderately to steeply west-dipping shear zones that define a trend that is parallel to, but to the east of the Tasiast trend.

 

The Project area has considerable additional exploration potential as illustrated by the extensive levelled gold in soil anomalies shown in Figure 9-1. Several areas have been identified by TMLSA on the current Tasiast permits for near term drill testing. Targeting incorporates all available data sets including satellite imagery (Worldview-2), regional gold-in-soil data, airborne geophysical data (high resolution aeromagnetics and VTEM), regional scale geological maps of two generations, several generations of target scale geological maps, multi-element geochemical data derived from RC drill chips, assay results derived from historical and recent property scale drilling and trenching, reconnaissance geological observations and prospecting.

 

 
Page 51

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 9-1: Levelled Gold in Soil Grid

 

(GRAPHIC) 

 

 
Page 52

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

10.drilling

 

The total number of drill holes completed on the Project totals 16,600 holes (15,525 RC holes, 861 diamond core holes and 214 RC pre-collar with diamond tail holes) with an aggregate total of 1,739,350 m. Drill holes from 1999 to 2013 used in the resource model include 3,890 RC (620,106 m) and 290 diamond core holes (89,735 m) and 163 RC pre-collar with diamond tails (118,068 m) with a total of approximately 827,909 m (Table 10-1).

 

Drill programs were completed primarily by contract drill crews, supervised by geological staff of the Project operator. Where programs are referred to by company name, that company was the Project manager at the time of drilling and was responsible for the collection of data.

 

10.1Drilling Methods and Equipment

 

Normandy LaSource Development Ltd. Drill Programs

 

NLSD completed two drill campaigns between 1999 and 2000, including 412 RC holes for 32,463 m (including 43 RAB holes totalling 2,135 m) and 47 core holes for 5,456 m.

 

Drilling was initially undertaken on 200 m spaced east-west sections with 50 m hole centres on section, to depths of 50 m to 100 m. Drilling methods were predominantly RC with lesser core drilling (HQ; 63.5 mm core diameter) and included core tails to some RC holes (NQ; 47.6 mm diameter core).

 

Defiance Drill Programs

 

From March 1 to June 18, 2003, a total of 303 RC drill holes (25,812 m) were completed on the Piment zone by Defiance. RC drill holes were drilled in between old NLSD RC holes along drill fences at 25 m spacing along east-west fences. The majority of the RC drill holes were drilled at an azimuth of 270° (grid orientation) and at an inclination of -60°. From March 2004 to October 2004, a total of 112 RC holes (8,947 m including 4 RC pre-collars of four deep core drill holes) were completed on the Piment Zone and to the west (as sterilization of the waste dumps and tailings dam areas). RC drill hole diameters were 130.4 mm (5 5/16”).

 

From March 1 to May 25, 2003, a total of 29 core drill holes (2,908 m) were completed on Piment Central, Piment South, and Piment North (southern extension) by Defiance. Core diameter used was HQ3 (61.1 mm core diameter) for 25 of the 29 drill holes, while one core hole (SC062) was drilled utilizing NQ core diameter. Seven of the core holes were drilled primarily for geotechnical purposes and three vertical PQ3 (83 mm core diameter) drill holes (SC059, SC060 and SC061) were drilled to collect samples for metallurgical test work.

 

 
Page 53

  

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 10-1: Global and Resource Drill Hole Summary

 

Global Drill Holes - Collar File    
    Reverse Circulation * RC Pre-collar & Diamond Tail Diamond Total
Company Year Qty Metres Qty Metres Qty Metres Holes Metres
Normandy - La Source 1999 355 28,447 - - 11 585 366 29,032
Normandy - La Source 2000 57 4,016 - - 36 4,871 93 8,886
Defiance 2003 303 25,812 4 1,417 29 2,908 336 30,138
Defiance 2004 112 8,947 -  -  - - 112 8,947
Rio Narcea 2006 9 1,435 - - - - 9 1,435
Rio Narcea* 2007 242 25,110 1 173 72 7,927 315 33,210
Rio Narcea - Red Back* 2008 1,022 112,777 - - 23 2,716 1,045 115,493
Red Back 2009 2,946 203,324 1 300 26 2,681 2,973 206,306
Red Back - Kinross* 2010 2,904 243,666 75 52,628 66 13,265 3,045 309,559
Kinross* 2011 2,811 288,543 99 68,516 176 98,410 3,086 455,469
Kinross* 2012 2,693 267,175 12 1,892 287 66,329 2,992 335,396
Kinross* 2013 663 63,341 12 2,300 82 14,406 757 80,047
Kinross* 2014 456.00 37,068 1 491 22 4,924 479 42,483
Kinross* 2015 952.00 75,330 9 3,873 31 3,746 992 82,949
Grand Total   15,525 1,384,991 214 131,590 861 222,768 16,600 1,739,350

 

* Diamond Drill Holes include Met & Geotech Holes 213 holes @ 43,932 m (from 2007 to 2013). 1999 Reverse Circulation Holes include 43 holes @ 2,135 m of Rotary Blast holes. 2014 Reverse Circulation Holes include 15 holes @ 1,210 of Rotary Blast holes.

 

Resource/Reserve Model Drill Holes - Collar File    
    Reverse Circulation RC Pre-collar with Diamond Tail Diamond

Total

 

Company Year Qty Metres Qty Metres Qty Metres Holes Metres
Normandy - La source 1999 219 19,336 - - - - 219 19,336
Normandy - La source 2000 - - - - 31 4,358 31 4,358
Defiance 2003 299 25,644 4 1,417 28 2,798 331 29,859
Defiance 2004 28 6,011 - - - - 28 6,011
Rio Narcea - Red Back 2007 235 23,890 1 173 61 7,611 297 31,674
Red Back 2008 872 97,506 -   - - 872 97,506
Red Back 2009 759 113,045 1 300 - - 760 113,345
Red Back - Kinross 2010 735 153,577 70 50,966 - - 805 204,543
Kinross 2011 700 171,119 87 65,212 89 59,812 876 296,143
Kinross 2012 35 9,458 - - 29 8,296 64 17,754
Kinross 2013 8 520 - - 52 6,860 60 7,380
Subtotal   3,890 620,106 163 118,068 290 89,735 4,343 827,909

 

 
Page 54

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

From March 2003 to October 2003, four RC holes with core tails totalling 1,417 m were completed on the Piment Zone to check the down-dip extension of the northern Piment Central shoot.

 

Rio Narcea Drill Programs

 

During late 2006 and into 2007, Rio Narcea drill programs used an in-house CS2000 drill rig and an RC rig supplied by Drillcorp Sahara. During the period to August 10, 2007, before Red Back acquired the Tasiast Project, Rio Narcea drilled RC and diamond core holes. The RC drilling was specifically aimed at testing the northern extensions of the Piment Zone and infill drilling at the West Branch prospect.

 

2007-Sept 2010 Red Back Mining Drill Programs

 

Following the acquisition of the Project, Red Back commenced an aggressive program of RC drilling to fully define the mineral resources in the Piment and West Branch mineralized zones. Red Back also used a small RC rig to conduct shallow (40 m) open face RC-style drilling on district targets.

 

In 2010, Red Back initiated a diamond drilling program for deep exploration beyond the depth limit of the RC rigs, metallurgical test work relating to the dump and heap leach potential of the Project, and for quality control purposes. The majority of holes included RC pre-collars drilled to depths ranging from 200 to 300 m and were tailed with HQ core.

 

Sept 2010-Present TMLSA Drill Programs

 

TMLSA commenced a ramp up in exploration activity following completion of the Red Back acquisition.

 

The majority of the drilling that TMSLA completed between September 17, 2010, and December 31, 2010, focused on the West Branch deposits to expand the mineral resource, to test the extents of mineralization, and to continue with metallurgical test work. The majority of the holes included RC pre-collars drilled to depths ranging from 200 m to 300 m and were tailed with HQ core. Drill rigs used included the following types: Schramm T685WS, EDM2000 RC, EDM2000 core, UDR200, UDR650, UDR1200, Golden Bear 1400, Silver Bear A5, Coretex YDX-1800 and YDX-3L, and LF230.

 

In 2011, a total of 23 drill rigs were operating on site. This was reduced to three drilling rigs at the end of 2015.

 

 
Page 55

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Logging Procedures

 

For the Defiance, Red Back and TMLSA RC drill programs, a field geologist described the rock chips (dry and wet), and then placed a representative sample into pre-labelled plastic RC chip boxes. Logging was performed on hard-copy sheets by Defiance and data recorded included drill hole ID, sample number and depth, oxidation state, colour, presence of water, sample weight, lithologies, grain size, structure, alteration, vein types, and sulphide types and percentages. Red Back and TMLSA logging was recorded directly in digital format at the rigs. Data recorded included drill hole ID, sample number and depth, oxidation state, colour, presence of water, and lithologies. Selected RC holes from the West Branch region have been relogged for alteration and mineralization.

 

The Defiance, Red Back and TMLSA core logging geologists completed all geological and geotechnical descriptions and these were recorded on separate geological and geotechnical hard copy log sheets. All geological and geotechnical descriptions were encoded and standard codes were utilized during the program.

 

Once a core drill hole was completed, the detailed geological and geotechnical core drill logs were then submitted to the Geology Department for data input in Microsoft® Excel files. This procedure was replaced (near the end of 2009) with the current system of digitally recording geological information from core holes into Tough Books computers and uploading these directly into a Century System Geological Database software. Logging recorded rock quality designation (RQD), lithology, oxidation state, structural orientation, mineral association, vein types and density, sulphide types and volume, specific gravity, and point load test (PLT).

 

Defiance geologists mounted a digital camera on a frame with fluorescent lights for photographing all core in the boxes. Red Back and TMLSA captured core images under natural light.

 

10.2Collar Surveys

 

During the Defiance drill programs, the Defiance surveyor surveyed the collar of each RC and diamond drill hole upon completion, using a Geodimeter 510 total station instrument. The measurement was taken on the west side of the collar. The surveyor recorded the Cartesian coordinates digitally for each drill hole.

 

During Red Back and TMLSA programs, the surveyor surveyed the collar upon completion of the hole using a differential (GPS). Once completed, the Cartesian coordinates were digitally recorded and emailed to the database manager.

 

Since 2012, the survey data were recorded, validated and imported directly into the Fusion Remote Data Base by the surveyor.

 

 
Page 56

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

10.3Down-hole Surveys

 

During the Defiance drill programs, down-hole surveys of the drill holes were completed with a Humphries gyroscope due to the strong magnetism of the BIF units. Down-hole gyroscope measurements for drill holes drilled from 0 to 60 m involved a reading taken at 10 m intervals. Measurements were taken every 20 m down the hole for drill holes below 60 m depth. The gyroscope was oriented using the Geodimeter total station relative to the local NLSD 2500 E baseline grid. All of the survey data was digitally acquired, recorded and submitted to Defiance on a weekly basis on floppy diskette by Surtron survey personnel as Excel and Word files. Defiance geologists would review the raw collar and down-hole survey data for accuracy before uploading to the database.

 

Down-hole surveys completed during Red Back and TMLSA programs used north seeking gyroscope (continuous and multishot), single shot reflex and Mems gyroscope instruments. Measurements from the multishot tools were at 5 m intervals. Survey data was digitally acquired, recorded and submitted to Red Back and TMLSA on a daily basis via email. The tools were tested and calibrated on a weekly basis from a set station. Additionally, from mid-2012, Optical Televiewer (OPTV) and Acoustic Televiewer (BHTV) imagery were acquired for many diamond drill holes. The OPTV and BHTV data are mainly used for structural and geotechnical analyses.

 

10.4Recovery

 

Sample recovery for RC drilling in the NLSD campaigns is reported to have been good (Guibal et al., 2003). SRK noted that drill core recovery was variable in the oxidized zone and high (90% to 100%) in the fresh rock.

 

Diamond core recovery from Red Back and Kinross drill programs were collected on all core holes. Based on 17,718 measurements the average total recovery from core runs (in both oxide and fresh) is 98% and the RQD is greater than 93%. Measurements from downhole depths below 50 m (approximate oxide-fresh boundary) returned values of 99% and 95% for total recovery and RQD, in comparison to shallower depths where total recovery is 87% and RQD averages 43%.

 

Reverse circulation holes after September 2013 recorded the total weight of the samples for every metre drilled.

 

10.5Deposit Drilling

 

The Piment and shallow portion of West Branch deposits have typically been drilled at approximate 25 m x 25 m spacing, whereas the deeper portion (below 430 m vertical) of West Branch has been drilled out at 70 m x 70 m spacing.

 

 
Page 57

  

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Drill hole inclinations dominantly range between -50° and -75°, azimuths are dominantly 270°, and the mineralized zones dip between 45° and 65° to the east. Most holes therefore intersect the mineralized zones at a high angle; however the drill hole intercept widths reported for the Project are not true widths. Depending on the dip of the drill hole, and the dip of the mineralization, drill intercept widths are typically greater than true widths.

 

10.6Geotechnical, Hydrological and Metallurgical Drilling

 

Geomechanical drilling campaigns were conducted across the mine lease to identify potentially suitable locations for mine infrastructure. The campaigns required detailed knowledge of rock mass characteristics and ground-water conditions. Hydrological drilling was conducted in the area of the water bore field, to identify sufficient water for processing.

 

Large diameter core holes were completed to provide sufficient sample for metallurgical test work.

 

The various geotechnical studies completed, based upon the progress of pit development, include the following:

 

·Golder Associates (2004): This study provided preliminary pit slope design parameters for the oxide zone and fresh zone. Results were based on the analysis of geotechnical data collected in 2003 and were used in the preliminary mine planning and development of the project. The study focused on the BIF lithology as four open pits were proposed within this lithological unit. Rock testing was confined to this unit, and the drill-hole data was subject to a strong directional bias with almost all boreholes drilled at either 60° or 270° azimuths.

 

·Scott Wilson (2008a,b,c; 2009): This study provided slope stability analysis and ultimate pit slope design parameters of the four open pits (Piment North, Central, South-North and South-South) for the oxide zone and fresh zone. Results were based on the analysis of the geotechnical data collected in 2008, which was based on an orthogonally oriented drill hole program. Geotechnical and discontinuity data were collected and processed to form eleven pit sectors based on geotechnical characteristics. The study also included a review of the seismicity and hydrogeology of the Piment site. The 2008 investigation also focused on logging the wider variety of lithologies and structural features encountered within the four open pits. Laboratory and field rock strength testing was also undertaken on representative samples to establish base design values. Each pit sector was compared to the discontinuity sets to identify kinematically feasible modes of failure. Slope designs were done for a base pit, as defined by

 

 
Page 58

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

  the “$700 (ultimate) pit shell” provided by TMLSA. A series of recommendations included overall slope angle, bench stack angles, inter-ramp angles, and the structural and bedding controls based on operational assumptions adopted for safe operation.

 

·Scott Wilson (2010): This study provided slope stability analysis and ultimate pit slope design parameters for the West Branch area. Results were based on the analysis of geotechnical data collected in 2010, which was based on an orthogonal oriented drill-hole program. Geotechnical and discontinuity data were collected and processed to form four broad pit sectors based on geotechnical characteristics. The collected data was based on the configuration of drill holes of the West Branch proposed pit shell. The focus of the study was on logging a wider variety of lithologies and structural features encountered within the open pit footprint, based on experiences from the study conducted in 2008. Laboratory and field rock strength testing was also undertaken on representative samples to establish base design values. Each pit sector was compared to the collected discontinuity sets to identify kinematically feasible modes of failure. Slope designs were performed for a base of pit, as defined by a 30 kt/d CIL pit shell. A series of recommendations included overall slope angle, bench stack angles, inter-ramp angles, and the structural and bedding controls based on operational assumptions adopted for safe operation.

 

·Scott Wilson (2011): This study provided a slope stability analysis and refined the ultimate pit slope design parameters for the West Branch area. Results were based on analysis of the geotechnical data collected in 2010 and 2011. A total of 23 geotechnical and six hydrogeological drill holes were completed. Two pits at West Branch were designed (North and South pits). The northern pit assumes a 700 m pit depth, whereas the southern pit assumes a shallower depth.

 

·Golder Associates (2014) and Schlumberger (2014): A geotechnical and hydrogeological drilling program for the West Branch pit was completed from March to June of 2013 (eight holes at 4,612 m). The purpose of the drilling and investigation program was to provide additional geotechnical and hydrogeological data where data are lacking and to complement those data that currently exist from previous investigation campaigns.

 

10.7Comment on Drill Programs

 

In the opinion of the QP, the quantity and quality of the lithological, geotechnical, collar and down hole survey data collected in exploration and infill drill programs are sufficient to support mineral resource and mineral reserve estimation as follows:

 

 
Page 59

  

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

·Core logging meets industry standards for gold exploration

 

·Collar surveys have been performed using industry-standard instrumentation

 

·Down hole surveys have been performed using industry-standard instrumentation

 

·Recovery data from core drill programs are acceptable

 

·Geotechnical logging of drill core meets industry standards for open pit operations

 

·Drilling is normally perpendicular to the strike of the mineralization. Depending on the dip of the drill hole, and the dip of the mineralization, drill intercept widths are typically greater than true widths

 

·Drill orientations for Tasiast are generally appropriate for the mineralization style, and have been drilled at orientations that are optimal for the orientation of mineralization for the bulk of the deposit area. Drill orientations are shown in the cross-sections (Figure 7-7, Figure 7-8, and Figure 7-9), and can be seen to appropriately test the mineralization.

 

 
Page 60

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

11.sample COLLECTION, preparation, analyses, and security

 

Project staff of the operator at the time was typically responsible for the following:

 

·Sample collection;

 

·Core splitting;

 

·Delivery of samples to the analytical laboratory;

 

·Density (specific gravity) determinations;

 

·Sample storage; and

 

·Sample security.

 

11.1Sampling Method and Approach

 

Geochemical and Trench Sampling

 

As the geochemical and trench data have been superseded by information from drilling and mining operations, these sample types are not discussed further in the Technical Report. This information is not relied on for use in geological modelling or resource estimations.

 

NLSD

 

Little information has been kept or is available regarding drilling procedures used in this drilling by NLSD.

 

2003-2004 Defiance and 2007 Rio Narcea

 

RC Sampling

 

All of the RC holes were sampled at one-metre intervals and each sample was collected in a large plastic sample bag that was held below the cyclone spigot by a drill helper. All samples were sent for assay except those that originated from the non-mineralized hanging wall at the start of each hole. To avoid sample contamination after a drill run was completed, blow-backs were carried out at the end of each 6.0 m run by the driller whereby the percussion bit was lifted off the bottom of the hole and the hole was blown clean. When water was encountered in the hole, the driller would dry out the hole by increasing air pressure into the hole and lifting and lowering the rods prior to continuing the drilling.

 

 
Page 61

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Throughout the Defiance RC drill program, logging of all RC drill holes was conducted by the field geologist at the drill site. After each drilled 1.0 m interval, the sample was weighed, sieved and split to give a 2 kg to 3 kg sample for analysis.

 

A representative sub-sample for geological logging was collected from the large sample bag by spearing a small diameter PVC pipe into the bag and emptying the contents of the PVC pipe into a hand sieve.

 

At the end of each day or at the completion of a RC hole, calico sample bags for RC drill holes completed that day were loaded onto a 4x4 pick-up truck by the field geologist and then delivered directly to the on-site sample preparation laboratory. Once the samples were unloaded from the pick-up truck and both the field geologist and laboratory technician confirmed receipt of all calico sample bags, the field geologist then registered the sample number sequence in the database.

 

Diamond Drill Core Sampling

 

Upon completion of geological and geotechnical core logging of a diamond drill hole, Defiance’s core logging geologist identified the sections of core to be sampled and analysed for gold. Once identified, the core-logging geologist measured and marked out the sample intervals onto the uncut core down the right hand side of the orientation line. Individual sample intervals were recorded onto a core-sampling sheet. The core was sampled according to lithological boundaries and vein widths, but the maximum sample interval did not exceed 1.50 m in length.

 

At the core cutting facility the drill core boxes were stacked in ascending order so as to avoid sampling mix-ups. The core was cut on the orientation line marked by the geologist and the right hand side of the core (looking down hole) was placed in a numbered calico bag.

 

Once the core for a drill hole was cut and sampled, the core cutter and the core logging geologist then delivered the samples, with the core sampling sheet, to the preparation laboratory technician for sample preparation.

 

Red Back and TMLSA

 

RC Sampling Procedure

 

To minimize down-the-hole deviation, RC drilling is conducted with contract single and multi-purpose rigs using a standard 5½” face sampling hammer leading a 4½” rod string.

 

The entire sample is collected in a large plastic bag tightly clamped onto the cyclone base. The entire length of each RC hole is sampled. A one-metre sample length is used in all holes. Dry samples, of nominal 20 to 25 kg weight, are reduced in size by riffle

 

 
Page 62

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

splitting using a three stage Jones riffle splitter to about three to four kilograms, and then placed in pre-numbered sample bags for dispatch to the assay laboratory. A record is made at the drill site of the sample identity numbers and corresponding intervals, and this is also recorded in the geological log.

 

After September 2013, RC samples with a nominal weight from 36 kg to 40 kg (each 1 m) were collected in a large plastic bag, tightly clamped onto the cyclone base and reduced in the field by 50/50 manual riffle splitters. About 6 kg to 8 kg weight samples were placed into pre-numbered sample bags to dispatch to the laboratory. Every 20 samples, a field duplicate was collected as part of the quality assurance/quality control (QA/QC) procedure.

 

DH Sampling Procedure

 

For diamond drilling, core was transported from the drill rigs to the core facility where geological and geotechnical core logging was completed. The geologist marked one-metre intervals and orientation lines (bottom of hole) along the core axis for core cutting. A record was made at the core facility of the sample identity numbers and corresponding intervals. At the core cutting facility the drill core boxes were stacked in ascending order so as to avoid sampling mix-ups. The core was cut on the metre and orientation lines and the left hand side of the core looking down-hole is placed in a numbered plastic bag with sample ticket.

 

Once the core for a drill hole was cut, sampled and bag sealed, the core was then stored in a secure area (either locked 40 ft shipping container or fenced off area) for sample dispatch.

 

All the sampling processes for RC and diamond drilling were handled under TMLSA’s chain of custody.

 

Quality Assurance/Quality Control Sampling Procedure

 

Before 2012, the QA/QC process was as follows:

 

·A routine analytical sample ‘field duplicates’ were collected every 20th sample, and submitted in blind sequence after every 20th and 21st interval of the sample stream.

 

·For RC samples, a further representative triplicate sample was routinely collected every 60th original sample in the sequence, and retained for later submission to a third-party, independent referee laboratory.

 

 
Page 63

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

·Analytical ‘blanks’ were inserted every 20th original sample, and were taken from barren dune sand collected from a source distant from the mine.

 

·GANNET, ROCKLABS and GEOSTATS certified reference material, also known as standard reference material (SRM), in pulp form, were selected based on certain ‘resource thresholds,’ and inserted as standards every 20th sample.

 

·All QA/QC samples were inserted by the rig geologist at the rig.

 

·Grades of standards to be used were selected by the senior geologist and provided to the rig geologist in the rig box.

 

·TMLSA submitted 16% routine QC samples within the sample string.

 

·Holes were submitted by the rig geologist directly to the on-site laboratory as individual batch jobs, or dispatched from the site to Mali, Burkina Faso and South African laboratories.

 

In contrast to Defiance and Rio Narcea, Red Back and TMLSA routinely sampled every metre drilled for RC, and selectively sampled diamond holes, based on visual evidence of alteration and mineralization.

 

In 2012, a QA/QC team was established that was in charge of the sample procedure, sampling protocols, sample transport, sample tracking and reporting.

 

In 2012, the following quality control processes were implemented:

 

·Field duplicates were collected every 20th sample, and submitted in blind sequence after every 20th and 21st interval of the sample string. (This procedure was also performed before 2012.)

 

·Analytical ‘blanks’ were inserted every 20th original sample, and were taken from gold barren material (not sand) collected from a source distant from the mine. This material was submitted blind with the samples dispatched, as with other samples. RC blanks were crushed to simulate the RC sample grain size. Diamond drill blanks were used that resembled the diamond drill core size.

 

·CANMET, ROCKLABS and GEOSTATS certified reference material in pulp form were selected based on certain resource thresholds, and inserted as standards every 20th sample. (This practice was also performed before 2012.)

 

 
Page 64

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

·All QA/QC samples were inserted by the QA/QC team in the exploration yard, except the field duplicates that were generated at the drill. Grades of standards to be used were selected by the geologist that logged the RC or DD holes and they were provided by the QA/QC Team. For every batch, TMLSA inserted 16% QC samples within the sample string. Holes were submitted by the QA/QC team directly to the on-site laboratory as individual batch jobs, or dispatched from the site to Mali, Burkina Faso and South African laboratories.

 

Twice in 2013, 5% of the samples (pulp) were sent to a third laboratory to be checked.

 

Density/Specific Gravity

 

The results from 1,699 bulk density determinations completed by NLSD at Tasiast during previous drilling programs are available. The origin of the sample, its borehole number and sample depth was entered as an individual MS Access database file into NLSD’s project database. However, information on the sample size/length, lithology and oxidation state was not recorded in the NLSD database. The bulk density measurement for each NLSD sample was derived by using the Weight in Air/Weight in Water (Archimedes) method. The oxidized core samples were sealed with molten wax and re-weighed to determine the weight of the paraffin coating, prior to weighing in water. The bulk density determinations were done on short (5 cm), half core specimens, taken at close intervals. The NLSD bulk density data were collected from one core hole in the Piment South area and from 13 core holes from the Piment Central area.

 

A total of 131 bulk density measurements were carried out on lengths of complete drill core by Defiance during their programs. Density determinations were undertaken prior to core sawing on 131 samples of about 8 cm to 15 cm in length and of both HQ and HQ3 diameter. The water displacement method was used.

 

From 2008 to December 2011, Red Back and TMLSA completed 24,702 specific gravity determinations of bulk density using the Archimedes method. The samples were selected to provide a representative suite of densities covering all major lithology types and from all oxidation levels.

 

Initial Red Back and TMLSA density determinations were done using wax-coated samples for both oxide and primary material. This procedure was changed by using uncoated core samples for only primary material to speed up the test work. Duplicate tests with one-wax coated samples for every lithology per hole were done to evaluate bias between the data pairs. About 650 duplicate tests were done up to December 2011. Initial analysis of the check samples showed very good correlation between the uncoated and coated density values. A total of 90% of the dataset shows a difference of 1% variability between the samples pairs (coated and uncoated). For the 2013 model,

 

 
Page 65

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

26,940 density records were used to develop the new density values. The 2013 model used the same methodology of combining the rock type (or lithology) and state of oxidation to determine the appropriate density value. These values were assigned to the block model, based on these two values. If no data were available, the 2011 model density values were still used in the 2013 model.

 

Using specific gravity measurements taken on the various rock types, an average density value was calculated for each logged rock type and oxide type. These values were then assigned to the domains in the block model using simple manipulation scripts.

 

The results of the on-going density measurements on the different rock types for the grade control are in good agreement with the resource model values used for West Branch. The reconciliation of total tonnes mined between the resource model and actual production is also good for both 2014 and 2015.

 

11.2Analytical Laboratories

 

Sample preparation was undertaken on site by NLSD staff during their drill programs. Analytical laboratories used were the BRGM laboratory in Orleans, France and the OMAC laboratory in Ireland. QA/QC was undertaken by Genalysis Laboratories in Perth, Australia, and SGS Laboratories in France. Laboratory accreditations at the time are not known; all analytical laboratories were independent of NLSD.

 

During Defiance’s RC and diamond drill programs, the analytical work was carried out by SGS Analab in Kayes, Mali and by Abilab located in Bamako, Mali. Analab is an ISO accredited laboratory whereas Abilab is not ISO accredited. The laboratories were independent of Defiance.

