Restructuring
6 Months Ended
Aug. 30, 2025
Restructuring and Related Activities [Abstract]  
Restructuring Restructuring
During the fourth quarter of fiscal 2024, we announced strategic actions to streamline our business operations, enable a more efficient cost model, and better position the Company for profitable growth (referred to as “Project Fortify”). Project Fortify primarily impacted the Architectural Metals Segment and included:
Eliminating certain lower-margin product and service offerings, enabling consolidation into a single operating entity.
Transferring production operations from the Company’s facility in Walker, Michigan, to the Company’s facilities in Monett, Missouri and Wausau, Wisconsin.
Simplifying the segment’s brand portfolio and commercial model to improve flexibility, better leverage the Company’s capabilities, and enhance customer service.
Additionally, the Company implemented actions to optimize processes and streamline resources in its Architectural Services Segment and Corporate and Other. The Company completed Project Fortify during the fourth quarter of fiscal 2025 and incurred a total of $16.7 million of restructuring charges, which led to an annualized pre-tax cost savings of approximately $14 million.
On April 23, 2025, we announced a second phase of Project Fortify (referred to as "Project Fortify Phase 2" or "Phase 2") to drive further cost efficiencies, primarily in the Architectural Metals and Architectural Services Segments. Phase 2 focuses on further optimizing our operating footprint and aligning resources to enable a more effective operating model. We expect to incur approximately $24 million to $26 million of pre-tax charges associated with Phase 2. The total charges are expected to include the following:
$9 million to $10 million of severance and employee related costs;
$5 million to $6 million of contract termination costs; and
$9 million to $10 million of other expenses.
We expect the actions associated with Phase 2 to be substantially completed by the end of the fourth quarter of fiscal 2026 and expect them to deliver annualized pre-tax cost savings of approximately $13 million to $15 million.
During the second quarter of fiscal 2026, we incurred $3.1 million of pre-tax costs associated with Phase 2, of which $3.0 million is included in cost of sales and $0.1 million is included within SG&A. During the first six months of fiscal 2026, we incurred $18.5 million of pre-tax costs associated with Phase 2, of which, $9.9 million is included in cost of sales and $8.6 million is included within SG&A. For the six months ended August 30, 2025, SG&A charges include a $5.0 million non-cash intangible asset impairment charge in the Architectural Services segment and a $2.6 million non-cash asset write-off and other charges in Corporate and Other.
The table below reflects the pretax impact of Project Fortify for the quarters ended August 30, 2025, and August 31, 2024, respectively.
(In thousands)
Architectural Metals
Architectural Services
Corporate and Other
Total
August 30, 2025
Termination benefits$— $476 $— $476 
Contract termination costs201 1,659 — 1,860 
Other restructuring charges154 623 10 787 
Total restructuring charges$355 $2,758 $10 $3,123 
August 31, 2024
Termination benefits$271 $172 $$448 
Contract termination costs108 — — 108 
Other restructuring charges537 86 — 623 
Total restructuring charges$916 $258 $$1,179 
The table below reflects the pretax impact of Project Fortify for the six months ended August 30, 2025, and August 31, 2024, respectively.
(In thousands)
Architectural Metals
Architectural Services
Corporate and Other
Total
August 30, 2025
Termination benefits $805 $6,424 $— $7,229 
Contract termination costs802 1,932 — 2,734 
Other restructuring charges218 5,650 2,641 8,509 
Total restructuring charges$1,825 $14,006 $2,641 $18,472 
August 31, 2024
Termination benefits$573 $172 $129 $874 
Contract termination costs108 — — 108 
Other restructuring charges1,233 86 — 1,319 
Total restructuring charges$1,914 $258 $129 $2,301 
The following table summarizes our restructuring related accrual balances included within accrued payroll and related benefits and other current liabilities in the consolidated balance sheets. All remaining accrual balances are expected to be paid within fiscal 2026.
(In thousands)Architectural Metals Architectural ServicesCorporate and OtherTotal
Balance at March 1, 2025$1,286 $650 $511 $2,447 
Restructuring expense1,567 6,050 10 7,627 
Payments(965)(2,872)(329)(4,166)
Balance at August 30, 2025$1,888 $3,828 $192 $5,908 
The charges presented in the roll forward of our restructuring accruals do not include items charged directly to expense as incurred, as those items are not reflected in accrued payroll and related benefits and other current liabilities in the consolidated balance sheets.