 

Following Red Back’s acquisition of the Tasiast deposit in August 2007, an on-site SGS Analab assay facility became operational. Prior to that time, samples had been prepared on site by Red Back staff under supervision of senior geological staff. All drill samples since 2007 have been prepared and analysed under contract by SGS on site and by SGS Analab in Kayes, Mali, SGS Analab in Morila, Mali, and SGS in Ouagadougou, Burkina Faso. Laboratories were independent of Red Back. The two SGS laboratories hold ISO9000 accreditations.

 

In December 2010, SGS constructed and commissioned a mobile sample preparation facility in Nouakchott, Mauritania, and selected samples were submitted to the facility for preparation. In late 2011, a new on-site SGS preparation and assay laboratory was commissioned at Tasiast, with a capacity of up to 2,000 samples per day. In mid-2012, TMLSA stopped sending exploration samples to the SGS Tasiast laboratory due to quality control concerns. Due to the large volumes of the samples and laboratory delays,

 

 
Page 66

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

TMLSA started sending samples to nine laboratories outside the country to different accredited laboratories. In April 2013, ALS Chemex took over the Tasiast laboratory facilities and initiated carrying on the sample preparation and analytical services. The Tasiast laboratory facilities were previously operated by SGS.

 

11.3Sample Preparation

 

Midas, Defiance and Rio Narcea RC drill sample preparation involved the entire RC calico sample bag, which was oven-dried for 24 hours and then weighed before pulverizing the entire 2 kg to 3 kg subsample using a Labtecnics LM5 mill. Each core sample was crushed to -10 mm in a jaw crusher, and the entire sample was pulverized to P90 (90% passing) at 75 µm using a Labtecnics LM5 mill. Barren dune sand was used to clean the bowls after every sample. The pulverized material was sampled using a spatula, and two 120 g pulp sub-splits were taken; one packet was prepared for shipment to the assay laboratory and one packet remained on site for future reference. Blanks of dune sand and certified reference standard were then inserted with the field samples.

 

Sample pulp shipments were conducted on a weekly basis. The samples were transported in secured wood boxes to Nouakchott, where Mauritanian Custom inspected the shipment and released the proper documentation for exportation. The boxes included a sample submission sheet prepared by the laboratory manager. Samples were then shipped by airfreight to SGS Analab.

 

At SGS Tasiast and SGS Nouakchott, the entire RC and core sample was oven-dried for 24 hours in a cleaned metal dish, weighed and then crushed to 75% passing at 2 mm. At SGS Tasiast, a 1.5 kg subsample was split using a Jones riffle splitter, and pulverized in a Labtech Essa LM2 ring pulverizer using a 2 kg bowl to 85% passing at 75 µm. At SGS Nouakchott, the sample was split once using a Jones riffle splitter and pulverized in a Labtech Essa LM2 ring pulverizer using a 2 kg bowl to 85% passing at 75 µm. Both laboratories took a 200 g subsample for gold (Au) fire assay.

 

At the SGS Tasiast laboratory and relocated mobile sample preparation facility, the procedure for sample analysis remains unchanged. However, subsample size at the Tasiast laboratory has been increased to 2 kg, to improve the precision of results.

 

For RC and core samples processed by SGS Analab in Kayes, samples were stockpiled in a secure area within the Tasiast core facility, and collected by a truck contracted by either Analab or TMLSA for shipment to Kayes. The samples were enclosed and secured in a large tarpaulin and transported directly from the site to the laboratory. The entire core or RC sample was oven-dried for 24 hours and then weighed before pulverization. Samples were crushed to 75% passing 2 mm, and two 1.5 kg subsamples

 

 
Page 67

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

were split using a Jones riffle splitter and pulverized in a Labtech Essa LM2 ring pulverized using a 2 kg bowl to 85% passing at 75 µm. These two pulps were recombined before being subsampled (200 g) for an Au fire assay.

 

After ALS Chemex took over the laboratory facilities at Tasiast in early 2013, a few changes were introduced at the sampling preparation stage, including:

 

·Drying the entire RC or core samples for three to four hours at 105 ºC.

 

·Registering the dry weight.

 

·Crushing the entire samples 80% passing 2 mm. In November 2013, it was decided to increase the passing to 85% passing 2 mm. Every 20 samples must generate a preparation duplicate.

 

·Splitting the samples using a Jones riffle splitter to obtain 1 kg, and pulverizing the samples to 85% passing 75 µm.

 

·Taking 200 g for analysis. Every 20 samples must generate a pulp duplicate.

 

11.4Sample Analysis

 

For the samples processed by BRGM on behalf of NLSD, the following methods were used:

 

·Roasting (77 Phase 1 samples and all Phase 2 samples)

 

·Total attack (hydrofluoric acid and aqua regia);

 

·Atomic absorption (AA) analysis, detection limit: 20 ppb Au (Phase 1) and 100 ppb Au (Phase 2).

 

Check analysis of 74 Phase 1 samples showed no significant variations between roasted and non-roasted samples (Guibal et al., 2003).

 

OMAC used the following methods on samples processed for NLSD:

 

·Ignition / Aqua Regia Digest / MIBK Extraction / AA on 30 g sample; detection limit: 10 ppb Au; 10% repeats.

 

·Fire assay (30 g sample): re-analysis of 903 mineralized samples (Phases 1 & 2) + all samples >1 g/t Au and those <1 g/t Au which were included in mineralized intersections (Phases 3 & 4); detection limit: 10 ppb Au.

 

 
Page 68

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

All of the sample pulps from the Midas, Defiance and Rio Narcea drill programs were analysed for gold using a 50 g fire assay with an atomic absorption spectroscopy (AAS) finish at both laboratories. The Analab 50 g fire assay/AAS method (FA50) has a lower detection limit of 0.005 g/t Au; Abilab’s lower detection limit is 0.010 g/t Au.

 

Analab routinely ran random check assays in all batches. However, when the laboratory was notified of possible samples containing high values of gold for the core samples, Analab carried out a fire assay/AAS method, with repeats in some case, as well as fire assay/gravimetric analysis for samples grading greater than 5.00 g/t Au. Analab also provided Defiance with its internal QA/QC data during the analysis period.

 

For Red Back and TMLSA samples, sample pulps were analysed for gold using a 50 g fire assay with an AAS finish with a detection limit of 0.01 g/t Au. Results higher than 5 g/t Au were re-analyzed by fire assay technique and gravimetric finish. In 2012, TMLSA began gravimetric finishes for gold above 5 g/t, and also began screened metallic fire assays.

 

11.5Quality Assurance and Quality Control

 

Most of the documented QA/QC cited by SRK in 2003 on NLSD samples related to measurements of the analytical errors through pulp duplicates, where two analytical methods (aqua regia: AAS and Fire assaying: FA) are compared (Guibal et al., 2003). No significant problem was detected. In early 2003 a total of 429 pulp samples, collected by staff from TMLSA and representing close to 10% of the mineralized samples within the wireframed resources, along with 54 standards (of values 0.5, 1.66 and 3.22 g/t Au) and 18 blanks were re-assayed by Genalysis. SRK noted that the Genalysis results compared well with the database and standards and blanks were assayed within acceptable limits.

 

For the Defiance and Rio Narcea drill programs, a total of 21,686 RC sample pulps, including field duplicates, blanks and standards, and 904 diamond drill hole core sample pulps, including field duplicates, blanks and standards, were shipped in 16 batches, of which 14 went to Analab and two went to Abilab. Included within these sample batches were a total of 774 field duplicate samples, each one being a second split from a 1 m interval field sample bag, and 1,136 preparation duplicates, each one being a second split from the pulverized RC and core sample at the preparation laboratory.

 

The analytical QA/QC program implemented by Defiance was monitored by the routine submission of commercial SRMs purchased from Gannet Holdings Pty. Ltd. of South Perth, Western Australia. SRMs were inserted at every 20th sample and an internally prepared coarse blank sand inserted at every 10th sample within the RC and core sample stream. Field duplicates were collected by the field geologist after the completion of each

 

 
Page 69

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

RC hole and the number of field duplicates on a per RC hole basis was dependent on the length of the hole or equivalent to every 20th sample. Preparation duplicates were selected for every 20th sample number in a sequence and submitted as a separate sample number series on a per batch basis.

 

TMLSA commenced a systematic process for analysis of ‘Prep Duplicates’ and ‘Pulp Duplicates’ from mid-2011. The duplicates are collected every 20th sample within intervals of visual mineralization and resubmitted blind to the laboratory. In addition, other initiatives TMLSA implemented for QA/QC measures in August 2011 included using the standard deviation of the mean value for the standard reference material (previously ±10% of mean value), rules for batch pass and failures, and a log of all errors.

 

In 2011, TMLSA engaged an independent consultant to provide a regular review of the QA/QC data. Issues identified during the early review in September 2011 (Heberlein, 2011), such as switched standards and standard identification, have been corrected and control actions implemented. Other issues, such as analytical repeatability over time, are still being addressed, and since then control actions were implemented to reduce the number of errors.

 

Additional actions implemented in 2012 and 2013 to address other recognized issues, such as duplicate precision, include the following:

 

1.Conducted routine crushing and analyzed pulverized duplicate samples at the majority of the laboratories.

 

2.Conducted gradual replacement of three tier-riffle splitters and cone splitters on RC rigs by 50/50 manual riffle splitters.

 

3.Established a dedicated group to control and monitor sampling, dispatch and quality control analytical results.

 

4.Assigned a Tasiast technician permanently to the on-site Tasiast exploration preparation facility to monitor and control the workflow.

 

5.Conducted a routine independent-consultant review of data and laboratory audits.

 

6.Reviewed various sample volume and preparation methods that have resulted in larger samples (between 5 kg and 10 kg) collected from RC rigs in 2013.

 

 
Page 70

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

SRK 2013 QAQC Review

 

In April 2013, SRK conducted a review of the analytical quality control procedures and results for the Tasiast gold project in Mauritania (Chartier, 2013). The objective of the review was to provide an independent analysis of the sampling procedures and a review of the analytical quality control results for the data to be used in the current resource estimate.

 

SRK visited the Project site from October 11 to 15, 2013. SRK also visited a third-party preparation laboratory operated by SGS Minerals in Nouakchott, Mauritania. The purpose of the site visit was to audit project technical data and collect all relevant information for the compilation of the Sample Preparation, Analyses, and Security and Data Verification sections of a technical report. SRK was given full access to relevant data and conducted interviews with Kinross personnel to obtain information on past exploration work and understand the procedures used to collect, record and analyze historical and current exploration data.

 

SRK reviewed the field procedures and analytical quality control measures used in the Tasiast gold project. In SRK’s opinion, Kinross personnel used care in collecting and managing field and assay exploration data. The sample preparation, security and analytical procedures used by Kinross are consistent with generally accepted industry best practices, and are therefore adequate to support the mineral resource estimation.

 

A summary of SRK’s main conclusions are:

 

·The sampling procedures used meet industry best practices. All borehole sampling was conducted by appropriately qualified personnel under the direct supervision of appropriately qualified geologists. The sample preparation, security, and analytical procedures were consistent with generally accepted industry best practices and are therefore adequate to support Mineral Resource estimation.

 

·The paired data results are consistent with results expected from gold mineralization in an epigenetic deposit that is structurally and lithologically controlled.

 

·Results from the SRMs are acceptable.

 

·The non-certified field blanks consistently returned values at or below the detection limit at most primary laboratories.

 

·SRK concurred with Heberlein (2013) that sample preparation procedures are failing to properly homogenize the samples. SRK attributes part of that failure to

 

 
Page 71

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

 a prominent nugget effect and notes that control charts display no apparent bias between original and duplicate samples.

 

·Much of the analytical data informing the Mineral Resource estimate was derived from several different unaccredited laboratories, including the mine laboratory operated by SGS.

 

11.6Sample Storage

 

Sample pulps are returned from the laboratory in plastic vials or sealed paper envelopes, and these are stored in sealed containers at site. The majority of historic coarse reject samples were not stored, but TMLSA has commenced storing selected mineralized coarse reject material. The remaining half of the drill core is well stored in stacked wooden trays referenced by hole identification number and interval length. Some core intervals have been totally sampled for metallurgical or check (umpire) sampling.

 

11.7Sample Security

 

Following TMLSA’s acquisition of the Project in September 2010, all drill samples collected are under direct supervision of Project staff from the drill rig and remained within the custody of staff up to the moment the samples were delivered to laboratory or placed on contracted trucks for delivery to the Mali laboratory. Samples, including duplicates, blanks and certified reference materials are delivered daily from the drill rig to a secure storage area within the fenced Tasiast core facility.

 

Chain of custody procedures consist of filling out sample submittal forms that are sent to the laboratory with sample shipments to make certain that all samples are received by the laboratory.

 

11.8Comment on Sample Collection, Preparation, Analysis and Security

 

In the opinion of the QP, the sampling methods are acceptable, meet industry-standard practice, and are adequate for mineral resource and mineral reserve estimation and mine planning purposes, based on the following:

 

·Data are collected following industry standard sampling protocol

 

·Sampling has been performed in accordance with industry standard practices

 

·Sample intervals in RC and core drilling comprise a maximum of 1.5 m for core and 1 m to 2 m for RC. Samples are broken at lithological and mineralization changes in the core. Sample intervals are typical of sample intervals used for

 

 
Page 72

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

 gold mineralization in the industry, and are considered to be adequately representative of the true thicknesses of mineralization. Not all drill material was sampled in early drill programs

 

·The specific gravity determination procedure is consistent with industry-standard procedures

 

·There are sufficient specific gravity determinations to support the specific gravity values utilized in waste and mineralization tonnage interpolations

 

·Geochemical sampling covered sufficient area and was adequately spaced to generate first-order geochemical anomalies, and thus is representative of first-pass exploration sampling

 

·Drill sampling has been adequately spaced to first define, then infill, gold anomalies to produce prospect-scale and deposit-scale drill data. In general, the drill collar spacing ranges from 25 m x 25 m to 70 m x 70 m

 

·Sample preparation for RC and core samples has followed similar preparation procedures. These procedures are in line with industry-standard methods, and suitable for the greenstone- and BIF-hosted coarse-gold deposit style

 

·The QA/QC program comprised insertion of blank, duplicate and SRM samples. The QA/QC program results do not indicate any problems with the analytical programs, therefore the gold analyses from the RC and core drilling are suitable for inclusion in mineral resource and mineral reserve estimation

 

·Sample security has relied upon the fact that the samples were always attended or locked in appropriate sample storage areas prior to dispatch to the sample preparation facility. Chain of custody procedures consist of filling out sample submittal forms that are sent to the laboratory with sample shipments to make certain that all samples are received by the laboratory

 

·No factors were identified with the drill programs that could affect mineral resource or mineral reserve estimation

 

·Current sample storage procedures and storage areas are consistent with industry standards.

 

 
Page 73

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

12.data verification

 

A number of verification checks have been performed on data collected from the Project, either in support of technical reports, or as part of the Project feasibility study.

 

12.1Verification in Support of Technical Reports

 

A number of external consultants and consultancies have reviewed Project data, and made recommendations for future work.

 

SRK 2003

 

SRK (Guibal, 2003) reviewed the data available in 2003, as part of supporting documentation for the acquisition of Midas by Geomaque, and commented:

 

·Although SRK was not involved in the selection and collection of the check samples, the documentation supplied by [Midas] which includes all the analytical results show that the general quality of the sampling/assaying is acceptable and to industry standards;

 

·Although the density data originates from a relatively small number of drill holes, there are indications that a single tonnage factor for oxide and for primary, as used in the resource estimates, is a simplification of the true variation with depth.

 

ACA Howe 2003 and 2007

 

ACA Howe inspected Defiance’s sample preparation facility, and considered the facility to be reasonably well equipped and maintained, in accordance with acceptable industry standards (Leroux and Puritch, 2003; Leroux et al., 2007).

 

Midas collected a total of 429 pulp samples of known NLSD drilled mineralized zones in early 2003 (Hyde, 2003). Midas inserted blanks and standards and submitted this sample batch to Genalysis. The Genalysis results compared well with the NLSD assays and the standards and blanks inserted by Midas assayed within acceptable limits.

 

A comparison of RC and core duplicate samples indicated no major bias across all grade ranges. Howe considered that the degree of scatter shown in graphed data was acceptable for resource estimation purposes. No bias occurred towards the higher-grade original or repeat assays.

 

A total of 134 one metre interval RC samples from six of Defiance’s RC drill holes and 27 core pulp samples from two Defiance core drill holes were submitted by Howe to ALS Chemex Laboratories in Mississauga, Ontario for check analysis. Upon review of the

 

 
Page 74

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

results, Howe was of the opinion that its independent check assay results confirmed the presence of gold mineralization at Tasiast.

 

SNC-Lavalin 2004

 

Defiance selected mineralized intersections from 30 RC holes covering the four mineralized areas of the Piment Zone, which were sent to Canada for metallurgical test work. SNC-Lavalin (SNC) (Demers et al., 2004) reviewed the drill hole information on the geological sections prepared by Howe and combined the sampled intersections of several drill holes to obtain nine samples considered to be more or less representative for the various mineralized zones and their high and low gold grades. These samples were sent to SGS Lakefield in Ontario, Canada; an ISO/IEC 17025 accredited laboratory for assay. The comparison of the assay results of the initial samples and those from Lakefield was acceptable and showed a reasonable correlation.

 

SNC representatives collected eight samples of RC drilling chips that had previously been assayed by Analab. These samples were sent to Lakefield for assay. Results showed that gold was present in the indicated mineralized zones even though the correlation was rather erratic due to the statistically low number of samples.

 

Red Back 2008-2010

 

Red Back conducted an analysis of the available, historical QA/QC data from Defiance and Rio Narcea as part of the February 2008 resource update comparing all historical data with data generated by Red Back as at February 2008.

 

The following conclusions were noted (Stuart, 2008):

 

·Globally, all of the laboratories used to compile the Tasiast resource have reported the ore grade standards well. On average, 85% of the six +1.5 g/t Au internationally-accredited standard reference materials (SRMs) submitted reported to within an accuracy of +/-10%. The historical pre-Red Back database reported 86%. The Red Back database reported 84%

 

·A minor negative bias was repeated in each of the standards tested at each of the laboratories. The negative direction of the standards bias, however, results in a degree of conservatism in the assays reported

 

·The <1.0 g/t Au standards performed less well with a range of 67% to 75% of the standards submitted reporting to within +/-10%. The poorer precision and accuracy of the QA/QC data below 1.0 g/t Au is evident across the whole of the resource timeframe

 

·Both routine Red Back and pre-Red Back blank submissions performed well, exhibiting only a minor low level <50 ppb Au cross-contamination. Evidence

 

 
Page 75

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

 suggests a component of poor blank selection may have contributed to the Red Back higher bias and was noted for further attention

 

·The total operational precision (TOP) achieved by Red Back, demonstrated by a percent Median Absolute Half Difference (%MAHD) = ±14% of resource grade assays >0.2 g/t Au, is generally within acceptable limits of a coarse gold deposit such Tasiast. The coarse gold nature of the deposit is apparent within the range of errors expressed by the 90th percentile Absolute Half Difference (AHD) = ± 58%

 

·While analysing the historical pre-Red Back duplicate data it was observed that the historical resource data reported similar “nuggetty” duplicate assaying, closely comparative to the RBK data with %MAHD = ±14% and a P90 AHD = ± 50% >0.2 g/t Au. The datasets have equivalent coarse gold features and equivalent assaying precision

 

·The imprecision consequent of coarse gold is evident across the entire Tasiast grade profile from 0.2 g/t Au to 10 g/t Au. Clustering of “nuggetty assaying” is often observed in mesothermal greenschist facies, epigenetic, structurally-controlled deposits at the high-grade end of the profile due to the coarse gold being hosted dominantly in the quartz vein materials, the gold being finer, and closer to sulphide lattice within the disseminated selvages

 

·Red Back considered the extant of the assay data included in the Tasiast resource data to be accurate and precise to within the inherent, natural coarse grade variation observed in the grade profile of this structurally controlled, sub-amphibolite, BIF-hosted style of gold mineralization.

 

Review of the blank, duplicate and SRM submissions in 2009 and 2010 (Stuart, 2009; Stuart, 2010) indicated no significant errors or biases in the analytical data. Prior to late 2009 the majority of the field duplicate analyses completed were from non-Greenschist mineralisation styles, e.g., Piment iron-formation and West Branch footwall. A total of 16,907 (2009) and 15,929 (2010) QA/QC samples were blindly inserted as part of the routine sample preparation and were submitted for analysis. Red Back concluded that the QA/QC data reported was of industry accepted standards and the assay data was considered reliable for inclusion in the December 2008, 2009 and 2010 resource estimations.

 

12.2TMLSA QA/QC

 

The data presented below covers all QA/QC data for 2011. In 2011 a total of 22,525 QA/QC samples including standards (STD), blank (BLK) and field duplicates (FDups) were submitted routinely and blindly to the labs with resource related submissions. TMLSA maintained 10% total QC through the sample stream.

 

 
Page 76

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Because of the volume of samples, 18 different laboratories were used for the sample analysis. Table 12-1 presents the summary statistics of sample types submitted to the various laboratories for analysis.

 

Table 12-1: QA/QC Samples by Laboratory

 

Laboratory Standard Blank RC Duplicate Core Duplicate
Actlab Burkina Faso 199 209 222 0
ALS Chemex Ouaga 447 454 189 262
ALS Johannesburg 599 621 403 251
ALS Kumasi 326 330 288 63
ALS Loughrea 108 86 82 42
ALS Nouakchott 4 4 0 5
ALS Romania 527 512 303 280
ALS Tasiast 94 90 4 86
ALS Vancouver 226 252 231 15
SGS Kayes 13,498 14,583 12,706 1,162
SGS Kayes Lab 68 77 14 160
SGS Lakefield 9 9   18
SGS Morila 6,180 6,583 5,968 364
SGS Ouaga 1,420 1,484 1,213 223
SGS Ouaga Lab 81 80   80
SGS TM Lab 386 400 54 338
SGS TML 4,714 5,215 4,416 809
Unknown 812 1,905 0 0
Total 29,698 32,894 26,093 4,158

 

Table 12-2 presents the data used for the 2011 QA/QC analysis after results that are likely to cause bias in the analysis have been removed. Assay results that were excluded in the QA/QC analysis are as follows:

 

·IS - insufficient samples with assigned values of -1 in the assay results.

 

·LNS - listed not received samples with assigned values of -2 in the assay results.

 

·Samples with gold values below the resource threshold of 0.1 g/t Au were excluded in the Half Absolute Relative Difference (HARD) analysis for the

 

 
Page 77

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

 duplicate data pairs because it does not have much relevance to the potential limit of economic mineralization.

 

·Assay pairs involving standards and duplicates with unrelated results were considered as results with gross errors. The threshold for assays with gross errors was fixed at HARD value of ±75%. Assay pairs (standards and duplicates) with values greater than this threshold were excluded from the QA/QC analysis.

 

Table 12-2: 2011 QA/QC Samples Analysed by Laboratory

 

Laboratory Standard Blank RC
Duplicate
Core
Duplicate
ALS JHB 290 300 50 42
ALS Ouaga 308 316 15 25
SGS Kayes 3,570 3,638 552 159
SGS Morila 1,758 1,828 289 83
SGS Ouaga 570 598 25 73
SGS TML 1,075 1,101 113 100
Total 7,571 7,781 1,044 482

 

Each standard is rated on how accurately the laboratory has reported its value. Results of the standards are assessed against the inner (±2 x standard deviation) and outer limits (±3 x standard deviation). The blanks are also expected not to report above 0.05 g/t Au. Standards and blanks that failed accuracy controls were requested to be re-analyzed where a material impact on the reported results was considered. A precision analysis is conducted on the duplicates. Precision is defined as the level of error obtained at the 90th percentile in order to reproduce a sample or data.

 

An average accuracy of 93% was achieved for the internationally accredited SRM standards (see Table 12-3). This implies that 93% of the total SRM samples submitted to the various laboratories reported within acceptable limit of ±3 standard deviation. Routine field blank samples submitted to the various laboratories reported about 99% of the samples below 0.05 g/t Au.

 

 
Page 78

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 12-3: 2011 Resource QA/QC Results

 

Laboratory Total QA/QC
(Standards)
STD within
1 ∂
STD
within 2 ∂
STD
within 3 ∂
BLANK <
50 ppb
Actlab Burkina Faso 199 91% 93% 94% 99%
ALS Chemex Ouaga 447 75% 93% 97% 99%
ALS Johannesburg 599 67% 88% 96% 99%
ALS Kumasi 326 70% 93% 96% 99%
ALS Loughrea 108 74% 90% 98% 99%
ALS Nouakchott 4 90% 100% 100% 100%
ALS Romania 527 90% 100% 100% 100%
ALS Tasiast 94 84% 91% 100% 100%
ALS Vancouver 226 81% 96% 98% 99%
SGS Kayes 13,498 78% 94% 98% 100%
SGS Kayes Lab 68 79% 97% 100% 100%
SGS LAKEFIELD 9 100% 100% 100% 100%
SGS Morila 6,180 81% 96% 99% 99%
SGS Ouaga 1,420 78% 12% 8% 98%
SGS Ouaga Lab 81 80% 99% 100% 99%
SGS TM Lab 386 78% 95% 99% 99%
SGS TML 4,714 65% 86% 93% 95%
Unknown 812 55% 83% 93% 99%
Total 29,698 76% 89% 93% 99%

 

The few deviations in the standards were mainly due to failed standards and swapping of identification numbers. Deviations in the blanks are related with low level cross contamination in the laboratories and sample switches. Example charts showing deviations in standards (Standard G305-2) and blanks plotting as spikes are presented in Figures 12-1 and 12-2.

 

The TOP of the duplicates as expressed by a 50th %MAHD is between ±13.5% and ±17.6% for RC duplicates and between ±21.0% and ±31.6% for core duplicates for resource grade assays >0.1 g/t Au and is somewhat within acceptable industry limits for coarse gold deposit. Values for field duplicate core samples are on the high side and this is possibly a reflection of the decrease in sample homogeneity in moving from RC to core sample.

 

 
Page 79

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 12-1: Standard Control Plot for Standard G305-2 Results from SGS Kayes

 

(LINE GRAPH)

 

According to Heberlein (2013), measurable improvement was observed in the QA/QC procedures since his involvement in the Project.

 

The improvement has resulted in a measurable increase in the overall precision of the analytical results. Early precision estimates of field duplicate results (containing the total error of sampling, preparation and analysis) showed unacceptably high values for both core and RC duplicate samples. The initial analysis of duplicate results in 2011 determined precisions in the 80% to 90% range for core and 30% to 40% range for RC. Improvements to sampling and sample preparation procedures, particularly at the on-site laboratory (TML) have brought the drill core precision down to the 45% to 50 % range, which is reasonable for the nugget style of mineralization at Tasiast.

 

 
Page 80

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 12-2: Blank control plot for Blank results from SGS Kayes.

 

(LINE GRAPH)

 

Database

 

Red Back and TMLSA import and store drill related data in a Century database management system (CDMS) under the supervision of an experienced on-site database manager. All drill data has been imported into this system and has been re-validated. The drill data for resource estimation purposes was exported as comma delimited ASCII files. The CDMS was also used to generate monthly, quarterly and yearly QA/QC reports.

 

TMLSA carried out a 5% quality control analysis of the imported assay values in the resource database versus those from the certificate. The analysis included 53,469 samples from 235 holes and no major issues were identified. Eleven samples in the analysis had database assays values that did not correspond to the certificates and were

 

 
Page 81

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

from failed assay batches. Proper labelling of failed batches and re-analyzed batches has been recommended as part of ongoing quality control checks.

 

From May to July 2013, Kinross conducted an extensive data validation using a set procedure with guidance from CAE Mining (Holman and Castro, 2013). Geological data collected by the exploration team at Tasiast, including drilling and surface data, are stored in a commercially available Relational Database System called Fusion. The Fusion database was implemented at Tasiast by the previous owner of the property, Red Back, and Kinross migrated to a different system structure, but maintained the integrity of the existing data when the site was purchased in 2010.

 

In July 2013, SRK completed additional checks and comparisons to ensure the integrity of the export files (i.e., building and rebuilding queries, and exporting the same file twice to ensure all results carried over). No significant discrepancies were observed (Chartier, 2013).

 

Data Validation

 

Data validation ensures that accurate data are used for preparation of the resource estimate. An initial analysis of the data extracted revealed that the majority of the data needed extra validation and verification. The major problem found was in the QA/QC status of many historical holes that were showing a “failed” status.

 

A total of 1,363 batches had a failed status. Those batches were reviewed by the Tasiast Exploration managers. The batches were grouped by laboratory, and their QA/QC charts were printed or regenerated to aid in the analysis done by the QP. From all the batches reviewed, the status of 58.2% of the batches could be changed from “failed” to “QP-Accepted”. In the majority of the cases, the failures were due to the definition of the standards in the database. By default, a batch would fail if it had at least one control sample with a result that was more than two standard deviations; however, Kinross uses three standard deviations instead of two for a single sample. Furthermore, 38% of the batches reviewed needed more review because the QA/QC team might have mistakenly switched the definition of the samples (i.e., a sample was defined as a standard when it should have been defined as a blank, or similar issues).

 

Other validation performed on the data at Tasiast included:

 

1.Collar coordinates, by comparing the data in the database with the data obtained by the surveyor.

 

2.Downhole survey, by plotting the holes in 3D software and checking for any anomalies in the deviations of the holes. Many different instruments for measuring hole deviation in downhole surveying were used at Tasiast. So a

 

 
Page 82

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

ranking of instrument was implemented, giving priority to the instrument with better precision, when multiple instruments were used to survey the same hole. Instruments giving the more accurate reading preceded all other surveys.

 

3.Lithology, alteration, mineralization, by comparing the data in the database with the data captured in the logs and correcting a few cases of gaps and/or overlaps.

 

4.Assays, by comparing 5% of the results in the database to the results in the original certificates provided by the laboratories.

 

5.The validation process was completed by importing the data into Micromine (mining software) to visually check the validity of the data and to generate a report.

 

Twin Holes

 

In 2010 and 2011 TMLSA also twinned three RC holes from the Greenschist zone. In 2010 two twin holes were completed on the lower portion of the Greenschist zone to test for due diligence and variability between RC and core drilling. Results from the work returned a strong to acceptable correlation between mineralized intervals in the RC and core holes. The purpose of the 2011 hole that drilled shallow in the Greenschist zone is to improve understanding of any potential sampling differences between RC and core material. Geological logs between the core and RC drilled in the shallow portion of the zone retuned similar data with lithological units within expectations.

 

 
Page 83

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

12.3Comment on Data Verification

 

The process of data verification for the Project has been performed by TMLSA, Red Back, and personnel of precursor companies, and external consultancies contracted by those companies.

 

The QP has reviewed the reports and is of the opinion that the data verification programs undertaken on the data collected from the Project adequately support the geological interpretations, the analytical and database quality, and therefore support the use of the data in mineral resource and mineral reserve estimation.

 

Data used to support mineral resource and mineral reserve estimates have been subjected to validation, using built-in software program triggers that automatically check data for a range of data entry errors. Verification checks on surveys, collar coordinates, lithology, and assay data have also been conducted. The checks are appropriate, and consistent with industry standards.

 

Ongoing sample preparation and analytical work is recommended to obtain more acceptable precision from the duplicate samples.

 

 
Page 84

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

13.mineral processing and metallurgical testing

 

13.1Mineralogy

 

The Tasiast mineralization is free-milling and amenable to gold extraction by simple cyanide leaching. The existing mill has been operating since 2008 initially treating oxide banded iron mineralization (BIM) hosted ore yielding a typical gold recovery of 93%. Gold recovery from fresh ore, which forms an increasing portion of the mill feed since 2010, varies between 91% and 93%. A proportion of the gold is coarse and responds well to gravity concentration. Gold mineralization is associated with structurally controlled faults and shears, quartz-veining and silica-flooding. Gold grains observed in the exploration core holes are seen in isolated grains in quartz veins and are closely associated with pyrrhotite. The mineralization has relatively low levels of sulphides approximately 1% to 5% S, predominantly represented by pyrrhotite and to lesser extents pyrite, arsenopyrite, and chalcopyrite. Other metal contents are low such as silver approximately 1 ppm to 2 ppm, copper approximately 100 ppm, arsenic approximately 10 ppm and very low levels of mercury, less than 0.3 ppm Hg.

 

13.2Metallurgical Test Work

 

The bulk of the metallurgical test work has been done to evaluate the optimum process for the West Branch ore which has become the major source to the processing plant. Major metallurgical sampling campaigns were conducted on the West branch mineralized zone and test work to optimize cyanide addition rate and grinding tests were completed.

 

Evaluation of West Branch Ore Processing

 

Four major metallurgical sampling campaigns were conducted on the West Branch mineralized zone as follows:

 

·Campaign 1: AMMTEC Pty. Ltd. (AMMTEC)

 

·Campaign 2: SGS Canada Inc. (SGS)

 

·Campaign 3: SGS, additional boreholes to test for variability

 

·Campaign 4: KHD Humboldt Wedag (KDH) and JKTech Pty. Ltd. (JKTech), high pressure grinding roll (HPGR) and comminution tests

 

A program of waste rock sampling and characterization was also undertaken with core samples selected to represent all rock lithologies and depths.

 

 
Page 85

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Test Work Program

 

Test work was conducted by multiple laboratories and the results from the different laboratories were comparable.

 

The information generated in the test work programs was sufficient for:

 

·Preparation of ore characterization

 

·Process selection

 

·Process Flowsheet development

 

·Production scheduling

 

·Expenditure estimates

 

Summary of Comminution Characteristics

 

The comminution characteristics of West Branch samples Work was carried out by Ammtec, SGS and JKTech to:

 

·Assess the variation in comminution parameters for the deeper deposits.

 

·Confirm grinding energy requirements for the deeper ore.

 

All of the samples were checked for their correct lithologies and split into separate lithology tables for analysis. The mine plan by lithology is shown in Table 13-1 and comminution parameters obtained from laboratory testwork are in Table 13-2.

 

Table 13-1: Mine Plan by Lithology

 

  Year 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 LOM
Oxides GST_ox - - 0.08 - - - - - - - - - - - - 0.00
BIM HW_ox - - 0.26 - 0.36 - - - - - - 0.49 - - - 0.08
BIM FW_ox - - - - - - - - - - - 0.01 - - - 0.00
FVC_ox - - 2.06 - - - - - - - - 1.56 - - - 0.20
SVC_ox - - - - 0.02 - - - - - - 0.02 - - - 0.00

Fresh

Rock

 

GST_fr 62.56 97.59 74.75 56.78 47.94 80.95 70.63 51.35 61.46 93.22 82.06 44.02 34.19 34.19 34.19 60.08
BIM HW_fr - - 11.28 12.25 1.38 5.73 16.02 24.88 14.65 1.48 1.59 7.34 12.28 12.28 12.28 9.62
BIM FW fr 10.89 - - 1.14 0.53 - - 0.15 0.17 - 0.18 0.84 1.40 1.40 1.40 0.73
FVC_fr 5.45 0.77 7.28 7.89 8.96 2.03 1.61 6.43 3.94 2.21 3.21 9.02 14.02 14.02 14.02 6.81
SVC_fr 20.32 0.06 3.96 21.36 30.50 11.08 11.01 11.06 13.15 2.37 4.76 18.28 25.02 25.02 25.02 15.34
Dike_fr 0.78 1.59 0.32 0.57 0.47 0.21 0.73 0.86 0.87 0.72 1.98 1.19 1.58 1.58 1.58 1.01
Existing Stockpiles   - - - - 9.8 - - 5.3 5.8 - 6.2 17.2 11.5 11.5 11.5
Total Milled   100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

 

 
Page 86

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 13-2: Comminution Characteristics by Lithology

 

  Life of Mine Comminution Characteristics1 - 75th Percentile - 30 kt/d
  Lithology SG ta A x b A b DWI CWI RWI BWI Ai

West Branch + Stockpiles

 

 

 

WB-fBIMFrW 3.24 0.29 35.3 65.3 0.50 9.2 14.6 19.2 13.7 0.464
WB-FVC FrW 2.68 0.26 26.5 83.5 0.27 10.2 15.9 25.3 17.1 0.713
WB-GST FrW 2.90 0.25 28.0 68.3 0.32 10.2 17.7 17.9 14.0 0.398
WB-hBIMFrW 3.28 0.30 37.8 63.2 0.56 8.8 14.6 19.2 14.1 0.550
WB-SVC FrW 2.85 0.31 33.0 63.1 0.47 8.6 16.8 19.2 14.4 0.373
Piment + Stockpiles PM-fBIMFrP 3.24 0.29 35.3 65.3 0.50 9.2 14.6 19.2 13.7 0.464
PM-fBIMOxP 3.28 0.28 34.4 64.4 0.47 9.4 14.6 19.2 13.5 0.422
PM-FVC FrP 2.68 0.26 26.5 83.5 0.27 10.2 15.9 25.3 17.1 0.713
PIM SVC 2.99 0.33 33.5 62.1 0.54 7.8 14.6 19.5 15.5 0.265
PM-hBIMFrP 3.31 0.28 33.4 63.4 0.45 9.6 14.6 19.2 13.3 0.379
PM-SVC FrP 2.85 0.31 33.0 63.1 0.47 8.6 16.8 19.2 14.4 0.373
1.A, b and ta are parameters in the JKTech Drop Weight Test model (JKTech, undated). Acronyms for the other parameters in this table are listed in Section 2.5 List of Abbreviations.

 

Metallurgical Testing

 

Metallurgical Test Work Parameters

 

Extensive metallurgical testing was completed on West Branch samples, twinned hole samples and deeper level variability samples. In general, test work indicated that the ore was amenable to gravity recovery and cyanide leaching, resulting in selection of a flow sheet similar to that of the existing plant. Some of the key parameters that resulted from the test work are:

 

·Grind size: 90 µm

 

·Gravity recovery: 30% to 50%

 

·Leach retention: 24 hours

 

·Ore is not preg-robbing

 

·Leach environment: seawater

 

·Cyanide consumption: 0.47 kg/t

 

Cyanide Concentrations and Grinding Test Work

 

The cyanide addition rate has been optimized to a low addition rate. Test work results indicate that cyanide concentrations as low as 0.5 g/L, corresponding to a cyanide addition rate of 0.6 kg/t, still provide adequate overall gold extraction after 24 hours, as shown in Figure 13-1.

 

 
Page 87

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The grinding test work results show that gold extraction increases with a finer grind size. Gold dissolution kinetics were enhanced at the finer 80% passing (P80) grind sizes of 90 µm and 75 µm. At the selected grind of 90 µm, test work indicates that some dissolution still takes place after 24 hours of leach. However, the plant processing circuit will include grinding in process water containing cyanide recycled from the tailings thickener. Also, in the operating plant the coarser gold reports to the cyclone underflow and will be recovered by gravity, allowing smaller particles to overflow. Since this cannot be accurately simulated in a laboratory, 24 hours is concluded to be a suitable leach time. In the operating plant, the balance between finer grind (power cost) and gold recovery will be optimized.

 

Figure 13-1: Gold Recovery as a Function of Grind and Leach Retention

 

(LINE GRAPH) 

 

Summary of Tests and Recoveries

 

A compilation of all the relevant tests done, limited to those samples within the currently defined resource, produced the recoveries shown in Figure 13-2.

 

 
Page 88

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 13-2: Gold Grade vs. Recovery Relationship

 

(LINE GRAPH)

 

The figure shows that all of the selected samples leached well, that oxygen enhancement improved leach rate, and that recoveries are between 87% and 93% at a grade of 2 g/t. The recoveries are predominantly above 86%, with four exceptions that, from a metallurgical perspective, gives high confidence that all the sampled parts of the orebody are amenable to gravity and cyanidation. The trend line indicates a relationship between head grade and gold recovery, with higher recoveries achieved at higher gold head grades as expected. The mathematical relationship developed was used to estimate recovery based on the ore grade obtained from the mine plan.

 

Summary of Thickening Characteristics

 

AMMTEC performed flocculant screening tests on ground composite samples of West Branch ore using seawater obtained near Perth. Magnafloc MF336 flocculant was selected for subsequent settling tests to optimize flocculant consumption and develop thickener sizing criteria.

 

Thickening characteristics of deeper level variability samples were determined through Outotec test work in 2010, FLSmidth test work in 2011, SGS Lakefield test work in 2013

 

 
Page 89

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

and FLSmidth test work in 2013. Outotec investigated the dynamic settling characteristics and determined the thickener sizing criteria. In 2011, FLSmidth conducted sedimentation and rheology testing. SGS conducted dynamic settling tests on a number of composite samples that had been prepared for leaching test work in 2012 and 2013. Based on all the current test work a unit rate of 0.45 m2/t/d was selected for design.

 

Acid Mine Drainage Characteristics of West Branch Samples

 

Acid rock drainage (ARD) testing was completed on leach residue generated from the GST samples in the AMMTEC 2011 follow-up test work program to simulate plant tailings. Results indicated that the leach residues do not have potential acid generating characteristics, but have significant acid consuming capacity (likely due to the carbonate content of each ore composite).

 

In 2011, a waste rock material characterization program was conducted by URS Scott Wilson and supported by Kinross Tasiast and SRK Consulting. During the study, 154 samples were collected from exploration drilling core of different lithologies to assess the ARD potential. Study results showed that waste rock typically exhibits a significant residual neutralization potential for all the lithologies investigated.

 

The study results, coupled with the favorable arid climate, lack of surface water and very limited groundwater (no viable groundwater aquifer exists) and a Materials Management Plan (as outlined in Section 14.2 under “Acid Rock Drainage Potential” and Section 16 under “Waste Dumps”) indicate low potential for ARD or metal leaching to develop.

 

 
Page 90

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

14.mineral resource estimate

 

The Mineral Resource statement for Tasiast comprises estimates for West Branch, Piment, Prolongation and satellite deposits (Tamaya, C68W, C67 and Fennec).

 

The Mineral Resource is stated using variable cut off grades and the derived Lerchs-Grossman pit shells, which are dependent upon the ore type and distance from the mill. The effective date of this Mineral Resource is December 31, 2015

 

The main components of the stated Mineral Resources are West Branch (WB), and Piment and Prolongation (PP), which is where all open pit mining has taken place to date. These models remain unchanged from the 2013 Feasibility Study (FS). The satellite deposits do not provide material contributions to the overall resources, and the associated datasets and block models are therefore not discussed in detail in this report. Unless otherwise mentioned, all discussions in this section pertain to West Branch, Piment and Prolongation only.

 

Figure 14-1 illustrates the locations of the satellite deposits relative to West Branch, Piment and Prolongation.

 

14.1Database

 

The database for the West Branch, Piment and Prolongation models contained 4,857 drill holes, of which 93% were RC holes and 7% were diamond drill holes. A total of 4,343 holes (89.4%) in the database provided were used for grade estimation (Table 14-1). The previous resource estimate contained 4,038 holes, so an additional 819 additional holes were available for the models discussed in this report.

 

The holes (or assay values) that were not used in the models were primarily excluded due to QA/QC failure, incomplete holes or because they were outside the interpreted mineralized domains.

 

Table 14-1: Summary of Drill Hole Database

 

Area No. of Drill
Holes
No. of
Overlap
Drill
Holes*
No. of
Assay
Records
No. of
Survey
Records
Total Depth
(m)
West Branch 2,481 123 493,327 60,765 589,356.94
Piment+Prolongation 2,653 154 304,075 27,488 351,165.82

* to avoid edge effects from the resource estimation process, drill holes were exported from the database with a 200 m overlap on either side of the initial model boundary of 72,325N.0

 

 
Page 91

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-1: Tasiast Satellite Deposits

 

(MAP)

 

 
Page 92

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Data Import

 

Before conducting statistical analyses, all data were imported into GEMS software and a check on the database was performed to search for any obvious errors, such as negative values and overlapping sample intervals.

 

A visual check of the drilling against the most recent topographic surface revealed that the majority of collars are set to the surface. However, some drill holes were noted above the topographic surface, and this was deemed to be a consequence of poor topographic resolution and the variable elevation arising from the mining operations.

 

14.2Wireframes

 

Four sets of wireframes were included in the West Branch, Piment and Prolongation models:

 

·Lithology

 

·Oxide

 

·Mineralized domains

 

·Acid rock drainage (ARD) potential

 

The mineralized domains were the basis for grade estimation, the lithological wireframes were used for density, and the oxide surfaces were used to assist with density assignment and to determine ore type for resource reporting.

 

Figure 14-2 and Figure 14-3 show section and plan views of WB and PP, from the GEMS models.

 

Wireframe Construction Methodology

 

Lithologies

 

Geological wireframes were generated based on sectional interpretations every 25 m. Table 14-2 summarizes the codes and provides a brief description of each lithology.

 

 
Page 93

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-2: Lithology codes

 

Lithcode Lithstring Description
10 Dike Mafic Dike
20 RSPRLT Saprolite and Talus (overburden)
30 GST Greenschist Zone
40 BIM Banded Iron and Magnetite Formation
50 FVC Felsite
60 SVC Epiclastic Unit

 

Mineralization

 

Mineralized domains were constructed using a 0.1 g/t Au threshold value of the logged vein mineralization. For the high-grade zone associated with the GST lithology of West Branch, a high-grade core was defined using a 2.0 g/t Au threshold value. Table 14-3 describes the mineralization domains based on threshold values and associated lithology.

 

Table 14-3: Mineralization Domains

 

Domcode Domstring Description
10 Dike Mafic Dike, Barren
110 Dom6_1 GST, >2 g/t Au
120 Dom6_2 GST, 0.1<Au<2 g/t
130 DOM2 BIM (FW), >0.1 g/t Au
140 DOM7 South portion of GST (oxide), >0.1 g/t Au
150 DOM3 SVC (FW), >0.1 g/t Au
160 DOM8 FVC, >0.1 g/t Au
170 DOM9 Mineralized portion of BIM (HW), >0.1 g/t Au
180 DOM5 FVC/SVC (mineralized zones not included in other domains), >0.1 g/t Au
210 WBEXTEAS SVC/FVC bridge between WB and PP, >0.1 g/t Au
220 WBEXTWES SVC/FVC bridge between WB and PP, >0.1 g/t Au
230 PSSMAIN East of WBEXTEAS/WBEXTWES, >0.1 g/t Au
240 PN Piment North, >0.1 g/t Au
250 PCMAIN Piment Central - Main Zone, >0.1 g/t Au
260 PCWEST Piment Central - West Zone, >0.1 g/t Au
270 PSNMAIN Piment Main extensions, >0.1 g/t Au
310 PRO2B Prolongation, >0.1 g/t Au
320 PRO2A Prolongation, >0.1 g/t Au
330 PRO1C Prolongation, >0.1 g/t Au
340 PRO1B Prolongation, >0.1 g/t Au
350 PRO1A Prolongation, >0.1 g/t Au

 

 
Page 94

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-2: West Branch Mineralization Plan and Section Views

 

(GRAPHIC)

 

 
Page 95

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-3: Piment Mineralization Plan and Section Views

 

(GRAPHIC)

 

 
Page 96

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Oxide

 

The oxide surfaces were created in 2011 from sectional interpretations every 25 m. The interpretation was based on the logged REDOX field. Metallurgical test work demonstrated that the upper transition is amenable to dump leaching, so the oxide surface is critical for ore categorization and mine planning. Table 14-4 summarizes the oxide codes that were used to code the OX variable in the block model.

 

Table 14-4: Oxide Codes

 

Oxide Code Oxide String Description
1 Oxide Oxide material
2 UT Upper transition
3 LT Lower transition
4 Fresh Fresh material

 

Acid Rock Drainage Potential

 

Although the ARD test work results showed there is overall low potential for ARD concerns to develop, results for a very limited lithology and tonnage showed Potential Acid Forming conditions. In taking a precautionary approach, a wireframe for the ARD potential material at West Branch was created based on the contact between the hanging wall BIM and FVC unit combined with the presence of sulphide (pyrrhotite and pyrite) reported in the exploration mineralization and relogging files. If the sulphide presence was not reported for holes that crossed the lithological contact, a buffer of up to 5 m into the contact was applied. No ARD was interpreted for Piment and Prolongation.

 

14.3Exploratory Data Analysis

 

Exploratory data analysis (EDA) is the application of various statistical tools to explain the characteristics of a data set. In this case, the objective is to understand the population distribution of the grade elements using tools such as histograms, descriptive statistics and probability plots.

 

Outlier Management and Capping Strategy

 

When dealing with skewed populations and outlier assay samples relative to the normal population distribution, it is common practice to restrict the influence of these high-grade assays through capping. The capping limits were chosen as a function of the continuity-discontinuity of the high-grade tail of the gold assays.

 

The analysis included a visual review of the probability plots, a statistical assessment of the 97% and 99.9% percentiles, and decile analysis using the Parrish method. A summary of the analysis and the recommended capping levels are included in Table 14-5 and Table 14-6. As a result, 501

 

 
Page 97

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

gold assays were capped. These values represent 0.13% of the entire sample population. Capping was applied because a visual review of the outliers did not identify a spatial constraint or sufficient drill density to constrain the overestimation of the outliers.

 

The capping was implemented by capping assay grades to the selected values before compositing.

 

 
Page 98

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-5: WB Au Capping Analysis

 

    Recommended Cap Summary Statistics, Au g/t   Probability Plot, Au g/t Decile Analysis
DomCode DomString Au g/t Count Count %Data  Mean Maximum  CV 97% 99.9%  Outlier Au g/t
10 DYKE 1.0 278 10,174 3.3 0.147 101.000 9.14 1.0 8.0 50.0  
110 DOM6_1 150.0 2 15,661 5.1 3.411 176.000 1.33 12.0 50.0 150.0 70.0
120 DOM6_2 60.0 3 32,018 10.4 0.857 175.000 2.45 4.5 25.0 60.0 60.0
130 DOM2 60.0 1 16,871 5.5 0.427 77.200 2.49 1.8 10.0 60.0 20.0
140 DOM7 10.0 9 7,458 2.4 0.540 52.700 2.28 2.8 12.0 42.0 40.0
150 DOM3 70.0 8 79,244 25.7 0.435 496.000 5.61 2.8 15.0 70.0 70.0
160 DOM8 45.0 6 56,123 18.2 0.227 81.900 5.02 1.3 15.0 45.0 40.0
170 DOM9 8.0 24 8,067 2.6 0.308 15.800 2.85 2.4 10.0 8.0 8.0
180 DOM5 70.0 6 63,951 20.7 0.133 129.000 10.85 0.6 15.0 70.0 70.0
210 WBEXTEAS 100.0 1 7,725 2.5 0.517 154.000 5.46 3.0 35.0 150.0 150.0
220 WBEXTWES 15.0 6 2,954 1.0 0.460 100.000 4.86 3.5 18.0 15.0 15.0
230 PSSMAIN 60.0 3 8,137 2.6 0.492 83.500 3.75 3.0 20.0 65.0 60.0
* GLOBAL   347 308,383   0.522 496.000 4.15 2.8 17.0 60.0 60.0

 

Table 14-6: PP Au Capping Analysis

 

    Recommended Cap Summary Statistics, Au g/t   Probability Plot, Au g/t Decile Analysis
DomCode DomString Au g/t Count Count %Data  Mean Maximum  CV 97% 99.9%  Outlier Au g/t
10 DYKE 1.0 16 5,698 6.5 0.021 7.700 7.21 0.1 3.0 10.0  
210 WBEXTEAS 100.0 1 5,431 6.2 0.501 154.000 5.88 3.0 35.0 150.0 150.0
220 WBEXTWES 15.0 3 1,551 1.8 0.438 18.900 3.11 4.0 15.0 17.0 15.0
230 PSSMAIN 60.0 6 19,885 22.6 0.733 88.900 3.13 4.5 30.0 60.0 60.0
240 PN 35.0 5 2,809 3.2 1.555 119.000 2.78 10.3 40.0 35.0 35.0
250 PCMAIN 35.0 64 25,165 28.6 1.219 118.000 3.03 8.0 50.0 35.0 35.0
260 PCWEST 35.0 29 13,520 15.3 0.663 166.000 5.09 5.0 45.0 35.0 35.0
270 PSNMAIN 20.0 16 9,234 10.5 0.714 83.300 3.15 5.0 25.0 20.0 20.0
310 PRO2B 18.0 6 645 0.7 0.548 28.200 4.12 5.5 28.0 18.0 20.0
320 PRO2A 9.0 2 524 0.6 0.278 21.100 4.27 3.0 21.0 9.0 9.0
330 PRO1C 35.0 3 1,276 1.4 1.275 49.300 3.02 11.0 40.0 35.0 35.0
340 PRO1B 10.0 1 315 0.4 0.264 20.300 4.92 1.5 20.0 20.0 20.0
350 PRO1A 50.0 2 2,072 2.4 1.014 57.000 3.04 7.5 50.0 50.0 50.0
* GLOBAL   154 88,125   0.857 166.000 3.58 2.5 25.0 65.0 65.0

 

 
Page 99

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Compositing and Descriptive Statistics (Capped and Uncapped)

 

Upon examination of the raw sample length statistics, a composite length of 2 m was chosen for the assay samples. Composites honoured the mineralized domain boundaries and were applied to the capped raw assays.

 

When compositing, assay values less than the detection limit were assigned a value half of the lower detection limit value, which depending on the laboratory, was commonly 0.003 g/t Au or 0.005 g/t Au.

 

Table 14-7 and Table 14-8 summarize statistics by mineralized domain for uncapped and capped gold composite grades in WB.

 

Table 14-7: WB Uncapped Gold Composite Grade Statistics by Domain

 

DomCode DomString Count Mean Grade
(g/t)
Standard Deviation Variance Coefficient of
Variation
10 DYKE 6667 0.152 0.951 0.904 6.252
110 DOM6_1 8594 3.381 3.493 12.200 1.033
120 DOM6_2 17567 0.876 1.548 2.397 1.767
130 DOM2 9428 0.434 1.053 1.108 2.423
140 DOM7 4171 0.533 0.932 0.868 1.750
150 DOM3 43902 0.435 1.533 2.351 3.523
160 DOM8 32142 0.228 0.891 0.795 3.903
170 DOM9 5029 0.309 0.676 0.457 2.185
180 DOM5 36858 0.133 1.232 1.519 9.261
210 WBEXTEAS 4329 0.516 1.984 3.934 3.848
220 WBEXTWES 1741 0.461 1.557 2.425 3.380
230 PSSMAIN 4522 0.492 1.291 1.666 2.625

 

Table 14-8: WB Capped Gold Composite Grade Statistics by Domain

 

DomCode DomString Count Mean Grade
(g/t)
Standard Deviation Variance Coefficient of
Variation
10 DYKE 6667 0.093 0.204 0.042 2.194
110 DOM6_1 8594 3.379 3.412 11.643 1.010
120 DOM6_2 17567 0.871 1.364 1.861 1.567
130 DOM2 9428 0.432 0.917 0.841 2.121
140 DOM7 4171 0.518 0.702 0.493 1.355
150 DOM3 43902 0.427 1.086 1.179 2.544
160 DOM8 32142 0.226 0.792 0.628 3.503
170 DOM9 5029 0.303 0.626 0.392 2.064
180 DOM5 36858 0.131 1.112 1.237 8.500
210 WBEXTEAS 4329 0.509 1.749 3.058 3.438
220 WBEXTWES 1741 0.429 0.999 0.998 2.332
230 PSSMAIN 4522 0.487 1.187 1.410 2.438

 

 
Page 100

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-9 and Table 14-10 summarize statistics by mineralized domain for uncapped and capped gold composite grades in PP.

 

Table 14-9: PP Uncapped Gold Composite Grade Statistics by Domain

 

DomCode DomString Count Mean
Grade (g/t)
Standard Deviation Variance Coefficient of Variation
10 DYKE 3735 0.025 0.121 0.015 4.843
210 WBEXTEAS 2997 0.531 2.120 4.492 3.994
220 WBEXTWES 916 0.481 1.093 1.194 2.274
230 PSSMAIN 11067 0.760 1.777 3.156 2.337
240 PN 1515 1.592 3.474 12.066 2.182
250 PCMAIN 14367 1.246 3.123 9.751 2.506
260 PCWEST 7082 0.668 2.532 6.410 3.790
270 PSNMAIN 5169 0.735 1.723 2.970 2.345
310 PRO2B 502 0.807 2.062 4.251 2.554
320 PRO2A 357 0.376 1.129 1.274 3.001
330 PRO1C 673 1.325 3.113 9.689 2.349
340 PRO1B 214 0.337 1.042 1.085 3.088
350 PRO1A 1346 1.272 2.679 7.179 2.106

 

Table 14-10: PP Capped Gold Composite Grade Statistics by Domain

 

DomCode DomString Count Mean
Grade (g/t)
Standard Deviation Variance Coefficient of Variation
10 DYKE 3735 0.022 0.065 0.004 2.977
210 WBEXTEAS 2997 0.521 1.801 3.243 3.458
220 WBEXTWES 916 0.477 1.070 1.145 2.243
230 PSSMAIN 11067 0.757 1.712 2.931 2.263
240 PN 1515 1.552 3.022 9.130 1.947
250 PCMAIN 14367 1.203 2.634 6.936 2.188
260 PCWEST 7082 0.629 1.985 3.941 3.154
270 PSNMAIN 5169 0.709 1.411 1.991 1.989
310 PRO2B 502 0.768 1.866 3.482 2.429
320 PRO2A 357 0.352 0.873 0.763 2.482
330 PRO1C 673 1.305 2.974 8.844 2.280
340 PRO1B 214 0.306 0.787 0.619 2.572
350 PRO1A 1346 1.268 2.640 6.969 2.082

 

 
Page 101

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Contact Profiles

 

Contact profiles were generated to confirm the grade interpolation limits along the domain contacts. Contact plots were generated between all domains. Contacts may be interpreted as:

 

·Soft (S): soft contacts show no significant grade differential at, or near, the contact

 

·Firm (F): firm contacts are present if the grade is transitional between two domains

 

·Hard (H): hard contacts exhibit a sharp grade differential at the domain contact

 

Table 14-11 summarizes the contact relationships for West Branch. The default contact relationship was assumed to be hard. At WB, soft and firm contacts were identified. Firm contacts were implemented during grade interpolation as soft contacts.

 

Table 14-11: Summary of Domain Contact Relationship, WB

 

    10 110 120 130 140 150 160 170 180 210 220 230
DYKE 10   H H H H H H H H H H H
DOM6_1 110 H   H H H H H H H H H H
DOM6_2 120 H H   H H H H H H H H H
DOM2 130 H H H   H S H H H H H H
DOM7 140 H H H H   F H H H H H H
DOM3 150 H H H S F   S H H H S H
DOM8 160 H H H H H S   F S F H H
DOM9 170 H H H H H H F   H H H S
DOM5 180 H H H H H H S     H F H
WBEXTEAS 210 H H H H H H F H H   H H
WBEXTWES 220 H H H H H S H H F H   H
PSSMAIN 230 H H H H H H H S H H H  

 

For PP, no soft boundaries were identified and only a single firm contact relationship was identified, as most of the domains were not in contact with adjoining domains. All contacts in PP were implemented as hard boundaries.

 

14.4Variography

 

Variogram models were developed using SAGE2001© software. Directional sample correlograms were calculated along horizontal azimuths of 0, 30, 60, 120, 150, 180, 210, 240, 270, 300 and 330 degrees. For each azimuth, sample correlograms were also calculated at dips of 30 degrees and 60 degrees, in addition to horizontally. Lastly, a

 

 
Page 102

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

correlogram was calculated in the vertical direction (-90 degrees). The model was fitted to reflect geological knowledge and grade continuity of the deposit.

 

All conventions follow those of the Cartesian coordinate system. For example, the Z axis will be vertical with values increasing upward, if the system of axes is oriented so that:

 

·The X axis runs east-west with values increasing to the east

 

·The Y axis runs north-south with values increasing to the north

 

A positive dip angle is measured upwards from the horizontal, whereas a negative dip angle is measured downwards from the horizontal.

 

The order and direction of the rotations around the three axes are given by the following (in each case the direction is given by the right-hand rule):

 

·The first rotation is around the Z axis.

 

·The second rotation is around the rotated Y axis.

 

·The third rotation is around the rotated Z axis.

 

Table 14-12 and Table 14-13 summarize the variogram results for the capped 2.0 m Au composites for WB and PP. All correlograms were spherical models consisting of a nugget and two structures.

 

 
Page 103

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-12: WB Gold Grade Correlogram Models

 

Domain Nugget Sill Rot. Z Rot. Y’ Rot. Z’ Range Z’ Range Y’ Range X’
10 0.450 0.524 4 -52 -3 7.0 135.8 21.6
0.026 -97 119 75 322.3 245.4 136.1
110 0.200 0.700 54 125 34 14.2 28.4 7.4
0.100 -57 -68 126 134.2 36.4 70.0
120 0.400 0.500 22 52 22 15.0 25.0 15.0
0.100 58 -49 -35 300.0 150.0 50.0
130 0.400 0.490 -21 -22 43 25.0 30.0 25.0
0.110 11 -41 92 250.0 50.0 250.0
140 0.400 0.402 -50 18 -1 4.8 35.2 35.5
0.198 -18 -47 22 583.8 424.4 34.1
150 0.350 0.554 -19 45 -9 6.1 17.7 33.9
0.096 -57 -69 31 516.9 408.8 54.4
160 0.350 0.600 9 55 -51 10.0 15.0 30.0
0.050 59 -56 -33 111.3 184.8 31.7
170 0.250 0.539 23 11 55 4.5 39.3 41.0
0.211 14 -40 -2 263.0 604.8 41.2
180 0.350 0.500 -2 -25 58 15.0 40.0 30.0
0.150 -71 99 123 250.0 60.0 50.0
210 0.500 0.350 -7 -78 -3 30.0 45.0 10.0
0.150 -32 126 66 250.0 35.0 45.0
220 0.200 0.650 -1 57 10 20.0 25.0 45.0
0.150 -62 -72 52 350.0 250.0 60.0
230 0.400 0.492 -1 46 37 6.5 21.4 32.4
0.108 3 -53 -3 141.5 247.0 64.2

 

 
Page 104

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-13: PP Gold Grade Correlogram Models

 

Domain Nugget Sill Rot. Z Rot. X’ Rot. Z’ Range Z’ Range X’ Range Y’
10 0.150 0.800 2 -50 0 15.0 25.0 20.0
0.050 4 -33 -3 150.0 250.0 70.0
210 0.500 0.465 -9 49 9 5.9 8.5 20.1
0.035 -12 -52 6 191.9 292.2 14.3
220 0.200 0.600 16 36 -41 10.0 20.0 60.0
0.200 -45 -49 33 250.0 150.0 40.0
230 0.250 0.578 -18 19 13 7.4 23.7 29.6
0.172 28 -43 -20 156.4 392.4 27.6
240 0.350 0.396 -14 48 94 3.2 24.3 16.2
0.254 13 73 -3 97.8 73.9 7.3
250 0.150 0.689 4 -18 -59 8.5 18.5 11.1
0.161 63 -23 -43 70.2 330.2 26.1
260 0.400 0.500 5 17 56 7.5 8.4 36.7
0.100 -83 93 19 154.6 26.8 40.0
270 0.350 0.475 18 11 31 4.5 21.9 28.0
0.175 36 -49 -24 83.8 177.9 27.8

310

320

0.250 0.600 34 49 32 10.0 10.0 15.0
0.150 50 -96 71 125.0 200.0 100.0

330

340

350

0.300 0.570 15 -14 -15 10.0 15.0 25.0

0.130

 

22 -26 -12 225.0 180.0 40.0

 

14.5Grade Interpolation

 

The interpolation methods used for populating the WB and PP block models were Inverse Distance Squared (ID2), Ordinary Kriging (OK) and Nearest Neighbour (NN).

 

For the ID2 and OK interpolation methods, two passes were used. For the first pass, a minimum of seven composites and a maximum of 18 composites were used and a constraint of three composites per drill hole was imposed. This had the combined effect of estimating all blocks with a minimum of two drill holes. For the second pass, the same composite selection parameters were maintained, with the exception of using a minimum of four composites.

 

For the NN estimate, one pass was used, which reflected the second pass interpolation parameters use for ID2.

 

14.6Bulk Density Modelling

 

A total of 26,940 density records were used to assign values in the models. Rock type (or lithology) and state of oxidation were used to determine the appropriate density value (Table 14-14). These values were assigned to the block model based on these two

 

 
Page 105

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

values. If no data were available, the 2011 model density values were still used in the 2013 model.

 

Using specific gravity measurements taken on the various rock types, an average density value was calculated for each logged rock type and oxide type. These values were then assigned to the domains in the block model using simple manipulation scripts in Gemcom.

 

The differences in density values resulted from a change in geological interpretation based on relogging and updated lithological wireframes.

 

 
Page 106

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-14: Density Values Assigned to Models - g/cm3

 

      FS2013 Calculations 2011 MIK Calculations FS2013 Values Used

PP

Density

{value(count)}

WB

Density

{value(count)}

             
Code Lith Oxide PP
Density
WB
Density
PP
Density
{value(count)}
WB
Density
{value(count)}
10 DYKE oxide  -  - 2.79 2.79 2.79 2.79
10   upper transition  -  - 2.84 2.84 2.84 2.84
    lower transition  - 2.67 (2) 2.91 2.91 2.89 (77) 2.89 (77)
    fresh 2.89 (77) 2.96 (394) 2.97 2.97 2.89 (77) 2.96 (394)
20 RSPRLT oxide  - n/a n/a n/a 2.54 (70) n/a
20   upper transition  - n/a n/a n/a 2.72 (49) n/a
    lower transition  - n/a n/a n/a 2.83 (73) n/a
    fresh  - n/a n/a n/a n/a n/a
30 GST oxide n/a 2.64 (1) 2.3 2.3 n/a n/a
30   upper transition n/a 2.87 (5) 2.59 2.59 n/a n/a
    lower transition n/a 2.92 (7) 2.74 2.74 n/a n/a
    fresh n/a 2.87 (3,105) 2.85 2.85 n/a 2.87 (3,105)
40 BIMHW oxide 2.37 (26) 2.82 (47) 2.78 2.66 2.37 (26) 2.82 (47)
40   upper transition 2.88 (12) 2.86 (24) 2.9 2.96 2.88 (12) 2.86 (24)
    lower transition 2.88 (11) 2.94 (45) 2.91 3.14 2.88 (11) 2.94 (45)
    fresh 3.26 (969) 3.20 (5,964) 3.07 3.26 3.26 (969) 3.20 (5,964)
45 BIMFW oxide  -  - 2.52 2.52 2.52 2.52
45   upper transition  -  - 2.77 2.77 2.77 2.77
    lower transition 2.79 (3)  - 2.85 2.85 2.85 2.85
    fresh 3.02 (70) 3.12 (311) 3.04 3.04 3.02 (70) 3.12 (311)
50 FVC oxide  - 2.61 (3) 2.19 2.19 2.19 2.19
50   upper transition 2.7 (3) 2.57 (3) 2.57 2.57 2.57 2.57
    lower transition 2.64 (10) 2.77 (5) 2.64 2.64 2.64 (10) 2.64
    fresh 2.72 (765) 2.69 (4,866) 2.68 2.68 2.72 (765) 2.69 (4,866)
60 SVC oxide 2.54 (70) 2.41 (90) 2.45 2.45 2.54 (70) 2.41 (90)
60   upper transition 2.72 (49) 2.61 (56) 2.57 2.57 2.72 (49) 2.61 (56)
    lower transition 2.83 (73) 2.70 (81) 2.69 2.69 2.81 2.70 (81)
    fresh 2.81 (1,686) 2.77 (5,675) 2.76 2.76 2.81 (1686) 2.77 (5,675)

 

 
Page 107

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

14.7Mineral Resource Classification

 

The Mineral Resources are classified under the categories of Measured, Indicated and Inferred, in accordance with CIM Definition Standards (CIM, 2014). Classification of the resources reflects confidence of grade continuity, as a function of many factors, including primarily assay data quality, QA/QC procedures, quality of density data, and sample spacing relative to geological and geostatistical observations regarding the continuity of mineralization.

 

The resource model blocks were classified into Measured, Indicated and Inferred categories, based on the level of confidence in the grade estimate for each block. Measured resources were defined based on a nominal drill spacing of 25 m. Indicated resources were categorized based on a nominal drill spacing of 50 m, and the remaining interpolated blocks within 120 m of the nearest composite were classified as inferred resources. Blocks estimated using data beyond 120 m were not classified as mineral resources. A minimum of two drill holes were used to estimate all blocks. The selection of the nominal spacing was based on a combination of the review of the variogram structures (which typically demonstrated short range for the first structure within 10 m to 30 m), prior resource classification and the qualified person’s experience.

  

Figure 14-4 illustrates the resource classification code (RCLASS) for 95 m elevation in the WB model. Figure 14-5 illustrates RCLASS for the same elevation in PP. The pit outline is shown for reference.

 

 
Page 108

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-4: WB Resource Classification, 95 m Elevation

 

(LINE GRAPHIC)

 

Figure 14-5: PP Resource Classification, 95 m Elevation

 

(LINE GRAPHIC)

 

 
Page 109

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

14.8Block Model Validation

 

The Tasiast models for WB and PP were validated by:

 

1.Comparison of the global mean block grades for ID2, OK, NN and composites

 

2.Visual comparison of colour-coded block model grades with composites on section and in plan

 

3.Swath plots along the row, columns and levels of the block model

 

4.Comparison of OK and NN block grades with Herco distribution

 

Interpolation Validation—Global Comparison

 

The block model estimates were verified for global bias by comparing the average Au grade (with no cutoff value) for Measured, Indicated and Inferred resource category blocks from the model (OK) using ID2 and NN estimates. The NN estimator produces a theoretical unbiased estimate of the average value when no cutoff grade is imposed, and is a good method for checking the performance of different estimation methods. The results show no evidence of bias in the estimate (Table 14-15).

 

Table 14-15: Comparison of Mean Au Grade for OK, ID2 and NN Interpolations

 

AREA AUNN
(g/t)
AUCNN
(g/t)
AUID
(g/t)
AUCID
(g/t)
AUK
(g/t)
AUCK
(g/t)
WB 0.393 0.380 0.390 0.380 0.390 0.379
PP 0.565 0.550 0.604 0.587 0.610 0.592

 

Table 14-16 and Table 14-17 summarize the composite versus block model statistics for WB and PP.

 

Table 14-16: Comparison of WB Statistics for Capped Composites and Model Grades

 

Statistic Composite
AU_CAP
Block Model AUCK
Count 134,471 5,954,679
Mean (g/t) 0.518 0.379
Standard deviation 1.46 0.72
Sample variance 2.14 0.51
Coefficient of variance 2.82 1.89

 

 
Page 110

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-17: Comparison of PP Statistics for Capped Composites and Model Grades

 

Statistic Composite
AU_CAP
Block Model AUCK
Count 49,940 1,091,644
Mean (g/t) 0.839 0.592
Standard deviation 2.11 0.86
Sample variance 4.44 0.73
Coefficient of variance 2.51 1.44

 

Sectional Validation—Blocks versus Composites

 

Interpolated block grades, resource classification, geological interpretation outlines and drill hole composite intersections were verified on screen in plan and in vertical section. Based on visual inspection, the block model grades appear to honour the data well. The estimated grades exhibit a satisfactory consistency with the drill hole composites.

 

Swath Plots

 

Swath plots are commonly used as a block model validation tool as they provide a graphical comparison of key modeling outputs such as the number of composites, composite grades, raw grades, and block grades for various interpolation methods.

 

Swath plots were produced for the block model(s) vs the composites by domain and by deposit (e.g., WB, PP). A synopsis of the swath plots is presented in the following figures (Figure 14-6 to 14-9).

 

 
Page 111

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-6: 3D View of DOM6_1 and Swath Plot by Easting

 

(Graphic) 

 

 

(LINE GRAPHIC)

 

 
Page 112

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-7: DOM6_1 Swath Plots by Northing and Elevation

 

(Graphic) 

 

(LINE GRAPHIC)

 

 
Page 113

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-8: 3D View of DOM6_2 and Swath Plot by Easting

 

(Graphic) 

 

(Graphic) 

 

 
Page 114

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-9: DOM6_2 Swath Plots by Northing and Elevation

 

(Graphic)

 

 

(Graphic) 

 

 
Page 115

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Hermitian Correction

 

The relative degree of smoothing in the block model estimates can be evaluated using the Discrete Gaussian or Hermitian Polynomial Change of Support method (Journel and Huijbregts, 1978).

 

With this method, the distribution of the hypothetical block grades can be directly compared to the estimated (OK) model by using pseudograde/tonnage curves. Adjustments are made to the block model interpolation parameters until an acceptable match is made with the Hermitian Correction (Herco) distribution.

 

In general, the estimated model should be slightly higher in tonnage and slightly lower in grade, compared to the Herco distribution at the projected cut-off grade. These differences account for selectivity and other potential ore-handling issues that commonly occur during mining.

 

The Herco distribution is derived from the declustered composite grades that have been adjusted to account for the change in support from smaller drill-hole composite samples to the large blocks in the model. The transformation results in a less skewed distribution, but with the same mean as the original declustered samples.

 

Generally, the OK models are smooth relative to the Herco distribution. The key exception for WB is DOM6_1, which is the high-grade gold zone.

 

The resource cut-off grades for DL material were 0.37 g/t Au for Piment and Prolongation and 0.43 g/t Au for West Branch. For CIL material, the cut-off grade was 0.55 g/t Au for oxide and 0.56 g/t Au for fresh. As shown in Figure 14-10, an acceptable amount of smoothing was incorporated in the model at the cut-off grades.

 

 
Page 116

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 14-10: WB DOM6_1 Herco Grade-Tonnage Curves

 

(LINE GRAPH)

 

(LINE GRAPH)

 

 
Page 117

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

14.9Mineral Resource Statement

 

The Tasiast Mineral Resource statement comprises Measured, Indicated and Inferred resources. The Mineral Resources are stated in accordance with the definitions in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (NI 43-101). Mineral resources have an effective date of December 31, 2015. The Mineral Resource block model was prepared by Mr. Tim Maunula, P.Geo., Principal Geologist with T. Maunula & Associates Consulting Inc.

 

Mineral Resources are stated at variable cut-off grades, dependent on the metallurgical type, mining operating cost and variable process recoveries. The cut off grades were determined using a gold price of $1,400/oz.

 

Basis for Mineral Resource Statement

 

Estimation of the Tasiast Mineral Resources was based on a combination of development alternatives that assumed two potential processing options. These included CIL milling of fresh and high grade oxide resource and dump leaching for lower grade oxide material. The various processing recoveries and associated operating conditions were used to generate an optimized pit shell using a Lerchs-Grossman (LG) optimization algorithm.

 

Mineral Resource Statement

 

The Mineral Resources were reported below the projected December 31, 2015 mined surface or topographic surface and are constrained using the Lerchs-Grossman 30 kt/d pit shells designed by Kinross Technical Services. Kinross cautions that Mineral Resources that are not Mineral Reserves are not required to demonstrate economic viability. Table 14-18 and Table 14-19 show the classified Mineral Resources inclusive of Mineral Reserves. The resources within the current mining operations for WB and PP constitute 94.3% of the total resource. The remaining 5.7% of the resource are reported for the satellite projects Tamaya, Fennec, C67 and C68W.

 

Mineral Resources exclusive of Mineral Reserves are shown in Table 14-21.

 

 
Page 118

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-18: Mineral Resource Statement by Area Inclusive of Reserves

 

Area Class Tonnes Au g/t Au oz
West Branch Measured 22,894,434 1.34 985,200
  Indicated 137,609,068 1.89 8,340,279
  M&I 160,503,501 1.81 9,325,480
  Inferred 4,442,634 2.08 297,110
Piment Measured 7,845,013 1.51 380,811
  Indicated 16,529,688 1.42 753,476
  M&I 24,374,701 1.45 1,134,287
  Inferred 30,868 1.82 1,808
Prolongation Measured 0 0.00 0
  Indicated 1,908,479 1.42 87,367
  M&I 1,908,479 1.42 87,367
  Inferred 225,733 0.93 6,739
Tamaya Measured 0 0.00 0
  Indicated 7,426,796 1.32 314,551
  M&I 7,426,796 1.32 314,551
  Inferred 48,691 0.91 1,428
C67, C68W, Fennec Measured 0 0.00 0
  Indicated 4,474,786 2.07 297,414
  M&I 4,474,786 2.07 297,414
  Inferred 849,533 1.43 39,135
Total Measured 30,739,447 1.38 1,366,011
  Indicated 167,948,817 1.81 9,793,088
  M&I 198,688,264 1.75 11,159,099
  Inferred 5,597,460 1.92 346,221

 

1.Mineral Resources that are not Mineral Reserves are not required to demonstrate economic viability.

2.Mineral Resources are reported below the 31 December 2015 mined surface and are constrained using an optimized Lerchs-Grossman pit shell.

3.Mineral Resources are reported to a cut-off grade as listed in Table 14-20 based on a gold price of US$1,400/oz.

4.The above mineral resource estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

 
Page 119

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-19: Mineral Resource Statement by Material Type Inclusive of Reserves

 

Material Type Class Tonnes Au g/t Au oz
Dump Leach Measured 86,715 0.49 1,358
  Indicated 1,321,149 0.48 20,548
  M&I 1,407,863 0.48 21,907
  Inferred 70,917 0.49 1,121
CIL Measured 30,652,732 1.38 1,364,653
  Indicated 166,627,669 1.82 9,772,540
  M&I 197,280,401 1.76 11,137,193
  Inferred 5,526,544 1.94 345,100
Total Measured 30,739,447 1.38 1,366,011
  Indicated 167,948,817 1.81 9,793,088
  M&I 198,688,264 1.75 11,159,099
  Inferred 5,597,460 1.92 346,221

 

1.Mineral Resources that are not Mineral Reserves are not required to demonstrate economic viability.

2.Mineral Resources are reported below the 31 December 2015 mined surface and are constrained using an optimized Lerchs-Grossman pit shell.

3.Mineral Resources are reported to a cut-off grade as listed in Table 14-20 based on a gold price of US$1,400/oz.

4.The above mineral resource estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

Table 14-20: Cut-Off Grades (Au g/t)

 

Area Material CIL DL
C67 Fresh 0.57  
C68W

Oxide

Transition

Fresh

0.57

0.57

0.57

0.41
Fennec

Oxide

Transition

Fresh

0.58

0.58

0.58

0.43
Piment

Oxide

Fresh

0.55

0.56

0.37
Tamaya

Oxide

Transition

Fresh

0.60

0.60

0.60

0.49
West Branch

Oxide

Fresh

0.55

0.56

0.43

 

 
Page 120

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 14-21: 2015 Tasiast Mineral Resource Statement Exclusive of Reserves

 

Classification

Tonnes

(000’s)

Grade

(Au g/t)

Ounces

(000’s)

Measured 8,611 0.83 230
Indicated 66,236 1.40 2,980
Subtotal M&I 74,847 1.33 3,210
Resource Stockpile 293 0.63 6
       
Inferred 5,596 1.92 346

 

1.Mineral Resources that are not Mineral Reserves are not required to demonstrate economic viability.

2.Mineral Resources are reported below the 31 December 2015 mined surface and are constrained using an optimized Lerchs-Grossman pit shell.

3.Mineral Resources are reported to cut-off grades ranging from 0.55 g/t to 0.60 g/t Au for CIL and from 0.37 g/t to 0.49 g/t Au for dump leach based on a gold price of US$1,400/oz.

4.Stockpile balance above 0.7 g/t cut-off grade is considered as reserve, while below 0.7 g/t is considered as resource. Measured Resource includes the Resource Stockpile.

5.The above mineral resource estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

14.10Comment on Mineral Resources

 

The QP is of the opinion that the Mineral Resources for the Project, which have been estimated using core and reverse circulation drill data, have been prepared using industry best practices and conforms to the requirements of CIM Definition Standards. The Mineral Resources are adequate to support mine expansion studies.

 

Mineral Resources that are not Mineral Reserves do not have to demonstrate economic viability.

 

 
Page 121

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

15.mineral reserve estimate

 

The Mineral Reserve for the Tasiast open pit mine was estimated using a diluted mine planning model derived from the FS2013 resource models for West Branch (WB) and Piment (PM), as discussed in Section 14. These resource block models were diluted by applying a methodology that mimics the dilution and ore loss that is likely to occur during mining operations by re-blocking at cut-offs that match the grade control cut-off grades.

 

The 30 kt/d pre-feasibility reserves, effective December 31, 2015, were estimated using the diluted mine planning block model and applying a gold price of $1200/oz, a CIL processing cost of $16.04/t, a $10.90/t processing cost for dump leach ore, and a base mining cost of $2.00/t, excluding incremental haulage. The reserve estimate includes material contained within the final pit design that can be extracted and processed economically. Reported reserves are solely based on the Measured and Indicated mineral resource classifications which correspond to Proven and Probable reserves classifications shown in Table 15-1.

 

Table 15-1: Reserve Estimate Effective December 31, 2015

 

Classification

Tonnes 

(000’s)

Grade 

(Au g/t)

Ounces  

(000’s)

Proven 30,467 1.44 1,406
Probable 101,711 2.08 6,813
TOTAL 132,178 1.93 8,219
Reserve Stockpile 8,045 1.02 264

  

1.Mineral Reserves are reported to a cut-off grade of 0.7 g/t Au for CIL and 0.40 g/t Au for dump leach based on a gold price of US$1,200/oz less 5% gross royalty.

2.Stockpile balance above 0.7 g/t cut-off grade is considered as reserve, while below 0.7 g/t is considered as resource. Proven Reserve includes the Reserve Stockpile.

3.The Reserve Estimate assumes expansion to a 30 kt/d mill.

4.The above mineral reserve estimate is classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum’s “CIM Definition Standards - For Mineral Resources and Mineral Reserves” incorporated by reference into National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

 

15.1Basis of Reserve Estimate and Pit Optimization

 

An economic pit shell generated at a gold price of $1200/oz, with cost criteria, metallurgical recoveries, geologic and geotechnical considerations guides the final pit design. The economic pit shell used to define the final pit limits was created using Datamine’s NPV Scheduler software (NPVS). NPVS uses the Lerchs-Grossman (LG) algorithm to define blocks that can be mined at a profit. The program then creates an economic shell based on the following information:

 

·Starting topography

 

 
Page 122

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

·Overall slope angles by rock type

 

·Metallurgical recoveries by mineralization and rock type and oxidation state

 

·Geologic grade model with gold grades, density, lithology and mineral types

 

·Process and mining costs

 

·Incremental vertical bench mining cost

 

·Downstream costs, such as gold refining, freight and marketing

 

·Sustaining capital for future equipment replacements

 

·Mining dilution and recovery

 

The Mineral Reserve Estimate was prepared using the December 31, 2015 topography and the parameters detailed in Table 15-2.

 

 
Page 123

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 15-2: LG Optimization Parameters

 

LG Parameter Cost /
Assumption
Unit
Piment (PM) Mining Cost 2.00 US$/t
PM Haulage Increment Bench (5 m) 0.029 US$/t
     
West Branch (WB) Mining Cost 2.00 US$/t
WB Haulage Increment Bench (10 m) 0.038 US$/t
     
Process Cost 16.04 US$/t ore
Site Admin 5.66 US$/t ore
Sustaining Capital 1.65 US$/t ore
Stockpile Re-handle 1.00 US$/t stock
Dump Leach 10.90 US$/t ore
     
Gold Price 1200 US$/oz
Selling cost 60.60 US$/oz
Other costs 6.00 US$/oz
     
Royalties 5.00 %
Payable 99.95 %
Discount rate 5 %
Sinking rate 10 Bench/year

 

Mineral Reserves are stated within an ultimate pit design at variable cut-off grades that are based on the process type, operating costs and metallurgical recovery.

 

The dilution allowance for the Mineral Reserve estimate is applied using diluted model grades. The diluted model, which was built from the resource block model, incorporates dilution and ore loss and eliminates the need for applying additional factors.

 

Slope parameters based on geotechnical considerations were applied to the pit design along with ramps and geotechnical catch benches, and subsequently used to generate overall slope angles. The overall slope angles used in pit optimization are shown in Table 15-3.

 

 
Page 124

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 15-3: Overall Slope Angles Used in Pit Optimization

 

Material West Branch Piment
Azimuth (°) Slope (°) Azimuth (°) Slope (°)
Oxide 0 30 0 25
45 36 90 29
225 30 270 25
Fresh 0 33 0 34
20 48 90 48
210 33 270 34

 

Gold recovery is determined by ore type and process method. The gold recovery is calculated from the information in Table 15-4 where gold grade is expressed in grams per tonne (g/t).

 

Table 15-4: Process Recoveries

 

Facility Ore Type Gold Recovery (%)
CIL Oxide mineralization 93
Fresh mineralization

Recovery % = 

1.2143 x ln(head grade g/t) + 91.9

Dump leach West Branch – all rock types 60
Piment – all rock types 70

  

The mine operating costs used for pit optimization include ongoing major mine equipment capital costs. The mine equipment sustaining capital is used in the economic model to simulate mine capital expenditures when generating the economic pit.

 

The top-down discount method was used during pit optimization. This is a procedure based on multiplying the block value by a discount factor that is a function of the annual cost of money, an estimate of the average annual vertical advance rate of mining, and the relative depth of the block. This method simulates the actual mine plan discounted cash flow that is burdened with up front stripping costs and aids in the selection of a higher value pit.

 

15.2Comment on Mineral Reserves

 

Roscoe Postle Associates Inc. conducted a review of the resource model to assess the model’s suitability for pit optimization, design and resource estimation.

 

John Sims, AIPG Certified Professional Geologist, has certified that, to the best of his professional judgment as a QP (as defined under NI 43-101), the Mineral Reserve and Resource estimates have been prepared in compliance with NI 43-101, including the

 

 
Page 125

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

CIM Definition Standards incorporated by reference, and conform to generally accepted mining industry practices.

 

The results of the economic analysis to support Mineral Reserves represent forward-looking information that is subject to a number of known and unknown risks. These uncertainties and other factors may cause actual results to differ materially from those presented here. Areas of uncertainty that may materially impact mineral reserve estimation include:

 

·Commodity price and exchange rate assumptions;

 

·Capital and operating cost estimates; and

 

·Geotechnical slope designs for pit walls.

 

 
Page 126

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

16.MINING METHODS

 

Mining Operations

 

Commercial production of gold at Tasiast began in January 2008, and a total of 1,613,724 oz was produced by the end of 2015.

 

Ore and waste rock is currently mined by conventional open pit methods from two pits (West Branch and Piment). Prior mining has taken place in West Branch, Piment and several other completed pits at Tasiast. Since Kinross acquired the property in late 2010, a total of 379 million tonnes of material have been mined from various pits, including 51 million tonnes in 2011, 78 million tonnes in 2012 and 82 million tonnes in 2013, 55 million tonnes in 2014, and 63 million tonnes in 2015. Drilling and blasting is performed with regards to wall control and fragmentation using the same methods in both ore and waste material. The excavation fleet on site is made up of seven Caterpillar 6060 (formerly Bucyrus RH340) hydraulic excavators and six Komatsu PC1250 hydraulic excavators. The truck fleet is made up of 42 Caterpillar 793D 220 t haul trucks and 21 Komatsu 785 90 t haul trucks. The larger shovel and haul truck pairing (CAT6060 and CAT793) is used at West Branch (Figure 16-1), while the smaller shovel and truck combination (PC1250 and KOM785) is used at Piment. The introduction of larger mining equipment has shifted the mining strategy from a highly selective mining practice to a combination of both bulk and selective mining.

 

Figure 16-1: Excavators and Haul Trucks Working in West Branch Pit

 

(GRAPHIC)

 

Currently mill grade material is hauled to the run-of-mine (ROM) pad adjacent to the primary crusher and dumped onto the ROM stockpile for reclaim by a front-end-loader (CAT 988). Sub-grade material is stockpiled adjacent to the ROM pad for later treatment,

 

 
Page 127

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

while mill grade material goes directly to the existing 8 kt/d plant for processing. The grinding circuit produces a product size of 80% passing 90 microns which is then processed in a conventional CIL circuit and ADR plant to produce doré bullion. Gold recovery varies from 91% to 93%. Low-grade oxide material is trucked directly to the dump leach pads. The dump leach facility consists of two separate leach pads with a gold recovery of 60% from the West Branch pad and 70% from the Piment pad. Tailings slurry from the CIL process is pumped to the tailings storage facility (TSF), a specifically engineered facility consisting of two imperviously-lined paddock dams located one kilometre southwest of the processing plant. After settling out the solids, the process solution is recovered and pumped to the plant for re-use.

 

In March 2014, Kinross completed a feasibility study to expand Tasiast operation to 38 kt/d. Due to the lower gold prices in 2015, Kinross suspended the expansion to 38 kt/d and initiated a Tasiast optimization study to explore alternatives for Tasiast’s growth potential in the current gold price environment. The Tasiast optimization study recommended a two-phased expansion that leverages the existing mill infrastructure. Phase One of the expansion increases the mill throughput from the current 8 kt/d to 12 kt/d. Phase Two increases the mill throughput from 12 kt/d to 30 kt/d with the installation of additional milling, leaching, thickening and refinery capacity.

 

In 2015, Kinross initiated a feasibility study to assess the economic viability of Phase One and a pre-feasibility to assess the economic viability of Phase Two. The studies concluded with a recommendation to progress with Phase One into execution and advance Phase Two into a feasibility study. The mine plan, production schedule and reserves statement in this report are based on the 30 kt/d (Phase Two) pre-feasibility study.

 

The current conventional open pit truck and shovel mining method will continue to be used. Varied blasting techniques, such as presplit and buffer holes, will be employed to protect the pit slopes. Blasted material will be routed based on the application of cut-off grades. Cut-offs are initially based on the net block value at the pit optimization stage and later on the gold grades during scheduling. Applying cut-off controls ensures that the highest-value materials are routed to the CIL process, while lower-grade materials are routed to the stockpiles or, if appropriate, to the dump leach. Materials below the cut-off threshold are sent to the waste destinations. The material grades and potential stockpile destinations are shown in Table 16-1.

 

 
Page 128

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 16-1: Material Routing

 

Grade (g/t) Identification Potential Stockpile
2.0+ High grade High grade (HG) stockpile
1.5-2.0 High grade HG stockpile
1.0-1.5 Medium grade Medium grade (MG) stockpile
0.6-1.0 Low grade LG stockpile
0.4-1.0 Oxide material Leach dump

Oxide < 0.4 

Fresh < 0.7

Waste dump Waste dump

  

Loading and hauling requirements will be met by maintaining the current operating mining fleet and purchasing additional mining equipment as needed to support the processing expansion case to 30 kt/d. Equipment selection assumes extended use of the mobile mine equipment that is currently in operation at Tasiast. Estimates of future requirements are based on current operating practices, general and site experience, and take into consideration:

 

·Operation of several faces (shovel pits) simultaneously to meet the long-range schedule and requirements

 

·Use of existing and new large-scale mining equipment to lower operating costs

 

·Use of well-proven and advanced mine equipment technologies to improve performance

 

·Use of component replacement and preventive maintenance practices to minimize major equipment failures

 

·Design of constraints to accommodate the selected fleets in both direct production and support roles.

 

The current configuration of the existing shovel and haul truck fleets will be used for the duration of mining and no replacement of this equipment is anticipated for the remainder of the LOM. Equipment life has been projected from actual operating hours, with estimates of future usage based on the mine plan.

 

 
Page 129

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Mining at the 30 kt/d throughput rate will be performed by the current mining fleet and supported by new purchases shown in Table 16-2.  Table 16-2: 30 kt/d Total Mobile Equipment Schedule

 

The timing for the equipment purchases is informed by analysis of the LOM plans in the CAPEX model.

 

Table 16-2: 30 kt/d Total Mobile Equipment Schedule

 

Mobile Equipment Current Required Additional
Haulage
Cat 793 42 54 12
Komatsu 785 21 20 -
Loading
Cat 6060 (Previously RH340) 7 6 -
PC 1250 6 5 -
Cat 994 Loader 2 2 -
Drills
Pantera 1500/1100 (5m) 5 10 5
Pantera DR580 (5/10m) 2 4 2
Bucyrus SKFX (10m) 8 8 -
Atlas PV 235 (10M) 2 4 2
Major Support Equipment
D10T Bulldozer 8 7 -
D11T Bulldozer 2 2 -
Cat 854K Wheel Dozer 3 3 -
Cat 773G Lube Truck 4 5 1
Cat 24M Grader 3 6 3
Cat 950 1 1 -
Water Truck 4 4  
PC350 1 1 -
CAT 924 1 1 -

  

Mine Design

 

The Tasiast final pit design consists of a series of overlapping pits that extend along a strike length of approximately 8 km. The configuration of the mining area is shown in Figure 16-2. Only Piment and West Branch are actively being mined at present.

 

 
Page 130

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 16-2: Plan View of Tasiast pits 

 

(GRAPHIC)

 

 
Page 131

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Geotechnical Considerations

 

Historically, the project has been broken into two geotechnical zones where the Piment Zone is north of approximately 72,000 N and the West Branch Zone is south of 72,000 N. Overall pit slope angles and inter-ramp angles for the Piment Zone were initially determined by Scott Wilson Mining UK (Scott Wilson) in 2009 and subsequently optimized by Stacey Mining Geotechnical Ltd (Stacey) in 2011. The slope angles that are currently applied at Piment are shown in Table 16-3, with catch benches based on the bench face angles and total bench height.

 

Table 16-3: Geotechnical Design Parameters, Piment Zone

 

Zone Depth
(m)
Wall(s) Bench Face Angle
(°)
Inter-Ramp
Angle

(°)
Total
Bench
Height

(m)
Berm Width
(m)
Oxide 0 - 10 All walls 60 39 10 6.5
Transition 10 - 50 West wall (FW) 50 34 10 6.5
All other walls 65 42
Fresh > 50 West walls (FW) 50 38.5 20 8.5
East walls (HW) and end walls 75 55

  

The geotechnical parameters used to support the final West Branch pit design and subsequent pushbacks are based on the geotechnical investigation completed by Golder Associates (2014). The resulting slope design criteria are based on four key zones: oxide, upper transition, lower transition, and fresh.

  

The slope angles that are currently in use at West Branch are shown Table 16-4.

 

Table 16-4: Geotechnical Design Parameters - West Branch Zone

 

Zone Depth
(m)
Azimuth Bench Face Angle
(°)
Inter-Ramp Angle
(°)
Total
Bench
Height

(m)
Berm
Width

(m)
Oxide 0 - 30 330° to 210° 60 39.2 10 6.5
210° to 330° 45 31.2

Upper 

Transition

30 - 60 330° to 210° 65 41.9 10 6.5
210° to 330° 45 31.2

Lower 

Transition

60 - 100 330° to 210° 65 48.3 20 8.5
210° to 330° 45 35.1
Fresh >100 330° to 210° 75 58.3 30 10.5
210° to 330° 45 36.5

 

 
Page 132

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The designed operating bench height is 10 m in West Branch and 5 m in Piment. The final pit walls in West Branch will be triple benched where it is permissible, resulting in a bench height of 30 m. Piment will be quadruple benched, resulting in a 20 m bench height. Intervening catch benches vary based on the bench face angles and total bench height.

 

The overall slope angles used for optimization purposes (Table 15-3) were adjusted to reflect allowances for haul ramps and geotechnical step-outs.

 

Groundwater ingress is not expected to interfere with operations as mining progresses into fresh rock. A pit floor sump is currently used to remove water during mining of the oxide and transition zones. This water is used for dust suppression. Horizontal drains for pit wall depressurization and/or dewatering wells may be used in specific locations with conductive fractures in the rock mass.

 

Surface run-off from any unexpected storm events will be diverted from the pit by a ditch and berm system.

 

Pit Design

 

The basis for the ultimate pit design is the economic LG pit shell generated using the Datamine NPVS software package. The pit limit was generated by applying a $1,200/oz gold price, operating costs and geotechnical criteria to the Measured and Indicated resource. An economic model was created within the NPVS program and the final pit limit was generated using the industry standard LG algorithm. The resulting optimized economic pit shell does not include access ramps and is not restricted by equipment or mining limitations. The final design pit involves these considerations while maintaining as much of the LG guidance as is feasible.

 

The final pit design includes compliance with the geotechnical recommendations for slope design parameters, catch benches, and haul road width. The bench height was selected to ensure that the existing fleet of Caterpillar 6060 and Komatsu PC1250 excavators are able to mine safely. The design also places pit exits close to the various material destinations, uses flat switchbacks wherever possible, maintains ramps with a gradient of 10% and uses 20 m wide roads at Piment and 35 m wide roads at West Branch.

 

The processing plant is located on the east side of the Piment pit and access roads for ore haulage from west to east are located between the operational pits

 

Figure 16-3 shows a cross-section of the West Branch pits. This cross-section illustrates how the pushback sequencing targets high grade ore zones while minimizing the waste stripping requirements during the early pushbacks.

 

 
Page 133

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 16-3: Comparison of Designed Ultimate Pit versus LG Pit Shell

 

(LINE GRAPH)

 

Waste Dumps

 

Waste rock is used for haul road and tailings dam construction as needed. The road network currently in place is well developed, but will require continued maintenance. Additional roads will also be required throughout the life of the mine.

 

When not needed for infrastructure purposes, waste material is disposed of in constructed waste rock dumps situated at least 100 m radially away from the final crest of an open pit and outside the zone where there is potential for dilation, cracking and subsidence related to the pit walls. Management of these dumps during the mine life cycle is important to protect human health and safety, along with the environment. As no specific national standard for waste rock storage exists, the Kinross Standard for Waste Rock is applied to the Tasiast waste rock storage facilities.

 

The sites of the waste dumps are characterized by flat ground with a thin cover of soil, alluvium and drifting sand, with minor low outcrop. The soil and alluvium are thought to have a low clay content, but there is potential for localized shallow clay pans. The rock below this is completely weathered and partially weathered (pervasive oxidation) to a depth of about 40 mbgl. Minor quantities of groundwater are expected in this area, and much of this will drain as the pits are developed nearby. This suggests that there is unlikely to be significant subsidence as drainage occurs. No known transects of defined streams or gullies are in this area that would facilitate run-off water flow, nor are there paleo-alluvial channels. However, depressions might occur in which sheeting run-off water could become concentrated.

 

 
Page 134

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Dumped waste material comprises weathered and unweathered rock. The weathered material ranges from pervasively to partially weathered and includes patches of completely weathered, clayey rock. Partial weathering predominates. Blasted weathered rock is finely graded, including clay-silt fines. The unweathered rock is strong and massive and, when blasted, is coarsely graded, including boulders that will require secondary blasting for loading and haulage. This material is suitable for the base of the dump, as it does not have a high clay content.

 

Static Acid Rock Drainage (ARD) tests performed on the range of lithologies encountered in the mining area indicate that 92% of the samples were considered to be non-acid forming (NAF). Where materials have been identified as potentially acid forming (PAF), the magnitude of acid generation is generally regarded as comparatively low. On balance, the acid neutralization capacity of host waste rock is currently considered to be significantly in excess of the total acid generating potential.

 

Leachate testing demonstrated that under the provision that waste rock dumps remain at circum-neutral pH, no potential toxic metal leaching is to be anticipated.

 

As the climate is arid and there is no permanent surface water and very limited groundwater, there is low potential for ARD concerns to develop. However, any potential ARD issue will be mitigated by ensuring that material that is identified as PAF (per the material contained inside the wireframe for ARD, Section 14.2 under “Acid Rock Drainage Potential”) will not be dumped on the outer shell of the waste dumps.

 

The dump design is based on 10 m high lifts with a dump face angle at the angle of repose of the dump material (37°). Each successive lift will be stepped back by approximately 30 m from the crest of the underlying lift to create a benched configuration for the final face of the dump. Total heights will be limited to 50 m to 100 m. The dumps will be accessed by 35 m wide dual-lane ramps at a 10% gradient. Track bulldozers will be used to assist the haulage fleet to facilitate proper dump construction, including grading the top of each lift away from the pit to direct any rainwater run-off and placing coarsely-graded, unweathered rock on final rill faces.

 

The dump footprint and height requirements were enhanced based on an analysis that optimized haulage from the pit. The waste dumps are located within the footprints of previous studies and require no modification to the current permitting.

 

There are two waste dumps along the east and west sides of the Piment Pit and two waste dumps along the east and west side of the West Branch pit (Figure 16-4). Based on the 30k t/d pre-feasibility study mine plan, the waste dumps will require 788 Mt of capacity after 2015. Excess capacity is available in all waste dumps.

 

 
Page 135

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 16-4: Piment and West Branch Mining Limits and Infrastructure Layout

 

(GRAPHIC)

 

 
Page 136

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Production Schedule

 

The mining rate was optimized to feed the CIL plant at the current capacity and to prepare for Phase One expansion in 2018 and Phase Two expansion in 2020. As such, the recommended mining rate is ~68 Mt/a in 2016 and 2017. In 2018, the mining rate is increased to approximately 100 Mt/a in order to feed the 30kt/d mill (Phase Two) in 2020.

 

The distribution of equipment across the pits, phases and benches results in variable production rates using the same fleet. As such, the total material moved varies year over year (Table 16-5). The mining schedule was optimized with a maximum of 54 Caterpillar 793 haul trucks and a maximum of 20 Komatsu 785 haul trucks.

 

Mining of the West Branch pit continues throughout 2026. On the other hand, mining in Piment is resumed in 2020 and ends in 2026. The 30 kt/d expansion has an overall strip ratio of 6.3:1.

 

Table 16-5: 30 kt/d Case Mine Production Schedule

 

  Piment West Branch Total
  Ore Gold Waste Ore Gold Waste Mined
  Thousand t g/t Au Thousand t Thousand t g/t Au Thousand t Thousand t
2016 -- -- -- 8,266 1.47 60,115 68,381
2017 -- -- -- 6,850 1.99 60,859 67,709
2018 -- -- -- 10,682 1.66 94,523 105,205
2019 -- -- -- 10,446 1.68 94,554 105,000
2020 82 1.06 19,835 9,644 1.72 91,020 120,581
2021 1,575 1.27 17,918 19,157 2.11 75,532 114,181
2022 3,539 1.50 14,035 13,630 2.40 80,450 111,654
2023 4,310 1.64 12,001 5,643 2.35 82,482 104,435
2024 1,779 2.28 4,473 8,294 1.63 54,933 69,479
2025 195 3.50 124 12,419 2.58 20,841 33,579
2026 -- -- -- 7,624 2.43 4,484 12,108
LOM 11,479 1.67 68,386 112,654 2.03 719,793 912,312

Notes: 

1. Mine production schedule is based on the final pit design, diluted mine model, and the end of 2015 surface. 

2. Excludes ore tonnes and gold ounces in starting stockpile mined pre-2015.

  

The process plant will continue to operate at approximately 8 kt/d until Q4 2017. The 12 kt/d plant is anticipated to start up in Q4 2017, and is expected to achieve full production in Q1 2018. The 30 kt/d plant is expected to start up in mid-2019 and achieve full production in Q1 2020. Table 16-6 shows the process plant feed schedule by year.

 

 
Page 137

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 16-6: 30 kt/d Case Process Plant Feed Schedule

 

  CIL Process Plant Dump Leach
Ore  Au Grade Contained Gold Gold Recovery Ore  Au Grade Contained Gold Gold Recovery
Thousand t (g/t) Thousand oz (%) Thousand t (g/t) Thousand oz (%)
2016 2,739 2.06 181 93.01% 835 0.68 18 67.34%
2017 2,966 2.85 272 93.21%        
2018 4,277 2.65 364 93.15%        
2019 6,001 2.30 444 93.05%        
2020 10,950 1.97 695 92.85%        
2021 10,950 2.97 1,045 93.29%        
2022 10,950 2.90 1,022 93.28%        
2023 10,950 2.03 716 92.92%        
2024 10,950 1.79 629 92.76%        
2025 10,950 2.86 1,007 93.33%        
2026 10,950 2.06 726 92.92%        
2027 10,950 1.09 383 91.99%        
2028 10,950 0.80 283 91.54%        
2029 10,950 0.80 283 91.54%        
2030 5,859 0.80 151 91.54%        
LOM 131,343 1.94 8,201 92.68% 835 0.68 18 67.34%

Notes: 

1. Process plant feed schedule includes ore tonnes and gold ounces mined pre-2015, processed from stockpile. 

2. The dump leach recovery accounts for ounces in the circuit.

  

Once mining operations have been completed in 2026, the CIL plant will continue processing the low grade stockpiles that will have developed over the course of mining.

 

Personnel Requirements

 

The current mine operation at Tasiast is owner-operated and applies conventional open-pit operational practices, with drilling, blasting, loading, hauling, support and administrative functions. The mine operates 365 scheduled days per year and 24 hours per day, primarily divided into two 12-hour shifts per day for mine operations and mine maintenance.

 

The mine organization includes functional groups for mine operations (drilling and blasting, loading and hauling), maintenance, mine technology and technical services

 

 
Page 138

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

(Table 16-7). The organization is staffed to support operational, safety and environmental requirements. Mining-related functional groups are organized under the mine manager or technical services manager. The mine manager is allocated functional groups for mine operations, maintenance and mine technology. Among the functional groups responsible for mine operations, drilling and blasting are managed together, as are loading and hauling. The technical services manager oversees functional groups for technical services, geology and geotechnical services. The technical services function for the existing operations includes technical engineers in mine planning, surveying, geotechnical engineering and mine operations, as well as geologists in grade control. The mine manager and technical services manager collaborate to manage mine operations, with each reporting to the operations director at Tasiast.

 

Mining cost estimates for the expansion include appropriate staffing levels for mine operations, based on present staffing levels for the existing organization and future mine plan requirements. Expansion requirements for equipment operators and mechanics, along with the requisite supervisors and support equipment operators, have been projected in line with the vehicle operating hours required to realize planned tonnage as per the expansion case mine plan. Expansion mining cost estimates have been benchmarked against mines similar in scope to the expanded Tasiast mine.

 

Table 16-7 outlines staffing levels for the expansion plant by functional group. The expansion of the plant requires a significant increase in personnel from 2017 to 2018 to accommodate the increase in mined tonnage. This personnel increase is concentrated in mine operations (which includes drilling, blasting, loading and hauling) and mine maintenance, in which additional mechanics will be required to accommodate the larger mining fleet.

 

As shown in Table 16-7, staffing levels will continue to increase after 2016 to accommodate the increase in mining equipment required by the expansion case mine plan. For example, as the pit deepens and mining rates are sustained after 2019 (resulting in increased haulage distances and drilling requirements), mine operations personnel will rise from 408 in 2018 to 481 by 2020.

 

 
Page 139

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 16-7: Expansion Mining Personnel by Function by Year

 

  Site Budget Planned Personnel for Expansion Mine Plan
  2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Tonnes Mined
 (million t)
68 68 98 92 112 103 97 107 88 52 21 6 0 0 0
                               
Mine Management 3 3 3 3 3 3 3 3 3 3 3 0 0 0 0
Mine Operations 277 277 408 412 481 501 490 477 381 253 169 35 29 29 26
Mine Maintenance 226 238 341 340 335 327 327 325 324 232 160 65 64 64 64
Mine Technology 8 8 10 10 10 10 10 10 10 7 7 -- -- -- --
Mine Technical
Services
22 22 18 18 17 17 17 17 16 14 12 -- -- -- --
Geology 69 69 79 79 79 79 76 76 70 64 41 -- -- -- --
Mining Total 605 617 859 862 925 937 923 908 804 573 392 100 93 93 90

 

As a result of the limited number of skilled mining personnel in Mauritania, it is expected that expatriate staff will be recruited to fill key senior management and technical roles, as well as key operational roles, such as excavator operators and operator trainers. Over time, as members of the national workforce develop mining skills and expertise, selected roles will no longer be filled with expatriate employees, and expatriate staff numbers will be progressively reduced. Table 16-8 presents the gradual replacement of expatriate personnel with national personnel as more roles can be filled by Mauritanians.

 

Table 16-8: Expansion Expatriate and National Mining Personnel by Year

 

  Site Budget Planned Personnel for Expansion Mine Plan
  2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Expatriates (non-operator, non-mechanic, incl. RCN) 63 60 75 75 65 53 51 48 46 34 27 11 10 10 10
Nationals (Non-operator, Non-mechanic) 153 153 173 173 174 177 176 176 170 142 105 13 13 13 13
Operators 279 279 417 421 490 510 499 487 391 257 161 40 34 34 31
Mechanics 110 125 194 193 196 197 197 197 197 140 99 36 36 36 36
Mining Total 605 617 859 862 925 937 923 908 804 573 392 100 93 93 90

 

 
Page 140

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

17.RECOVERY METHODS

 

17.1Current Waste Rock Facility

 

Currently, two waste dumps along the east and west sides of the existing Piment Pit and the west side of West Branch pit are used to dispose of waste rock.

 

17.2Current Water Management

 

A water supply bore field provides raw water for the mine, processing plant, dump leach and camp. The site potable water requirements are met by three reverse osmosis plants. For further detail on Water Supply, see Section 18.

 

The plant rejects in the form of tailings slurry is pumped to a tailings storage facility, where approximately 50% of the contained tailings water is recovered and pumped back to the plant or dump leach storage ponds.

 

17.3Current Process Plant

 

The 8 kt/d (approximately 3 Mt/a) capacity processing plant uses the CIL process producing approximately 70-80% of the gold shipped from Tasiast. The remaining gold is produced from the dump leach operations via a dedicated ADR plant. All produced gold is in the form of doré and is transported regularly to a refinery for final refining and sale. The Tasiast process flow diagram based on 8 kt/d is shown on Figure 17-1.

 

Crushing

 

Mined ore above plant feed cut-off grade is transported from the open pits to the plant by truck and deposited onto the run-of-mine (ROM) pad. The material is blended according to grade and competency. To aid blending, material is transferred to the crushing plant feed bin by front end loader. Lower grade weathered ore is hauled directly, without crushing, to the dump leach pads.

 

Crushing of the mineralized material takes place in three stages; a primary jaw crusher that reduces rock to less than 150 mm; a secondary cone crusher and two tertiary cone crushers. Screens located before the secondary crusher remove material that is at the final product size, nominally passing 16 mm. Material that is greater than 16 mm is fed to the secondary crusher.

 

Secondary crushed material is conveyed to a screening section before two tertiary stage crushers. Oversized rock is subjected to further crushing and returned to the screens, the tertiary screens and crushers forming a closed circuit. Material passing through the

 

 
Page 141

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

tertiary screens joins the secondary screen undersize as final product, of 80% passing 16 mm screen, which is then transferred to two fine ore bins.

 

Grinding

 

Crushed material is transferred from the fine ore bin at a controlled rate to each of two ball mills by means of a conveyor belt, and water is added to maintain a fixed slurry density in the mills. The ground ore slurry is pumped to hydrocyclones for classification. The target grind size is 80% passing 90 µm. Cyclone overflow containing solids of the required size flows to the leaching circuit. Coarser solids are returned to the mill for further grinding, via a gravity circuit to capture liberated, coarse gold particles.

 

The cyclone clusters were upgraded in 2013 to remove a capacity restriction, and new gravity concentrators installed in each grinding circuit to maximise recovery of coarse gold. The gravity concentrates flow periodically to a Leach Reactor where the gold is dissolved from the concentrates and the resulting solution pumped for gold recovery in the gold room.

 

CIL

 

The leaching circuit at Tasiast comprises a single leach tank and 6 CIL (carbon-in-leach) tanks where the dissolved gold is recovered on activated carbon. Material that exits the grinding circuit has an approximate slurry density of 42% solids, by weight. The slurry gravitates to the first of the seven agitated tanks via a trash screen to remove oversize tramp particles. Lime is added to increase the slurry pH to 10.2 then dilute sodium cyanide solution is added to maintain a fixed cyanide concentration. Pure oxygen is injected into the first 4 tanks to enhance gold leaching kinetics. The oxygen demand in the remaining tanks is satisfied by compressed air injection.

 

Activated carbon granules contact slurry in the CIL tanks to adsorb the dissolved gold from solution. Carbon that has achieved the target gold content, typically around 2,500 g/t, is termed “loaded” and is transferred daily to the elution circuit for recovery of the gold on a batch basis. After each such transfer, carbon in the remaining tanks is advanced counter-current to the slurry flow on a sequential basis, and fresh or “barren” carbon is added to the last CIL tank to maintain the carbon inventory.

 

After maximising gold recovery from the solution and ore particles in the CIL process, the resulting slurry flows via carbon retention screens to the thickener, where the solids settle to achieve a density of approximately 55% solids and residual solution is returned to the process. This existing thickener was modified, as part of the de-bottlenecking project, to achieve higher settling capacity and returned to service in 2013.

 

 
Page 142

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Carbon Elution and Electrolysis

 

Loaded carbon recovered from the CIL slurry by screening is first washed to remove entrained ore particles and then washed with hydrochloric acid solution, in a dedicated wash vessel, to remove lime scale from the carbon surfaces. The acid-washed carbon after being neutralized is transferred to the elution pressure vessel. To recover gold from the loaded carbon, batches of approximately 6 tonnes of carbon are subjected to a high pressure and temperature leaching process, called elution. Tasiast is using the Anglo American Research Laboratories (AARL) strip process with no cyanide addition. A hot caustic soak under pressure followed by a rinse with demineralized water removes the gold from the carbon and into solution. After gold removal, the “barren” carbon is transferred to a regeneration kiln for thermal reactivation of the carbon. Reactivated carbon is returned to the last CIL tank. Gold is recovered from the caustic solution by electrowinning onto stainless steel wire wool cathodes in electrowinning cells, located within the Plant gold room. The gold is removed as a sludge by pressure washing the cathodes at intervals. The sludge is dried and mixed with fluxing materials and charged to a diesel-fired crucible furnace. After melting, the slag is poured, followed by pouring the gold into bullion moulds. Bullion or “doré” contains 94% or higher gold content together with a minor content of silver. The doré bars are transported by a security firm to a commercial refinery for further purification and sale.

 

 
Page 143

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-1: 8 kt/d Plant Process Flowsheet

 

 (GRAPHIC)

 

 
Page 144

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Current Tailings Storage Facility

 

Tailings from the CIL process plant are pumped to the tailings storage facility (TSF). A new facility (TSF3) was constructed and commissioned in 2012. TSF3 is an engineered facility, currently comprising a four-sided lined basin, located on the west side of the open pits. After settling of the solids, a proportion of the contained water drains to a collection area within the storage basin, from where it is pumped to the plant for makeup to the process water system. Solids are retained in TSF3.

 

Dump Leach

 

Dump Leach Pads (Heaps)

 

The dump leach operation has recently been re-designed to process up to 11 Mt/a of low-grade oxide mineralization using two dump leach operations: one pad (Piment) with five cells separated by a raised berm for solution drainage control, and the other pad (West Branch) with 8 cells. The design of each pad allows for three 10 m lifts for a final stack height of 30 m. All solution collection ponds are plastic-lined with installed leak detection systems and bird netting protection. The gold-containing (pregnant) solution produced by the dump leach operations is pumped to a dedicated ADR plant to recover the gold and reactivate the carbon.

 

The initial construction involved earthworks to ensure correct drainage and following compaction a 1.5 mm HDPE plastic geomembrane liner was laid down. The liner was covered with a 0.5 m layer of overliner (suitable crushed waste or low-grade mineralized rock) which acts as a cushion layer to protect the plastic when dumping. Slotted plastic drainage pipes are laid across the pad within the overliner to allow the solution percolating through the heap to be collected and passed to the main drainage pipe at the side of the pad and hence to the required process pond. In addition, leak detection systems were installed below the geomembrane liner. Three ponds adjacent to each of the two pads are provided for storage and management of the barren, intermediate and pregnant solutions.

 

Mine haulage trucks deliver low-grade ROM material directly to the pads, where the material is dumped and levelled as required by bulldozer. Once sufficient material has been placed to an initial height of 10 m, a layer of lime is spread on top, with typical usage of 4.0 kg/t, and the surface is ripped. The heap is then available for irrigation.

 

At each of the two pads, barren solution is pumped from the barren pond to irrigate the heap. The first drainage collection of “intermediate” solution is collected in a pond, then pumped to another section of the pad to contact freshly placed ore. The resulting drainage is captured in the pregnant solution pond adjacent to each pad and pumped at a controlled fixed rate to the ADR plant for gold recovery. Make-up water is added to the systems from the raw water pipeline system connecting the bore field with the CIL mill.

 

 
Page 146

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

The lime added during stacking maintains a minimum pH of 10. Irrigation is targeted at 10 L/h/m2 and is applied using a system of plastic pipe headers and dripper pipe. Anti-scalant solution is added at pumping points to inhibit scale formation. Pregnant solution contains approximately 0.5 g/t Au.

 

ADR Plant

 

The pregnant solution produced by the dump leach operations is received in a single train of six carbon containing columns at the ADR plant, as seen in Figure 17-2. The pregnant solution flows by gravity from column to column, contacting carbon in each column as it rises from the bottom to overflow. The activated carbon granules adsorb the dissolved gold from solution. The solution leaving the last column is barren solution and is pumped to the dump leach operations for re-use. When the carbon in the first column loads with gold to the target level, the first column’s contents are advanced by airlift to a screen and discharged to an acid wash vessel. Sequentially, each following column is advanced counter-current to solution flow.

 

After acid washing, the carbon is advanced to the elution vessel, where the same AARL process as in the Plant elution system is used to elute gold from the carbon. The gold rich “pregnant” solution is stored in a surge tank prior to electrowinning. After elution of the gold, the barren carbon is re-activated thermally in a diesel fired rotary kiln, stored in a surge bin and eventually returned to the column train via the last tank in series.

 

Figure 17-2: West Branch Solution Ponds and ADR Plant

 

 (GRAPHIC)

 

 
Page 146

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Gold is recovered from the pregnant solution by electro-winning onto stainless steel wire wool cathodes in a single electro-winning cell. The gold is washed from the cathodes after each elution cycle, dried in an oven, mixed with fluxes and melted in a crucible furnace, all within the gold room attached to the ADR plant. Doré bars of 94% or higher purity are produced and transported to a commercial refinery for further refining and sale.

 

Gold Recoveries

 

Unit gold recovery estimates for the existing plants are based on metallurgical test work and a review of historical performance. The recovery varies by mineralization type, lithology and treatment method as presented in Table 17-1.

 

Table 17-1: Metallurgical Recovery by Process

 

Process Oxide Primary
CIL Recovery 93% 91%
DL Recovery* 54% - 75%  

Note: * Dependent on lithology

 

17.4Recovery Methods (30 kt/d)

 

General

 

Kinross will transition from the existing Tasiast 8 kt/d CIL plant through the start-up of the Phase One, 12 kt/d process plant optimization front end, finishing with the Phase Two, 30 kt/d full facility. The 30 kt/d plant will be in the same area and will incorporate the 12 kt/d plant.

 

In Phase One, a new front end 1400 mm x 2100 mm gyratory crusher and a 40 ft x 25 ft, 26 MW Gearless Mill Drive (GMD) Semi-Autogenous Grinding (SAG) mill will be added with additional leaching capacity to the existing 8 kt/d plant, to increase capacity to 12 kt/d.

 

This will also include adding three more leach tanks, new tailings facility capacity, a new process water pond, and upgrades to some reagents’ areas to ensure stable 12 kt/d operation.

 

In Phase One, the SAG mill will be operated in a single stage closed circuit with hydrocyclones, augmented with the use of pebble crushing. The cyclone overflow will feed the existing ball mill pump boxes where the material will be pre-classified prior to feeding the gravity and secondary grinding circuits. The cyclone overflow will go through three new leach tanks to accommodate the higher through-put with an improvement to

 

 
Page 147

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

retention time. Additional oxygen enhancement and elution capacity will be added to ensure that recoveries are maintained or improved.

 

Phase Two will consist of the addition of: a 27 ft x 46 ft, 20.5 MW GMD ball mill, larger pebble crusher, pre-leach and tailings thickeners, leach tanks, CIL tanks, a gravity circuit consisting of centrifugal concentrators and intensive leach cyanidation, an elution circuit, gold room, cyanide destruction system, and reagent mixing storage and distribution. Phase Two will include the necessary upgrades to consumable storage and utilities to facilitate full operation.

 

After Phase Two the front end will be run as a traditional SABC (SAG and ball mill with pebble crusher) circuit. The ball mill will operate in closed circuit with hydrocyclone classification. The cyclone overflow will go to a trash screen followed by the pre-leach thickener prior to leaching where oxygen will be injected.

 

The new leach tanks will feed a new CIL circuit, and carbon will be loaded, stripped, regenerated, and returned to the tail end of the CIL circuit. Elution will feed pregnant solution to a new gold room, and after electrowinning and smelting, gold doré will be produced.

 

The gravity circuit will feed dedicated electrowinning, and will also produce gold doré.

 

The CIL tails will go to a new tailings thickener that will feed a new cyanide destruction circuit. This will include an upgrade to the TSF (tailings storage facility), and new tailings lines and new process water return lines with associated pumping will be added.

 

Design Criteria

 

The design capacities for the crushing plant and process plant are 70% and 92% operating effective time. Based on test work, the key nominal design criteria for the major process circuits are summarized in Table 17-2. It should be noted that design factors accounting for higher gold grades were applied when required to match the mine plan. The plant design life is 15 years.

 

 
Page 148

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 17-2: Key Process Design Criteria

 

Area Criteria Unit Nominal Value
General Gold g/t 2
Daily throughput t/d 30,000
Process plant availability % 92
Annual gold production oz/a 652,772
Primary crusher Availability and utilization % 70
Crusher work index kWh/t 14.40
ROM top size mm 1,100
Crusher product size (P80) mm 150
Ore storage Capacity (live) T 15,000
Capacity (live) h 12
Grinding and pebble crushing Bond ball mill work index kWh/t 13.8
JKTech Axb   31.4
SAG mill product size (P80) µm 2,000
Ball mill product size (P80) µm 90
Pebble crusher feed size mm 70
Nominal feed to pebble crusher t/h 430
Gravity recovery Gold recovery % 31
Feed % to gravity circuit (cyclone underflow) % 27
Screening and thickening Feed density % w/w 30.3
Thickener underflow density % w/w 50
Leaching and CIL Leach retention h 12
CIL residence time h 12
CIL carbon retention time d 14
CIL carbon concentration g/L 12
Tailings thickening Thickener underflow density mg/L 65.0
Cyanide destruction Discharge solution CNWAD mg/L 45.0
Residence time h 1
Carbon treatment Stripping solution flow rate BV/h 2
Operating temperature °C 140
Operating pressure kPa 450
Number of elution vessels   2
Elution batch size t 7.5
Electrowinning (EW) and refining EW recovery % 98

 

Location Study

 

The Tasiast Expansion Project is a brownfield expansion; however, the new process plant is located 200 m south of the existing plant location within the mine lease boundaries. Figure 17-3 and Figure 17-4 show the 12 kt/d and 30 kt/d CIL plant layouts.

 

 
Page 149

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-3: Phase One CIL Plant Layout (12 kt/d)

 

(GRAPHIC) 

 

 
Page 150

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-4: Phase Two CIL Plant Layout (30 kt/d)

 

 (GRAPHIC)

 

 
Page 151

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Engineering Design Basis

 

Material Selection

 

The environmental and plant conditions will be extreme and will require careful selection of construction materials to suit the 15-year design life of the facility. Erosive process slurries will cause wear to plant equipment and piping. Strong acids and bases, cyanide and the use of saline water as process water and wash water will expose most of the wetted equipment to corrosion conditions.

 

Solution and Slurry Containment

 

All wet areas of the process plant will be bunded with a containment volume equal to 110% of the volume of the largest tank in the containment area, or 25% of the total combined tank volume in the case of hazardous materials. All wet areas in the thickener, leach and CIL sections will be connected to optimize containment. An emergency spillage pond will be provided to the east of the leaching facilities to contain excess slurry spillage that cannot be contained within the grinding building bunded floor area.

 

Areas with specific requirements (design code requirements or incompatibility of solutions, such as hydrochloric acid and sodium cyanide) will be provided with separate containment.

 

Secondary containment will be provided for major spills. Spills will be collected in a separate process spillage pond adjacent to the process plant.

 

Interfaces between Process Facilities

 

During Phase One, gold containing pregnant solution generated by the leach reactor and the carbon treatment plant at the new CIL plant will be processed in a new elution circuit. The resulting barren solution from the circuit will be pumped back to the new CIL plant.

 

During Phase Two, a larger elution circuit will be built and will work in conjunction with a new gold room, where the barren solution will be sent to the Phase Two CIL circuit.

 

Simplified overall process flow diagrams are shown in Figure 17-5 and Figure 17-6.

 

 
Page 152

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-5: Phase One, 12 kt/d Plant Flowsheet

 

 (GRAPHIC)

 

 

 
Page 153

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-6: Phase Two, 30 kt/d Plant Flowsheet

 

 (GRAPHIC)

 

 
Page 154

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Primary Crushing

 

The primary crushing facility will include a gyratory crusher, rock breaker and an apron feeder with one belt conveyor to convey crushed ore to the ore stockpile.

 

ROM ore with a top size of approximately 1,100 mm will be delivered via 250 t capacity Caterpillar 793 rear-dump haulage trucks, or 90 t capacity Komatsu 785 rear-dump haulage trucks, to the gyratory crusher. The hopper layout will allow both types of trucks to dump from two sides to the gyratory crusher. Ore will be dumped into a 600 t capacity hopper directly over a 450 kW, 1400 mm diameter x 2100 mm long gyratory crusher.

 

Coarse Ore Storage

 

The ore storage facility will consist of a crushed ore stockpile with three in-line apron feeders located in a tunnel under the stockpile. The apron feeders will transfer ore from the stockpile to the conveyor feeding the SAG mill.

 

The stockpile will have a live capacity that can support process plant operation for about 12 hours when the gyratory crusher is not operating. Dead ore will be recovered by a bulldozer and front-end loader and will be pushed to the apron feeders, if the gyratory crusher is unavailable for extended periods. The total capacity of the stockpile, including the dead ore, is approximately 45,000 t. The ore storage layout is shown in Figure 17-7.

 

 
Page 155

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-7: Conceptual Ore Stockpile

 

 (GRAPHIC)

 

Grinding Area

 

The grinding circuit will consist of a SAG mill and one ball mill operating in closed circuit with a hydrocyclone cluster. The ball mill and SAG mill will not share a common pumpbox due to the phased approach of increasing plant through-put.

 

Grinding will be performed by a 12.2 m diameter by 7.6 m long (flange to flange), 26 MW grate discharge SAG mill and a 8.2 m diameter by 14.0 m long (flange to flange) 20.5 MW overflow discharge ball mill. Ore from the stockpile will be fed to the SAG mill via the SAG mill feed conveyor. Crushed pebbles from the pebble crushing plant will also be added to the SAG mill feed conveyor.

 

The SAG mill trommel screen oversize (pebbles too big to pass through the screen) will discharge onto a rail-mounted double deck vibrating screen where the remainder of the slurry will be removed, and pebbles will be sent to the pebble crusher.

 

The hydrocyclone cluster will classify the feed slurry into coarse and fine fractions.

 

 
Page 156

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Pebble Crushing

 

The pebble crushing plant will consist of a 2 m3 surge chute and a CH 660 pebble crusher in Phase One later upgraded to an MP1000 (746 kW) for Phase Two. The crusher will operate in closed circuit with the SAG mill.

 

Pebbles from the SAG mill will be conveyed by belt conveyor to the pebble crushing plant and feed the surge chute. A by-pass chute will allow the pebbles to go to a bunker in cases of required maintenance. The surge chute will have pebble feed control to the crusher through a vibrating feeder. The surge chute will allow pebble flow either to the feeder or overflow directly to the crushed pebble return conveyor. This method allows by-pass of the entire circuit and also by-pass of the crusher during operation.

 

The pebble crusher product will discharge onto the crushed pebble return conveyor that will return the material to the SAG mill feed conveyor.

 

Gravity Recovery and Intensive Leach Circuits

 

The gravity recovery and intensive leach circuits will consist of two centrifugal gravity concentrators with feed-scalping screens, concentrate hoppers and a skid-mounted intensive leach unit. The equipment will be located to the south of the grinding area.

 

A portion of the hydrocyclone underflow from the grinding area will be directed to scalping screens to remove coarse particles.

 

Gravity concentrate from the centrifugal concentrators will be batch processed in the intensive leach circuit.

 

At the completion of the batch leach cycle, the resulting gold-rich pregnant solution will be pumped to a pregnant-solution tank, and from there pumped to the new gold room electrowinning circuit to recover the gold.

 

Screening and Thickening

 

During Phase One, the existing ball mills will be used to feed the existing gravity and leach circuits. The existing tailings thickener will be modified and used for Phase One.

 

In Phase Two, the screening and thickening area will include parallel linear trash screens, a pre-leach thickener and a tailings thickener.

 

During Phase Two, hydrocyclone overflow will flow by gravity to a distributor where the stream will be split among linear trash screens to remove tramp material. The linear screens will have a total area of 50 - 75 m2 and will have a screen opening of 700 µm. The oversize rock particles and trash from the screens will be collected in a bunker and

 

 
Page 157

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

periodically picked up and trucked to the tailings area for disposal. The undersize from the screens as slurry will be collected in a pipe and flow by gravity to the pre-leach high-rate thickener via a feed box.

 

The pre-leach thickener will have a diameter of 50 m, a high-rate feed well design, and will produce a thickened slurry of 50% solids to feed the CIL circuit.

 

CIL tailings slurry will flow by gravity to the tailings thickener via the thickener feed tank, together with reclaim water and make-up raw water to wash the solids and recover and recycle the cyanide remaining in the slurry.

 

Overflow from the thickeners will flow by gravity to the process water tank for reuse in areas of the process plant.

 

Cyanidation - Leaching and CIL

 

During Phase One, three additional leach tanks will be added. Ball mill cyclone overflow will feed one of two parallel linear trash screens, through new cyclone towers. The rest of the CIL circuit will be used and carbon transfer pumps and interstage pumping screens will be upgraded accordingly.

 

The CIL tails will feed the existing thickener and another carbon safety screen will be added along with a modified thickener feedbox.

 

During Phase Two, the leach circuit will comprise four mechanically agitated leach tanks (20 m diameter by average 20 m high) and six mechanically agitated CIL tanks (17.5 m diameter by 18.5 m high).

 

A new pre-leach thickener underflow will be pumped to the first leach tank and leached in a weak cyanide solution to dissolve gold. The leach circuit will increase gold concentration in the solution before contact with activated carbon in the CIL circuit. The leach circuit has been designed to provide 12 hour leach retention time, with an additional 12 hours in the CIL tanks for a total of 24 hours. The process water returning to grinding will also contain cyanide, so additional, well-agitated and aerated leaching will occur before the process water enters the leach tanks. Oxygen will be sparged at the bottom of the leach tanks.

 

In the leach section, the ore slurry will flow by gravity from tank to tank. The leach tanks will have the same diameter (20 m), but the height of the tanks will be varied in 500 mm increments to facilitate gravity flow between the tanks. The foundation for all tanks will be at the same elevation.

 

 
Page 158

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Leached ore slurry from the last leach tank will flow by gravity to the CIL circuit. Dissolved gold and silver will be adsorbed onto activated carbon particles in the CIL tanks. The CIL circuit has been designed to provide 12 hours of slurry retention time.

 

Cyanide Destruction and Final Tailings

 

The Cyanide Destruction (CND) circuit will consist of two mechanically agitated tanks operating in series to provide a total residence time of minimum one hour. The cyanide content of the slurry will be reduced to below International Cyanide Management Code effluent guidelines using the Cyanco CombinOx process. Treated slurry from the CND circuit will flow by gravity to a final tailings pump box, where the tailings will be pumped to the tailings impoundment facility.

 

The CND circuit will treat thickened slurry from the new tailings thickener, process spills from various contained areas, and process bleed streams. The CND layout is illustrated in Figure 17-8.

 

 
Page 159

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-8: Conceptual Cyanide Destruction Layout

 

 (GRAPHIC)

 

Carbon Treatment

 

The carbon treatment circuit design has been based on a modified Zadra design, and will consist of acid wash, carbon elution (stripping) and carbon regeneration. This circuit will recover the gold from the carbon and reactivate the carbon for reuse in the CIL circuit. Two trains will be provided to operate in batch mode. The circuit has been designed to complete two carbon strips per day and process 30 t/d of carbon for the 30 kt/d plant. Each train will treat 15 t batches of carbon.

 

Electrowinning and Refining

 

Electrowinning and refining equipment for the new CIL plant will be located in the new gold room, and will consist of electrowinning cells with associated equipment to handle

 

 
Page 160

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

the barren solution and sludge from the electrowinning cells. This gold room will have two smelting furnaces and dust scrubbers to handle the additional gold production.

 

Tailings Reclaim

 

Water will be reclaimed from the tailings impoundment facility for reuse in the process plant via a decant process water pond and submersible pump system.

 

Tailings reclaim water will be used as wash water in the tailings thickener.

 

Dump Leach and ADR Plant

 

Oxidized or weathered low-grade material not meeting the minimum gold content required for processing in the CIL plant is processed by heap leaching of ROM material (without crushing) in the dedicated Piment and West Branch dump leach pads. In this process, weathered, low-grade ROM material is treated with dilute cyanide solution.

 

Placement of ore on dump leach is anticipated to cease in 2017. This process will be followed by a period of two to four years of continued irrigation, first to recover all of the available gold, and then with raw water to rinse residual cyanide solution from the leached ore before closure.

 

Dump Leach

 

The current dump leaching operation treats uncrushed ROM rock from the open pit on the dump leach facility on the west side of the open pit.

 

The facility comprises a graded and lined pad on which the ore is placed in layers 10 m high. Once the dumping cycle is finished, the dump is treated with dry hydrated lime for pH control and irrigated with dilute cyanide solution through a surface network of pipes and drippers. Solution percolates through the dump, collects at the base and drains to a collection pond. Two-stage counter current leaching is used to maximize gold recovery and minimize water consumption. Three ponds are used for solution management:

 

·Barren (feed) solution and make-up water

 

·Intermediate leach solution

 

·Pregnant (final product) leach solution

 

A new dedicated ADR plant to process solutions from the dump leach pads was designed, constructed and commissioned in October 2011, and was operational by January 2012. The ADR plant treats pregnant leach solution from both the Piment and West Branch dump leach pads and returns barren solution to these systems.

 

 
Page 161

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

ADR Plant

 

The current ADR plant comprises a series of carbon contacting columns (each containing 6 t of carbon) where pregnant solution pumped from both dump leach operations contacts activated carbon to absorb the gold. Solution flows from one column to the next by gravity, ensuring gradual removal of gold. The barren solution (after gold adsorption) is pumped to the pond system at each of the two dump leach pads.

 

Periodically, loaded carbon from the first column is removed to the loaded carbon screen and then flows into the acid-wash vessel. Washed carbon is then transferred by pump to the stainless-steel pressure elution vessel. The caustic solution is indirectly heated using a diesel-fired boiler. After elution, the carbon is pumped from the vessel and regenerated through a diesel fired rotating kiln. Treated carbon is sized and returned to the adsorption columns together with fresh carbon as a make-up.

 

Eluate is collected in a surge tank and then pumped to the gold room in the ADR plant for treatment in an electrowinning cell to recover gold as sludge. Periodically, the sludge is drained, filtered, mixed with fluxes and smelted to produce gold bullion, all within a secure and supervised area. The gold room is power ventilated to maintain a safe working environment.

 

Utilities and Reagents

 

Water Distribution

 

During Phase One, the only change to water distribution is a relocated TSF facility and the creation of a process water pond which will work in conjunction with existing plant infrastructure.

 

During Phase Two, the following different types of water will be used in the 30 kt/d process plant:

 

·Process water: Overflow from the pre-leach thickener and tailings thickeners will be used as process water. The water will have a low gold concentration and a cyanide concentration of about 28 ppm. Process water will be used predominantly in grinding and widely in the process plant, except for areas that process tailings.

 

·Demineralized water: Demineralized water will be produced in a reverse osmosis (RO) plant located next to the raw water pond. Demineralized water will be used for flocculant preparation, in the carbon treatment circuit, in the intensive leach reactor and for sodium hydroxide solution makeup.

 

·Raw water: Raw water for the process plant will be brackish water from the water supply bore field. Water will be pumped from the raw water pond and will be

 

 
Page 162

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

introduced into the tailings thickener for wash water and make-up water. Raw water will also be used in areas that process tailings and in the slurry-pump gland seals.

 

·Reclaim water: Water will be reclaimed from the tailings impoundment facility via a submerged pump decant system to the new process plant’s water storage tanks. Reclaim water will be used as process water make-up via the tailings thickener.

 

·Carbon Transport Water: RO water will be used for carbon transport in the carbon treatment area. The transport water will be recirculated within the acid wash and elution circuits. Carbon fines will be removed in a settling tank.

 

Air Distribution

 

The air distribution system for the new CIL plant will include instrument, plant and process air, and will be based on a decentralized system due to the significant distances between users. The following compressed air centres are planned:

 

·An instrument and plant air system with compressors and receivers will be provided and located in the grinding area. Instrument and plant air will be distributed to comminution users in the process plant.

 

·An instrument air system with compressors and receivers will be provided and located in the leaching area. Instrument and plant air will be distributed to all users in the wet end of the plant.

 

·A smaller and separate air compressor in the crushing area will provide air for the crusher building.

 

·Process air compressors will be located in a compressor house near the cyanide destruction tanks. The three compressors will supply low-pressure process air to the leach tanks (in case the oxygen plant is down) and CIL tanks.

 

Oxygen

 

A vacuum-pressure swing adsorption (VPSA) oxygen generation plant will provide oxygen gas to be used in the leach tanks. Oxygen will be sparged at the bottom of the leach tanks. The oxygen plant will be located adjacent to the process air compressors, and will be provided as a vendor package.

 

Reagent Mixing and Storage

 

General

 

In general, with the exception of lime, consumables are received in super sacs, totes and similar small containers after ocean transport in sea containers. With the exception

 

 
Page 163

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

of cyanide, the containers are emptied at the port and hauled to the site using typical highway-type trucks. Storage at the site is designed to provide continuous supply of the consumables after allowing for ocean shipping frequency, port disruptions and in-country delays. Typically, up to 45 days’ supply of each consumable is stored at the site.

 

Process reagents for the new CIL plant will be stored in segregated covered structures in a separately fenced area, located east of the plant. A portion of this area will be used for temporary storage of empty containers.

 

Slaked Lime Slurry

 

Slaked lime slurry, produced from quicklime (CaO) received in bulk, will be used for pH control in the leach and cyanide destruction circuits. While the existing operation receives hydrated lime in one-tonne bags, the supplier has proposed to erect a facility at one of the ports to receive coarse quicklime in bulk, to store and mill it to provide a ground, 2 mm dry product and to deliver it on a just-in-time basis to the mine. The supplier will purchase and operate the pneumatic tanker trucks for delivery.

 

Sodium Cyanide

 

Sodium cyanide will be used to dissolve gold and silver in the leach circuit. Sodium cyanide will be supplied in 1 t boxed bags as solid briquettes and dissolved in process water to make a 20% w/w solution in the 57 m3 mixing tank.

 

The sodium cyanide handling area layout is shown in Figure 17-9.

 

 
Page 164

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-9: Conceptual Cyanide Handling Area

 

(GRAPHIC)

 

Flocculant

 

A packaged flocculant make-up system will be provided to supply flocculant to the thickeners. Flocculant will be supplied in solid form and mixed with demineralized water in a mix tank. The flocculant preparation system is shown in Figure 17-10.

 

 
Page 165

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Figure 17-10: Conceptual Flocculant Preparation System

 

(GRAPHIC)

 

Sodium Hydroxide (Caustic)

 

Sodium hydroxide will be primarily used in the carbon treatment circuit. Sodium hydroxide will be supplied in solid form and dissolved in demineralized water to make a 20% w/w solution in a 20 m3 mixing tank. The mixed solution will be pumped to the 48 m3 supply tank, where it will be stored before being pumped to the carbon strip circuit.

 

Hydrochloric Acid

 

Hydrochloric acid will be used in the carbon treatment circuit. The hydrochloric acid will be supplied in liquid form at 30% v/v strength in 1000 L totes. The hydrochloric acid will be pumped from the totes to a 38 m3 mixing tank and will be diluted to a 3% v/v solution using demineralized water before being pumped to the acid-wash circulation tank at the carbon treatment circuit.

 

 
Page 166

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Activated Carbon

 

Activated carbon will be added to make up carbon losses and carbon fines removed in the carbon treatment circuit. The activated carbon will be supplied in solid form, and raw water will be added.

 

Copper Sulphate

 

Copper sulphate will be used as a catalyst in cyanide destruction. Copper sulphate will be supplied in solid form in 1 t bags and dissolved in raw water in a 10 m3 mixing tank to make a 15% w/w solution. The mixed solution will be pumped to the 20 m3 supply tank, where it will be stored before being pumped to the CND circuit.

 

Sodium Metabisulphite

 

Sodium metabisulphite (SMBS) will be used as the sulphur dioxide source for cyanide destruction. SMBS will be supplied in solid form and dissolved in seawater to make a 20% w/w solution in a 10 m3 mixing tank. The mixed solution will be pumped to the 20 m3 supply tank for the 30 kt/d plant, where it will be stored before being pumped to the cyanide destruction circuit. Both mixing and supply tanks will be located close to the copper sulphate system.

 

Hydrogen Peroxide

 

Hydrogen peroxide will be used for cyanide destruction. The hydrogen peroxide will be supplied in liquid form at 70% (by volume) strength in 25 t bulk iso-containers and will be pumped from the iso-container to a 7 m3 storage tank. Hydrogen peroxide will be pumped directly to cyanide destruction tanks.

 

Antiscalant

 

Antiscalant will be used in the carbon elution columns in the carbon treatment plant, and will be introduced via the elution barren tank. The antiscalant will be delivered to the plant in 1000 L capacity totes in liquid form, and will be pumped directly to the elution barren tank in the carbon strip circuit.

 

Facility Operations

 

Commissioning and Ramp-up

 

Phase One commissioning will start in Q4 2017 and ramp up from 8 kt/d to 12 kt/d in Q1 of 2018.

 

The Phase Two ramp up from 12 kt/d will start in July 2019 and be complete in January 2020.

 

 
Page 167

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Commissioning usually begins during the final stages of construction. As the construction of a section of the plant is completed, the section is handed over to commissioning. Having both construction and commissioning underway at the same time minimizes the delay between final construction completion and the start-up of the plant.

 

The main phases of commissioning are:

 

·Completion of installation
  
·Inspection, testing and trials of equipment
  
·Systems handover to the owner by the contractor
  
·System testing
  
·Plant start-up
  
·Plant ramp-up

 

When all systems have been tested, the plant is handed over to the owner’s operating team. Acceptance criteria in terms of plant throughput and duration of test runs will have been agreed upon before beginning commissioning.

 

Start-Up

 

When all systems have been successfully tested and accepted, the plant is handed over to the operations manager who then takes responsibility for operating the plant.

 

Ramp-Up and Performance Testing

 

This stage of commissioning consists of the period after handover and start-up during which the plant throughput is increased to full capacity, through gaining operational familiarity and removing any operational, mechanical or electrical constraints.

 

This stage varies in duration, depending on the complexity of the plant. For this plant, a comparatively simple CIL gold plant, the duration is planned to be about three months.

 

Bringing the plant up to design metallurgical performance might take longer, and involves the optimization of mill and cyclone performance, reagent dosage and control, carbon management and operator training. This work is planned to take an additional six months.

 

 
Page 168

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Performance testing is usually done within an agreed period after start-up and once the plant has reached full capacity. The period varies depending on the complexity of the plant; in this case, likely twelve months. Figure 17-11 shows the ramp-up schedule for the 30 kt/d new CIL plant with 92% operating time.

 

Figure 17-11: Commissioning Schedule

 

 (LINE GRAPH)

 

 
Page 169

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

18.Project Infrastructure

 

Water Supply

 

Raw water for the Tasiast site is from a water supply bore field, which is located 64 km west of the mine, and draws from a brackish aquifer using a system of 47 wells. Individual well yields range from 340 to 1,000 m3/d as determined during pump testing completed in June 2015. Individual wells within three separate well areas are combined in a manifold for each area and to feed three different systems. Each of these systems has a pumping station located at a facility referred as Sondage, with subsequent booster stations downstream. In total, the existing bore field and pipelines are capable of supplying up to 24,000 m3/d of raw water to the site based on the availability of the pipelines and pumps.

 

Reverse osmosis (RO) water treatment plants and storage basins/tanks are located at the mine site. Saline water produced from the RO plant is used to water the haul roads. Potable water is produced from RO water following additional disinfection steps. Potable water is also used for domestic purposes at the Tasiast site.

 

The current Tasiast permit allows a total extraction of 54.8 million m3 of water from the water supply bore field. The extraction allowed by the permit includes a limit of 36 million m3 of water from October 1, 2013 through December 31, 2020; and a daily extraction rate not exceeding 30,000 m3/day on a monthly average basis.

  

Tasiast has completed recent work supported by Schlumberger Water Services (SWS) to evaluate the abstraction capacity of the bore field. SWS concludes that the field can provide the water required for the 30kt/d expansion with a probability ranging from 80 to 90%. SWS has also indicated that potential water supply issues may be identified early through proper monitoring, providing a lead time of at least three years to design and implement remedial measures. Water supply issues are not expected for the 12 kt/d plant.

 

Tasiast will be required to apply for an extension of the permit in order to continue abstraction from the field beyond 2020 by substantiating the field’s capacity with a technical evaluation.

 

The project infrastructure required for the proposed expansion will include installation of new wells and development of an infrastructure replacement program for existing wells. The project will also include construction of a new raw water pipeline with a capacity of at least 12,000 m3/day in order to provide standby capacity for the system equivalent to at least 50% of the maximum daily demand.

 

 
Page 170

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Power Supply

 

Electric power is provided by the following installed equipment:

 

·The Phase 1 plant consists of eight LFO Caterpillar 3512 MUI high-speed generator sets and three HFO Caterpillar MaK 6CM32C medium-speed generator sets, with a total capacity of 12.7 MWe.

 

·The Phase 1B plant consists of four HFO fired (with LFO back-up) Wärtsilä 12V32 medium speed generator sets, with a total capacity of 18 MWe.

 

·The TTV plant consists of seven LFO MTU Model 16V40000G23 high-speed generator sets, with a total capacity of 11.9 MWe.

 

The Phase 1, TTV and Phase 1B power plants are all connected to and able to feed onto the 33 kV distribution system to supply required site loads. The above power supply totals 42.6 MWe, which is more than what is required for 12 kt/d.

 

There will also be a Phase Two power plant, to provide additional generation capacity to support expansion to 30 kt/d, located adjacent to the Phase 1B plant and the fuel oil storage area. Power generation will be from simple cycle, reciprocating engines located in a totally enclosed engine hall with an overhead crane for service and maintenance. Depending on the selected equipment manufacturer, medium-speed (500 rpm to 700 rpm) reciprocating units for this duty will be selected, running primarily on HFO with the flexibility to also operate on LFO continuously, if necessary, and for normal start-up and shutdown. The peak load for Phase Two is approximately 60 MWe and the total capacity for Phase Two is approximately 78 MWe.

 

The Phase Two power plant, operating in conjunction with the existing Phase 1B power plant, will be capable of servicing the required net peak power demand at any time and at any expected ambient condition, while accounting for equipment fouling, ageing effects and power plant parasitic loads. The plant configuration will also cater to the planned and forced outages of the generating sets expected during the design life of the plant. The power plant will not be connected to the national electric utility, and will operate 24 hours per day, seven days per week and 365 days per year as an islanded operation.

 

The existing Phase 1B power station will remain in service and will be integrated into the baseload operation of the new Phase Two power plant. The combined facility will have N-1 redundancy, meaning that the facility will still be able to meet the maximum site power demand with the loss of availability of one generator set. The TTV power plant, through the 33 kV power distribution system, will provide additional backup generating capacity on site on a stand-by basis.

 

 
Page 171

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Waste Management

 

Waste from plant and equipment maintenance, construction, offices, kitchens and accommodation is recycled or handled in an on-site landfill.

 

Sewage is disposed of through septic tanks fitted with soak away overflow systems. Currently there are septic tank systems at the mine camp and at the mine offices. Tanks are emptied on an ‘as required’ basis and the effluent is placed in a bunded area to dry. A waste water treatment plant was commissioned in 2011 and is treating approximately 50% of camp waste water. Treated effluent is disposed of through a spray field.

 

Tasiast Team Village (TTV)

 

The TTV is sized to accommodate a workforce of 3,540 personnel. It includes various facilities, such as clinic, laundry, kitchen and dining areas, gymnasiums, recreational rooms and various sports playgrounds.

 

Service and Administration Buildings

 

Service and administration buildings include:

 

·Guardhouse

 

·Training and development campus

 

·Training centre

 

·Warehouses

 

·Kitchen and dining hall

 

·Plant office building

 

·Welcome centre

 

 
Page 172

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

19.MARKET STUDIES AND CONTRACTS

 

Kinross typically establishes refining agreements with third-parties for refining of doré. Kinross’s bullion is sold on the spot market or as doré, by marketing experts retained in-house by Kinross. The terms contained within the refining contracts and sales contracts are typical and consistent with standard industry practice, and are similar to contracts for the supply of bullion and doré elsewhere in the world.

 

 
Page 173

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

20.Environmental studies, permitting, and social or community impact

 

20.1Environmental Studies

 

Current mine operations and the expansion project are based on the formal approval of a number of Environmental Impact Assessment (EIA) studies completed before and since mine commissioning in 2007.

 

For all project areas, environmental baseline conditions have been determined by reviewing existing published data, previous EIAs, satellite imagery and environmental reporting undertaken for the mine. Where appropriate, existing data for project areas was supplemented by primary data collected through environmental baseline surveys. Field-level baseline surveys were completed for project areas, including air quality, archaeology, flora, fauna, marine, water quality, traffic, and socioeconomics.

 

The baseline conditions formed the basis to assess the project through a series of EIAs and Environmental Impact Notices (EINs). The environmental assessments utilized applicable Mauritania legislation, the International Finance Corporation Performance Standards, the International Cyanide Management Code and Kinross Health, Safety, Environment and Social Management Systems for project design and management, mitigation strategies and performance monitoring. The environmental assessments determined appropriate mitigation and management where impacts could not be avoided through project design.

 

A review of waste rock geochemistry to determine the potential for acid rock drainage concluded that the rock has excess neutralizing capacity. Given the excess neutralizing capacity and the very low precipitation at Tasiast, acid rock drainage is not anticipated.

 

The Tasiast facilities operate under an environmental management system (EMS) that specifies activities to be planned and implemented by the mine’s environmental management team. The EMS incorporates the project design and management, mitigation strategies and performance monitoring commitments outlined in the environmental assessments, applicable legislation and specific permit requirements.

 

An element of each EIA prepared for the Tasiast mine site is a preliminary reclamation and closure plan and associated cost estimate. The preliminary reclamation and closure plan outlines the measures that will be taken to reclaim and close the proposed activities assessed in each EIA. The preliminary reclamation and closure cost estimate forms the basis of the financial assurance which is required prior to commencing activities outlined in the EIA. The current financial assurance for the existing operation is approximately

 

 
Page 174

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

$6.2 million. Discussions are currently underway with the Minister of Environment in regard to updating that amount based on current disturbance and another increase would be expected once the project is expanded. Those amounts are not known at this time. At least two years before entering closure, a detailed reclamation and closure plan must be submitted to the appropriate ministries for approval.

 

20.2Permitting

 

In addition to the exploitation permit No. 229 C2 (Section 4.2) and the adjacent exploitation and exploration permits, all other necessary permits for exploiting the Tasiast mine complex have been granted by the relevant Mauritanian authorities. A Phase 3 EIA for “off-site” sea water supply was approved following submission of a Phase 3 addendum. A subsequent EIA was approved to allow receipt of pre-assembled equipment at a beach landing and transportation to site. In addition, following discussion with the Government, an addendum to the Phase Two EIA was submitted and approved that described the project optimization through incremental increases in production and relocation of certain infrastructure. This addendum was approved by the Ministry of Environment in February 2016 and subsequent approval by the Ministry of Mines is pending. The key permits are shown in Table 20-1.

 

 
Page 175

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 20-1: Key Operating Permits and Environmental Assessments

 

Brief Name Issue Date
Authorization to construct a water pipeline route to the mine MMI Letter 090 – 23 May 2006
Authorization of water extraction (12 boreholes) MHE Letter 560 – 24 July 2008
Original EIA permit for Tasiast Mine

MEDD Letter 407 – 27 August 2009 

MIM Letter 264 – 27 August 2009

New developments EIA permit (dump leach, Tailings Storage Facility 2)

MEDD Letter 408 – 27 August 2009 

MIM Letter 264 – 27 August 2009

Groundwater abstraction permit for 30,000m3 per day MHA Letter 125 – 25 April 2011

Environmental authorization for Phase 1ai and Phase 1aii environmental impact  notices

MEDD Letter 151 – 16 June 2011 

MEDD Letter 166 – 10 July 2011

Environmental authorization for West Branch development (EIA)

MEDD Letter 665 – 10 October 2011 

MPEM Letter 1209 – 25 October 2011

Environmental authorization for Phase 1b development (EIA)

MEDD Letter 713 – 18 October 2011 

MPEM Letter 1210 – 25 October 2011

Environmental authorization for Phase 2 development (EIA)

MEDD Letter 556 – 19 July 2012 

MPEM Letter 1049 – 25 July 2012

Conditional environmental authorization for Phase 3 development (EIA)

MEDD Letter 600 – 22 September 2013 

MPEM Letter 844 – 6 October 2013

Extension of groundwater abstraction permit for 30,000 m3 per day until 2020 MHA Letter 6 – 7 January 2014
Addendum Phase 3 EIA, full authorization for Phase 3

MEDD Letter 605 – 21 June 2014 

MPEM Letter 751 – 31 July 2014

Beach Landing EIA AZFN Letter 2 – 13 January 2014
Addendum Phase 2 and Environmental Authorization

MEDD Letter 59 – 4 February 2016 

MPEM Letter Pending

  

20.3Socio-Economics

 

Mauritania is divided into 12 wilayahs (regions), one district (Nouakchott), 53 moughataas (counties) and 208 communes (municipalities).

 

The mine site is located in the Inchiri wilayah, which has a very low population density. The wilayah includes the Akjoujt moughataa and two main municipalities, Akjoujt and Bennichab, Akjoujt being the administrative capital with a population of approximately 8,500. The wilayah is administered by a council, directed by a governor (wali) who reports to the Minister of Interior. The basic administrative unit, the moughataa, is directed by a Prefect (Hakem) who exercises his power under the authority of the governor.

 

 
Page 176

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Inchiri is the least populated wilayah in the country, with the nomadic way of life being a key feature making up 20% of the total population. There tends to be a small number of nomadic people in the vicinity of the Tasiast mine. The mine itself is located 80 km northeast from the nearest permanent community of Chami.

 

The nearest industries to the site are in the towns of Chami, Boulanour, Akjoujt and Bennichab, which are respectively 80 km southwest, 120 km northwest, 150 km east-southeast and 130 km southeast from the mine site.

 

There are no permanent settlements within the vicinity of the Tasiast mine. However, within 30 km of the Tasiast mine, a number of isolated families have set up structures and reside, predominantly within three communities. Residents practice animal husbandry and other subsistence forms of livelihood. There are also nomadic groups that occasionally transit the area.

 

 
Page 177

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

21.capital and operating costs

 

This section covers Capital and Operating Costs for each phase of the Tasiast Expansion project.

 

21.1Capital Costs (Two-phased Expansion)

 

The scope of the Expansion Phase One and Two capital cost estimate includes the following:

 

·Phase One (from 8 kt/d to 12 kt/d) – Feasibility Level of Estimate

 

Gyratory Crusher

 

SAG Mill

 

New leach tanks

 

Tailings Facility

 

Improvements to ancillary facilities

 

·Phase Two (from 12 kt/d to 30 kt/d) – Pre-Feasibility Level of Estimate

 

Ball Mill

 

Leaching Facility

 

Expanded Power Plant

 

Water Supply

 

Mining Equipment

 

Improvements and additions to ancillary facilities

 

The capital cost estimates are summarized in Table 21-1.

 

 
Page 178

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 21-1: Capital Cost Estimate – Phases One and Two

 

Category

Cost (US$M)

Phase One 

(FS)

Phase Two 

(PFS)

Total
Direct Costs      
Mine Equipment - 71 71
Water Supply - 47 47
Power - 81 81
Site Infrastructure and Utilities 30 25 55
Crushing and Storage 41 - 41
Grinding (1) 46 32 78
Leaching 13 68 81
Other Processing 18 45 63
Tailings 26 11 37
Total Direct Cost 174 380 554
Indirects 48 79 127
Owner’s cost 13 17 30
Contingency 44 102 146
Taxes and duties 21 42 63
Total capital cost 300 620 920

(1) – Phases One and Two exclude the cost of a previously purchased SAG mill and ball mill respectively

 

The Phase One project execution plan assumes that $167 M will be spent in 2016 with $133 M assumed to be spent in 2017.

 

The Phase Two project execution plan assumes that $76 M will be spent in 2017, $382 M in 2018 and $162 M in 2019.

 

21.2Phase One Capital Costs - Basis of Estimate

 

The scope of the Phase One (from 8 kt/d to 12 kt/d) capital cost estimate includes, at a Feasibility Study level of estimate:

 

Gyratory Crusher

 

SAG Mill

 

Tailings Facility

 

The basis of estimate for Phase One is summarized in Table 21-2.

 

 
Page 179

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Table 21-2: Basis of Estimate – Capital Costs (Phase One)

Capital Cost Item Estimate Basis
Process Plant Equipment  
Major equipment

·     Open tenders were issued for the SAG mill (Kinross elected to use an existing mill rather than a tendered SAG) and the primary crusher

·     Budget quotations were obtained for all other major equipment items

Minor equipment ·     In-house database and costs from similar projects were used for the balance of equipment
Ductwork and chutes

·     Material Unit Costs were based on budget information and in-house data

·     MTOs were prepared by Ausenco Solutions Canada Inc. (Ausenco) and organized by WBS

Process Plant Bulk Materials and Site Works
Concrete

·     Concrete batch plant and material unit costs were based on budget pricing obtained from contractors

·     MTOs were prepared by Ausenco and organized by WBS

Structural steelwork

·     Material unit costs were based on budget pricing obtained from contractors

·     MTOs were prepared by Ausenco and organized by WBS

Process and services piping

·     Piping line list was developed for all piping ≥ 100 mm Nominal Bore (NB) and priced using budget and database costs

·     Piping < 100 NB was factored, using factors from similar-size projects (small bore pipe = 1.8 times length of total large bore pipe)

·     Fittings were factored from pipe cost based on the estimated complexity of the pipe, as calculated from the P&IDs and general arrangement layouts

Off-plot piping

·     Material unit costs were based on database pricing

·     MTOs were prepared by Ausenco and organized by WBS

Electrical

·     Budget pricing was obtained for selected electrical equipment

·     Material unit costs were based on budget pricing and from in-house data

·     MTOs were prepared by Ausenco and organized by WBS

Instrumentation and control system ·     Instrument take-offs were prepared from preliminary P&IDs

  

 
Page 180

  

 
 

  

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Capital Cost Item Estimate Basis
Earthworks

·     Material unit cost for mine waste and select fill was provided by Kinross

·     Sub-contractor rates for other earthworks activities were supplied by contractors

·     MTOs were prepared by Ausenco and organized by WBS

Tailings storage facility (TSF)

·     MTO quantities were provided by Klohn Crippen Berger

·     Material unit cost for TSF development was provided by Kinross

·     Database Pricing was obtained for the HDPE liner and geotextiles

Indirect Costs  
Construction temporary facilities and support services

·     Contractor temporary facility costs were included in contractor rates (contractor offices, power, plant & equipment)

·     Laydown areas defined and laid out by discipline

·     Existing construction office and ablutions to be relocated for EPCM team

Camp ·     Existing Tasiast camp (TTV) will not be sufficient for construction needs. Old camp to be partly refurbished to handle overflow
Catering ·     The catering rate (per day, per person) was provided by Kinross, based on the current camp operations
First Fills

·     Cost was estimated for the first fills of reagents, and the pricing was based on the reagent unit costs in the operating cost model

·     Cost was estimated for the first fills of lubricants

·     Costs for inventory and other consumables were excluded from the estimate

Spare parts ·     Major equipment spare parts defined (from quotes), minor spare parts factored
Vendor representatives ·     Calculated by package based on history from previous projects
Freight and handling of freight on site

·     Calculated on percentage by discipline and anticipated source for mechanical and electrical

·     Steel and platework freight included in contractor rates

Third-party consultants ·     Provisions included
Engineering, Procurement, & Construction Management (EPCM) ·     Cost of services estimate includes the work-hours for services, based on the estimate of deliverables and staffing plans, office expenses, travel and site assignment costs

  

 
Page 181

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Capital Cost Item Estimate Basis
Other Project Costs
Owner’s Cost ·     Includes Kinross team salaries and expenses, project insurance, office and other overhead cost, legal fees, environmental services, commissioning (including operators and operations support), training, community support. Developed by Kinross.
Contingency & Management Reserve

·     A Quantitative Risk Assessment was conducted for the project scope of work (excluding owner’s cost) covering cost and event risks

·     Contingency result was determined from a Monte Carlo simulation

Taxes and duties ·     Includes value added tax, customs duties, and withholding taxes
Escalation ·     No Escalation was calculated and is excluded from the capital cost estimate

  

21.3Phase Two Capital Costs – Basis of Estimate

 

The scope of the Phase Two (from 12 kt/d to 30 kt/d) capital cost estimate includes, at a Pre-Feasibility Study level of estimate:

 

Ball Mill
   

Leaching Facility
   

Power Plant
   

Water Supply
   

Mining Equipment
   

The basis of estimate for Phase Two is summarized in Table 21-3.

 

 
Page 182

  

 
 

  

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Table 21-3: Basis of Estimate – Capital Costs (Phase Two)

 

Capital Cost Item Estimate Basis
Mining  
Mine fleet equipment

·     Mine fleet equipment costs were based on quotes from vendors

·     Mine fleet quantities were provided by Kinross, based on mine plan requirements

·     Indirect costs were estimated by Kinross

Water Supply
Waterline from existing ground water source (Sondage)

·     Pipeline costs were escalated from actual costs of a similar line that was constructed in 2012

·     Indirects were estimated based on the requirements for managing the overall scope of work

Power Plant  
Power Plant ·     Based on EPC firm pricing tendered to market in December 2015
New CIL Process Plant Equipment
Major Equipment

·     Firm prices and budget were obtained for selected equipment

·     The 27’ Ball Mill is Kinross owned and hence did not require budgetary pricing

Minor Equipment

·     Budget prices were obtained for selected equipment

·     In-house database and costs from similar projects were used for the balance of equipment

Ductwork and chutes

·     Material unit costs were based on budget information and in-house data

·     Material take-offs (MTOs) were prepared by work breakdown structure (WBS)

New CIL Process Plant Materials and Site Works
Concrete

·     MTOs for the comminution circuit obtained from the Phase One FS

·     Preliminary MTOs developed for the 27’ ball mill

·     Preliminary MTOs based on sketches and previous projects developed for the balance of the plant

·     Concrete batch plant and material unit costs were based on budget pricing obtained from the Phase One FS

Structural steelwork

·     Material unit costs were based on budget pricing obtained from the Phase One FS estimate development

·     MTOs for the comminution circuit were obtained from the Phase One FS

·     Preliminary MTOs based on sketches and previous projects were developed for the balance of the plant

 

 
Page 183

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Capital Cost Item Estimate Basis
Process and services piping ·     Factored cost only from the installed mechanical cost on an area-by-area basis, factors used established from previous similar installations
Electrical

·     Material unit costs were based on budget pricing obtained from the Phase One FS

·     MTOs for the comminution circuit were obtained from the Phase One FS

·     Preliminary MTOs based on sketches and previous projects were developed for the balance of the plant

Instrumentation and control system

·     Process Control System pricing is based on known pricing for the existing control systems

·     MTOs for instrumentation obtained from the Phase One FS and factored for the balance of the plant

·     Budget pricing for instrumentation was obtained from the Phase One FS

Earthworks

·     Material unit cost for mine waste and select fill were obtained from the Phase One FS

·     MTOs for the comminution circuit were obtained from the Phase One FS

·     Preliminary MTOs based on sketches and previous projects were developed for the balance of the plant

Non-process buildings

·     Material unit costs are based on known costs for existing similar buildings at Tasiast, escalated as appropriate

·     MTOs were derived from previous FS studies and discussions with plant operations

Utilities

·     Material unit costs were based on known costs for existing similar buildings at Tasiast, escalated as appropriate

·     Preliminary MTOs based on sketches and previous projects were developed for the balance of the plant

Indirect Costs
Construction temporary facilities and support services

·     Includes: temporary offices, warehousing, laydown areas, temporary electrical power supply and distribution, water, sewage, information and communication technology, services such as surveying, warehousing, soil and concrete testing, structural steel torque verification and instrument calibrations

·     Laydown areas defined and laid out by discipline for the Phase One project will be re-used

·     Phase One office capacity will be re-used

Camp ·     The existing Tasiast camp (TTV) will be used with potential overflow going to the “old town” camp which will have been refurbished as part of the Phase One FS

 

 

 
Page 184

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Capital Cost Item Estimate Basis
Catering ·     The catering rate (per day, per person) was provided by Kinross based on the current camp operations
First Fills

·     Cost was estimated for the first fills of reagents, and the pricing was based on the reagent unit costs in the operating cost model

·     Cost was estimated for the first fills of lubricants

·     Costs for inventory and other consumables were excluded from the estimate

Spare parts ·     Spare parts defined (from quotes) if available, otherwise factored
Vendor representatives

·     Calculated by package based on history from previous projects

·     Steel and platework freight included in contractor rates

Freight and handling of freight on site ·     Calculated on percentage by discipline and anticipated source for mechanical and electrical
Engineering, procurement and construction management (EPCM)

·     Cost of services estimate includes work-hours for services, based on deliverables, staffing plans, office expenses, travel and site assignment costs

·     EPCM costs are based on a factor of direct capital cost

Other Project Costs
Owner’s Cost ·     Includes Kinross team salaries and expenses, project insurance, office and other overhead cost, legal fees, environmental services, commissioning (including operators and operations support), training, community support and was factored from the Phase One estimate
Contingency & Management Reserve ·     Contingency was developed based on a line by line review of the estimate
Taxes and duties ·     Includes value added tax, customs duties, and withholding taxes
Escalation ·     Escalation was calculated by Kinross and is excluded from the capital cost estimate

 

21.4Capitalized Stripping and Sustaining Capital

 

“Non-sustaining” capitalized stripping is summarized by year in Table 21-4. This is considered to be the mining required to expose the ore body. It is excluded from Table 21-1 and the calculation of the All-in Sustaining Cost metric.

 

 
Page 185

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 21-4: Annual Non-sustaining Capitalized Stripping

 

Year Non-sustaining Stripping (US$ million)
   
2016 79.9
2017 126.2
2018 157.4
2019 183.3
Total 547.0

 

The annual sustaining cost estimate is summarized in Table 21-5.

 

Table 21-5: Annual Sustaining Capital

 

Year Sustaining
Capitalized
Stripping
(US$ million)
Capitalized
Maintenance
(US$ million)
Other
(US$ million)
Total Sustaining
Capital
(US$ million)
2016 0.0 39.8 55.3 95.1
2017 0.0 23.5 28.1 51.7
2018 0.0 42.3 18.3 60.6
2019 0.0 49.3 46.7 96.0
2020 169.6 36.6 33.5 239.7
2021 96.5 57.4 19.6 173.5
2022 144.4 53.8 33.4 231.6
2023 164.6 27.0 20.3 211.9
2024 65.8 22.8 54.1 142.6
2025 0.4 10.9 29.2 40.6
2026 0.0 3.7 16.0 19.7
2027 0.0 3.6 12.4 15.9
2028 0.0 3.9 12.4 16.2
2029 0.0 1.7 12.3 14.1
2030 0.0 0.0 3.2 3.3
Total 641.4 376.3 394.8 1412.5

 

 
Page 186

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

21.5Operating Costs

 

Basis of Estimate – Operating Costs

 

The Tasiast “life of mine” operating costs are split into four primary categories: Mining, Processing, Site Administration, and Other. See Table 21-6 for a summary of the basis of estimate for the three categories.

 

Table 21-6: Basis of Estimate – Operating Costs

 

Operating
Cost
Category
Estimate Basis
Mining

Developed from first principles by:

·     Developing a detailed mine plan schedule

·     Calculating a haulage network (specific to the detailed mine plan) to generate equipment hours based on site conditions

·     Applying key cost parameter inputs such as:

○    Input prices (diesel, blasting consumables and tires) from existing site contracts

○    Productivity – either existing productivity or expected life of mine productivity

○    Headcounts – operators are based on the equipment hours; non-operator headcount is fitted to the scale of the mine (i.e. more management positions would be required as the mining rate increases)

○    Labour rates – based on 2016 budgeted labour rates

○    Fuel burn rates – based on existing site conditions

○    Maintenance costs, calculated from a zero-based maintenance model (tracks and schedules maintenance events for each piece of equipment at site)

○    Other inputs, such as tire life and drill consumables – based on existing site strategy

The following costs are allocated by department, based on each department’s headcount:

·     Tasiast Team Village (camp)

·     People Mobility

·     Nouakchott Accommodations

 

 
Page 187

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Operating
Cost
Category
Estimate Basis
Processing

Estimation methodology varied by cost component, but was primarily built from first principles, relying on a combination of:

·     Knowledge from existing operations

·     Laboratory testing completed for each phase of the expanded mill

·     Supplier reagent and consumable costs (based on current site contracts)

·     Energy consumption estimates per motor

·     Mass and water balance

 

The Tasiast dump leach is scheduled to commence decommissioning at the end of 2016. Dump leach costs are applicable for both tonnes placed in 2016, and tonnes placed before 2016, which are still being leached.

Major categories include the following, which collectively result in a processing cost estimate for the expansion scenario:

·     Power

·     Consumables (i.e. liner, grinding balls)

·     Reagents

·     Labour

·     Maintenance

·     Water

·     Laboratory

·     Plant admin

The following costs are allocated by department, based on each department’s headcount:

·     Tasiast Team Village (camp)

·     People Mobility

·     Nouakchott Accommodations

Site Administrative

Bottom-up approach applying labour, and other costs to various areas including:

·     Administration (finance, supply chain, security, IT, HR, etc…)

·     Heath, safety and environment:

·     Training

·     Site services

The following costs are allocated by department, based on each department’s headcount:

·     Tasiast Team Village (camp)

·     People Mobility

·     Nouakchott Accommodations

 

 
Page 188

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Operating
Cost
Category
Estimate Basis
Other

This category captures all operating costs not considered in the three categories above, including:

·     Franco Nevada Royalty (2% of Revenue)

·     Government Royalty (3% of Revenue)

·     World Gold Council Fee

·     VAT paid

·     Import IMF paid

 

Operating cost estimates are not escalated over time, given that the financial model is built assuming real values.

 

Life of Mine Estimates – Operating Costs

 

Operating cost estimates are shown in Table 21-7.

 

Table 21-7: Operating Cost Estimates (January 1, 2016 forward)

 

Operating Cost Unit

Phase One in operation

2018-20191

Phase Two in operation

2020-2030

Life-of-Mine Average

2016-2030

Mining (incl. stripping) US$/t mined2 1.98 2.37 2.25
Processing (Mill) US$/t processed 18.59 15.16 15.77
Processing (Dump Leach) US$/t processed3 N/A N/A 33.34
Site Admin million US$/a 61 48 55
Other US$/oz sold 70 69 70

 

1. Includes the 6-month Phase Two ramp-up (July 2019 to December 2019)

2. Excludes capitalized maintenance.

3. Limited tonnes placed on dump leach in 2016. Dump leach is decommissioned at the end of 2016.

 

 
Page 189

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

22.economic analysis

 

The economics of the Tasiast Expansion Project were evaluated using a real (non-escalated), after-tax discounted cash flow (DCF) model on a 100% project equity (unlevered) basis. Unless otherwise stated, all economic parameters are shown on an absolute basis (not incremental to existing operations). Production, revenues, operating costs, capital costs and taxes were considered in the financial model. The main economic assumptions are a US$1,200/oz gold price and a 5% discount rate.

 

The valuation date for the financial analysis was set for April 1, 2016. All cash flows assumed for the purposes of this study are from this date onward.

 

The cash flow analysis was used to estimate the economics of the two-phased 30 kt/d carbon-in-leach (CIL) plant expansion scenario. This scenario assumes that Phase One of the expansion (12kt/d mill) is at full capacity in Q1 2018, with Phase Two of the expansion (30kt/d mill) at full capacity on Jan 1, 2020. Note the approval of the Phase Two expansion is dependent on further study, macroeconomic conditions and availability of funds.

 

22.1Key Assumptions

 

Key assumptions in the financial model are summarized in Table 22-1.

 

Table 22-1: Financial model key assumptions

 

Parameter Assumption Description
General    
CIL plant throughput options 8,000t/d (current) to 12,000t/d (Ph1) to 30,000t/d (Ph2) The expansion scenario involves a 2-phased expansion with the existing mill facility (8kt/d) expanded to 12kt/d over the first phase, and then expanded to 30kt/d over the second phase.
Dump leach and adsorption, desorption and recovery timing Detailed recovery curve

This is the assumed recovery timing of the gold when the ore has been placed on the dump leach.

 

Recovery timing assumptions were estimated by the current site operations in conjunction and affect 2016 economics only.

Power option (for expansion option) HFO on-site The Phase One expansion uses the existing power supply at site (HFO & LFO), with Phase Two requiring an upgraded HFO power plant.
Mining years 11 years The number of years of mining operations has been set by the mineable inventory.

 

 
Page 190

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Parameter Assumption Description
Processing years 15 years The number of years of processing operations was set by the mineable inventory and stockpiles.
Currency US dollars & Mauritanian Ouguiya The model was constructed as a dual-currency model using US dollars (US$) and Mauritanian Ouguiya (MRO). All model output is in US$. ~10-20% of operating cost in in MRO.
Foreign Exchange Rate 300 MRO/US$ Foreign exchange rate was held constant over the life of mine
Inflation None –
real basis
All projected revenue and costs were assumed to be in April 1, 2016 real terms, with no inflation applied.
Starting basis April 1, 2016
go forward
All economic analyses were done on an April 1, 2016, “go-forward” basis. Spending before this date was treated as sunk, and was not considered in the analysis, except for opening balances for tax depreciation.
Capital structure Unlevered The calculated financial results assume the project will be internally financed. No debt financing or interest payments were assumed.
Discount rate 5% real All the NPVs shown in this report were calculated using a discount rate of 5%. Sensitivity analysis has been completed for 0% and 10% discount rates.
Commodity Prices
Gold US$1,200/oz Commodity prices were assumed to be constant over the DCF timeframe.
Oil (West Texas Intermediate [WTI]) US$45/bbl Commodity prices were assumed to be constant over the DCF timeframe.
Refining, Transport and Other Charges
Refining charge US$ 0.22/oz Au A refining charge of US$ 0.22/oz poured
Doré transportation US$ 55k/month A doré transportation charge was applied as a fixed value of $55k/month
World Gold Council Fees US$ 1.00/oz Au A world gold council fee of US$1.00/oz was applied

 

 
Page 191

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

  

Parameter Assumption Description
Capital and Operating Costs
Capital expenditures (CAPEX) Described in Section 21.1.

Spending before April 1, 2016, is treated as a sunk cost and is not considered in the analysis, except for opening balances for tax depreciation.

 

Sustaining capital costs: portions were derived using zero-based costing where possible. Provisional estimates for LOM values were made otherwise.

Core Credit US$ 67 million life of mine Core Credits represent the gain on disposal of fixed assets related to the replaced part in a capitalized maintenance event. Rates are as observed at the current operating site.
Operating costs (OPEX) Described in Section 21. Described in Section 21.
Closure and rehabilitation costs US$ 69 million Total closure costs were estimated at US$ 69 million for the expansion scenario. The majority of the costs were assumed to be incurred in the three years immediately following the completion of processing operations.
Working Capital
Accounts receivable N/A Opening AR balance is zero, with no changes over life of mine.
Pre-paid expenses Fluctuates over Life of Mine Balance of account expected to fluctuate (based on operating costs) over life of mine.
Supplies Inventory Fluctuates over Life of Mine Balance of account expected to fluctuate (based on operating costs) over life of mine.
Accounts payable & accrued liabilities Fluctuates over Life of Mine Balance of account expected to fluctuate (based on operating costs) over life of mine.
Stockpiles Expensed in the year that tonnes are processed For tax purposes, mining costs were expensed in the year that the tonnes were processed. Mining cost associated with stockpiled tonnes was tracked in working capital and considered a cash cost in the year expensed.
Finished Goods Inventory 30 days Assume that produced ounces take 30 days to sell.

 

 
Page 192

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Parameter Assumption Description
Taxes and Duties
Governing convention 2002 Mining Convention Unless otherwise noted, the economic evaluation in this feasibility study was assumed to be governed by the Tasiast Mauritanie Ltd. S.A. (TMLSA) 2002 Mining Convention.
Income taxes 25% Income taxes were included in this financial analysis with a marginal tax rate of 25%. The annual tax paid in the model is the higher of the income tax or the minimum tax (see below).
Minimum tax 1.25% The minimum tax was calculated on total metal revenues. The higher of the income tax or the minimum tax is the given tax paid in any year.
Royalties 5% total Royalties were forecasted to be constant over the mine life at 3% of revenue to the Mauritanian government and 2% to a third party (Franco-Nevada Corporation).
Import duties 5% Import duties for all non-resident goods were included in CAPEX and OPEX estimates. (Note that as part of the TMLSA Mining Convention, fuels are assumed to be exempt from import duties.)
Withholding tax 17.6% Withholding tax is applicable to all non-resident services.
VAT 16% VAT is applicable to all resident goods and services
VAT Exemption 50% Assume that VAT is only paid on 50% of spend on resident goods and services
VAT Recovery 30% Assume that 30% of VAT paid is recovered after 36 months
Tax loss carry forwards 5 years Tax-loss carry forwards expire after five years.
Non-deductible expenses Mauritanian Tax Code Tax deductibility of general and administrative costs are based on an interpretation of the Mauritanian tax code and the TMLSA Mining Convention
Undepreciated Assets Opening Balance US$ 1,249 million Sunk capital costs that have not yet been depreciated for taxation purposes
Depreciation of Fixed Assets Varies from 2 to 10 years depending on asset class For most assets, depreciation was calculated on a straight-line basis. Depreciation was calculated according to cash-tax depreciation rates and it is always applied in the year it is incurred. Depreciation-generated losses can be carried forward indefinitely and applied against future earnings. Accelerated depreciation is applied if the mine life is less than the asset life computed using the prescribed straight line rates.

 

 
Page 193

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

22.2Presentation of Results (30 kt/d)

 

The results of the financial analysis, with sensitivities to gold price and discount rate assumptions, are shown in Table 22-2, based on $1,200/oz gold, a real discount rate of 5%, and an oil price of $45/bbl except as stated in the last row. Annual life-of-mine cash flows are shown in Table 22-3.

 

With a 5% discount rate and an oil price of $45/bbl, the project shows favourable economics at a $1,200/oz gold price.

 

Table 22-2: Financial analysis results and sensitivities (April 1, 2016 forward)

 


Financial metric
Unit Gold Price (US$/oz)
1,100 1,200 1,300 1,500
NPV at 0% discount rate US$ billion 1.10 1.66 2.20 3.29
NPV at 5% discount rate US$ billion 0.48 0.89 1.27 2.06
NPV at 10% discount rate US$ billion 0.10 0.40 0.69 1.28
Internal rate of return % 12 17 22 33
Payback year (undiscounted) Year 2024 2022 2022 2021
NPV at 5% discount rate; $65/bbl (WTI) Oil US$ billion 0.34 0.74 1.14 1.91

 

 
Page 194

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 22-3: Life of Mine Cash Flows

 

Year

Cash flow, $1,200/oz Au

(US$M)

Gold recovered (Moz)
2016 (Jan-Dec) (316) 195
2017 (270) 253
2018 (399) 339
2019 (165) 413
2020 185 645
2021 510 975
2022 434 953
2023 258 666
2024 186 583
2025 541 940
2026 411 674
2027 167 353
2028 60 259
2029 47 259
2030 27 138
2031+ (65) 0


 

Cash cost and all-in sustaining cost ranges are shown in Table 22-4.

 

Table 22-4: Cash Cost per ounce and All-in Sustaining Cost per ounce

 

Cost Metric Unit 2016-19 2020-26 2027-30
Cash Cost US$/oz
produced
710 462 941
All-in Sustaining Cost US$/oz
produced
972 666 999

 

Sensitivity Analysis – oil price (30 kt/d)

 

The sensitivities of NPV and IRR to oil price are shown in Table 22-5.

 

 
Page 195

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 22-5: Project Economics Sensitivity to Oil Price

 


Financial metric

Unit WTI Oil Price (US$/bbl)
30 35 40 45 50 55 60 65
NPV at 5% discount rate US$
billion
0.99 0.96 0.92 0.89 0.85 0.82 0.78 0.74
Internal rate of return % 19 18 18 17 17 16 16 15

 

Sensitivity Analysis – Taxes

 

The economic analysis has assumed the application of a VAT exemption for qualifying local supplies. If this does not occur, there would be a net impact of ($45M) to project NPV and (0.9%) to project IRR.

 

The economic analysis has assumed that RIM will meet its financial obligations to refund qualifying VAT amounts. If that does not occur, there would be a net impact of ($47M) to project NPV and (0.8%) to project IRR.

 

If neither the VAT exemption nor the VAT recoveries are achieved (as planned), there would be a net impact of ($110M) to project NPV and (1.9%) to project IRR. Note that the NPV impact of the two sensitivities above is greater than the sum of its parts when put together.

 

The economic analysis makes assumptions regarding the tax deductibility of general and administrative costs. It has been assumed that G&A is deductible within the confines of our interpretation of the Mauritanian tax code & the TMLSA Mining Convention. If the government makes a different interpretation of the tax code, it will have an effect on project economics.

 

Sensitivity Analysis – Dilution

 

The sensitivity of NPV to potential additional ore dilution is summarized in Table 22-6.

 

Table 22-6: NPV Sensitivity to Dilution

 


Dilution (%)
NPV (US$ billion) Change in NPV (US$ billion)
2 $0.87 ($0.2)
4 $0.84 ($0.5)
6 $0.80 ($0.9)
8 $0.77 ($1.2)
10 $0.72 ($1.7)

 

 
Page 196

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

22.3Sensitivity Analysis – Phase One only

 

In a scenario where the Phase Two expansion is not approved, Tasiast would continue to operate as a 12 kt/d operation over the life of mine. The sensitivities in Table 22-7 show that operating the 12 kt/d plant would be economically viable at a variety of gold prices. Table 22-7 is based on an oil price of $45/bbl except as stated in the last row.

 

Table 22-7: Financial analysis results and sensitivities (Phase One only, April 1, 2016 forward)

 

Financial metric Unit Gold Price (US$/oz)
1,100 1,200 1,300 1,500
NPV at 0% discount rate US$ billion 0.76 1.16 1.55 2.31
NPV at 5% discount rate US$ billion 0.35 0.64 0.91 1.45
NPV at 10% discount rate US$ billion 0.10 0.32 0.52 0.92
Internal rate of return % 13 20 26 40
Payback year (undiscounted) Year 2024 2022 2021 2020
NPV at 5% discount rate; $65/bbl (WTI) Oil US$ billion 0.24 0.53 0.80 1.35

 

The mine plan remains the same for 2016 and 2017 whether or not Phase Two is implemented. Following 2018, should Phase Two not be implemented, the 2018 forward mine plan would move significantly fewer tonnes per year (60 to 70 million tonnes per year).

 

The processing facility would use the equipment installed during Phase One, with the remainder of the processing capacity leveraging the existing facility at site (i.e. ball mills, leach tanks, etc.). Refer to Figure 17-5 for a detailed 12,000 t/day flowsheet. See Table 22-8 for a summary of life-of-mine production and cost figures for the Phase One only sensitivity.

 

 
Page 197

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Table 22-8: Life of Mine Cost and Production Summary (Phase One only, January 1, 2016 forward)

 

Operational metric Unit 2016-17 2018-19 2020-27 2028-33
    Average over time period
Mining cost US$/t mined 2.15 2.25 2.51 N/A1
Processing Cost US$/t processed 24.50 20.15 20.69 20.60
Site Admin US$ million/yr 76 58 49 36
Sustaining Capital (excl. Stripping) US$ million/yr 74 55 43 6
Cash Cost US$/oz 967 566 530 944
All-in Sustaining Cost US$/oz 1304 725 769 997
Average grade milled g/t 2.5 2.8 3.2 1.3
Average process recovery % 93% 93% 93% 92%
Average strip ratio unitless 16 9 7 N/A
    Total over time period
Tonnes Mined Mt 134 133 379 0
Gold Produced koz 448 729 3,362 896
Cash Flow US$ (512) 170 1,274 1802
1.In 2028-2033, stockpile material is moved at a total cost of $57 M.

2.Includes 2034+ reclamation and closure costs.

 

 
Page 198

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

23.adjacent properties

 

There are no adjacent properties to be discussed in this Technical Report.

 

 
Page 199

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

24.Other relevant data and information

 

No additional information or explanation is necessary to make this Technical Report understandable and not misleading.

 

 
Page 200

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

25.INTERPRETATION AND conclusions

 

Tasiast is viewed as a long-term strategic asset for Kinross, located in a district that is believed to have significant future potential. The phased expansion project is believed to provide an opportunity to capitalize on the full potential of the operation and to solidify Tasiast as a low cost, long life asset within the company’s portfolio.

 

The project economics, as stated at a 5% discount rate and a $1,200 base case gold price, are robust and offer significant potential.

 

Kinross is confident in the technical and economic assessment presented in this Technical Report. However, the results of this Technical Report are subject to many risks including, but not limited to: commodity and foreign exchange assumptions (particularly relative movement of gold and oil prices), unanticipated inflation of capital or operating costs, significant changes in equipment productivities, geotechnical assumptions in pit designs, ore dilution or loss, throughput and recovery rate assumptions, availability of financing and changes in modelled taxes.

 

 
Page 201

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

26.RECOMMENDATIONS

 

It is recommended that Kinross proceed with the Phase One expansion to a 12 kt/d plant and conduct a Feasibility Study of the 30 kt/d plant, to further refine the design that was summarized in this report based on the 30 kt/d Pre-feasibility Study.

 

 
Page 202

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

27.references

 

Bailly, L., Lerouge, C., Bouchot, V., 1999. Etude petrographique et metallographique d’echantillons des sondages recoupant “La colonne Piment” de la Branche Est du Prospect C6-9, sillon D’Aouéouat (Tasiast, Mauritanie). Internal unpublished report (April, 1999).

 

Blake, C., 2011a. Mineralogical characterisation of five gold-bearing samples from the Tasiast mine, Mauritania for Kinross Gold Corporation. Internal unpublished report (February, 2011).

 

Blake, C., 2011b. Mineralogical characterisation of seven gold-bearing composite samples from the Tasiast Mine, Mauritania for Kinross Gold Corporation. Internal unpublished report (September, 2011).

 

Canadian Institute of Mining, Metallurgy and Petroleum (CIM), 2014. CIM Standards for Mineral Resources and Mineral Reserves, Definitions and Guidelines: Canadian Institute of Mining, Metallurgy and Petroleum, May 10, 2014.

 

Chartier, D., 2013. Draft of Sampling and Data Verification Sections for Tasiast Feasibility Study. Memo dated December 4, 2013.

 

Davies, B., 2011a. West Branch & the Tasiast gold system. Internal unpublished report (February, 2011).

 

Davies, B., 2011b. Aouéouat Greenstone Belt and adjacent areas: Summary notes to accompany a new geological map. Internal unpublished report (September, 2011).

 

Demers, P., Gauthier, D., Kroon, A.S., and Lafleur P-J., 2004. Technical Report on the Tasiast Gold Project, Islamic Republic of Mauritania: unpublished technical report prepared by SNC Lavelin for Defiance Mining Corporation Limited, effective date 27 May 2004.

 

Fabre, J., 2005. Géologie du Sahara occidental et central. Série/Reeks: Tervuren African Geosciences Collection, MRAC Tervuren, Belgique, 572 p.

 

Goodman, S., 2011. Structural Model of the Tasiast Mine, Mauritania. Internal unpublished report (October, 2011).

 

Golder Associates, 2004. Preliminary Pit Slope Design, Tasiast Project, Mauritania, Report 03-117-073. Unpublished Technical Report, June 2004.

 

Golder Associates, 2014. Geotechnical Study in Support of West Branch Expansion, Kinross Tasiast, Report 12514150422.502/A.0. Unpublished Technical Report, June 2014.

 

 
Page 203

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Guibal, D., Uttley, P., de Visser, J., and Warren, M., 2003. Independent Technical Assessment Report on the Tasiast Project, Mauritania; Report Prepared for Midas Gold plc. and Geomaque Explorations Ltd: unpublished technical report prepared by SRK Consulting for Midas Gold plc. and Geomaque Explorations Ltd, effective date 4 March 2003.

 

Heberlein, D., 2013. QAQC Update (August 2012). Internal report prepared for Tasiast Mauritanie Ltd S. A.; a division of Kinross Gold Corp. Dated September 4, 2013.

 

Heberlein, D., 2011. QAQC update – laboratory duplicate results (Oct-Dec, 2011). Internal unpublished report (October, 2011).

 

Holman K. and Castro C., 2013. Internal Exploration Database Verification: Tasiast Gold Mine. Internal Kinross report dated November 7, 2013.

 

Hyde, R., 2003. Tasiast Gold Project, Review of Sampling Procedures and QAQC Analysis for Midas Gold plc.: RSG Global Report No. TAS003, 42 pages (unpublished).

 

JKTech, undated. JK Drop Weight Test, “In Detail” white paper by JKTech Laboratory Services.

 

Journel, A. G. and Huijbregts, C. J, 1978. Mining Geostatistics, Academic Press.

 

Key, R.M., Loughlin, S.C., Gillespie, M., Del Rio, M. Horstwood, M.S.A., Crowley, Q.G., Darbyshire, D.P.F., Pitfield, P.E.J., & Henne, P.J., 2008. Two Mesoarchaean Terranes in the Reguibat Shield of NW Mauritania: Geological Society, London, Special Publications 2008, v. 297, p. 33-52.

 

Larson, L.T., 2011. Petrographic report. Internal unpublished report (March, 2011).

 

LaSource-BRGM (Bureau de Recherches Géologique et Minières), 1997. Permis Tasiast – Mauritanie. Etude d’indices et prospection d’anomalies aurifères. Rapport N 2534/LaSource 10.059.48 pages (unpublished).

 

Leitch, C., 2010. Petrographic report on 18 samples from Archean greenstone au deposit. Internal unpublished report (October, 2010).

 

Leroux, D.C. and Puritch, E., 2003. Technical Report and Resource Estimation on the Tasiast Gold Project Islamic Republic of Mauritania for Defiance Mining Corporation: unpublished technical report prepared by ACA Howe for Defiance Mining Corporation, effective date 10 October 2003.

 

Leroux, D.C., Roy, W.D., and Orava D., 2007. Technical Report on the Tasiast Gold Project Islamic Republic of Mauritania for Red Back Mining Inc.: unpublished technical report prepared by ACA Howe for Red Back Mining Inc., effective date 20 July 2007.

 

 
Page 204

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Maurin, G., Bronner, G., Le Goff, E., and Chardon, D., 1996. Châmi – Notice explicative de la carte géologique à 1:200,000: République Islamique de Mauritanie Projet FED no. 7 ACP MAU 009 (MAU 7002), Prospection aurifère dans le Tasiast – Tijirit, N2459.

 

Pollard, P., 2011. Hydrothermal Alteration and Mineralization in the Lower West Branch Zone, Tasiast Gold Mine, Mauritania: unpublished technical report prepared for Kinross Gold.

 

Schlumberger, 2014. Hydrogeological Characterisation of the West Branch Pit, Tasiast, Mauritania. Technical Report Ref 52116/R1. January 2014.

 

Schofield, D., Horstwood. M.S.A., Pitfield, P.E.J., Crowley, Q.G., Wilkinson, A.F. & Sidaty, H.C.O., 2006. Timing and kinematics of Eburnean tectonics in the central Reguibat Shield, Mauritania. Journal Geological Society London, 163, 549-560.

 

Scott Wilson 2008a. Tasiast Gold Project, Environmental Impact Study, Addendum II of IV, Environmental Impact Review of Tailings Storage Facility: Report prepared by Scott Wilson Limited for Tasiast Mauritania Limited S.A. for submission to Mauritanian Government, February 2008.

 

Scott Wilson, 2008b. Tasiast Gold Project, Environmental Impact Study, Addendum III of IV, Environmental Management Plan: Report prepared by Scott Wilson Limited for Tasiast Mauritania Limited S.A. for submission to Mauritanian Government, February 2008.

 

Scott Wilson, 2008c. Tasiast Gold Project, Environmental Impact Study, Addendum IV of IV Preliminary Rehabilitation and Closure Plan: Report prepared by Scott Wilson Limited for Tasiast Mauritania Limited S.A. for submission to Mauritanian Government, February 2008.

 

Scott Wilson, 2009. Tasiast Gold Project, Environmental Impact Study for New Developments.

 

Scott Wilson, 2010. Tasiast Gold Mine West Branch Development: Environmental Impact Assessment.

 

Strashimirov, S., 2010. Petrological and mineralogical studies of 10 samples from Mauritania. Internal unpublished report (August, 2010).

 

Stuart, H., 2008. Technical Report on the Tasiast Gold Mine Islamic Republic of Mauritania for Red Back Mining Inc.: unpublished technical report prepared for Red Back Mining Inc., effective date 24 May 2008.

 

Stuart, H., 2009. Technical Report on the Tasiast Gold Mine Islamic Republic of Mauritania for Red Back Mining Inc.: unpublished technical report prepared for Red Back Mining Inc., effective date 8 May 2009.

 

 
Page 205

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

Stuart, H., 2010. Technical Report on the Tasiast Gold Mine Islamic Republic of Mauritania for Red Back Mining Inc.: unpublished technical report prepared for Red Back Mining Inc., effective date 6 September 2010.

 

 
Page 206

 

 
 

 

(KINROSS LOGO) 

Kinross Gold Corporation

Tasiast Project

Mauritania

NI 43-101 Technical Report

 

28.DATE AND SIGNATURE PAGE

 

The effective date of this Technical Report entitled “Kinross Gold Corporation, Tasiast Project, Mauritania, NI 43-101 Technical Report” is March 30, 2016.

 

 

 

 

 

 

“Signed and sealed”

 

John Sims, AIPG Certified Professional Geologist

 

Dated March 30, 2016

 

 
Page 207