Regulatory matters Regulatory matters
The Company regularly reviews the need for electric and natural gas rate changes in each of the jurisdictions in which service is provided. The Company files for rate adjustments to seek recovery of operating costs and capital investments, as well as reasonable returns as allowed by regulators. Certain regulatory proceedings and cases may also contain recurring mechanisms that can have an annual true-up. Examples of these recurring mechanisms include: infrastructure riders, transmission trackers, renewable resource cost adjustment riders, as well as weather normalization and decoupling mechanisms. The following paragraphs summarize the Company's significant open regulatory proceedings and cases by jurisdiction including updates to those reported in the 2023 Annual Report and should be read in conjunction with previous filings. The Company is unable to predict the ultimate outcome of these matters, the timing of final decisions of the various regulators and courts, or the effect on the Company's results of operations, financial position or cash flows.
MTPSC
On July 15, 2024, Montana-Dakota filed a request with the MTPSC for a natural gas general rate increase of approximately $9.4 million annually or 11.1 percent above current rates. The requested increase is primarily to recover investments in system upgrades and pipeline replacement projects enhancing the reliability, safety and integrity of the natural gas system, as well as increased costs to operate and maintain that system. This matter is pending before the MTPSC.
NDPSC
On November 1, 2023, Montana-Dakota filed a request with the NDPSC for a natural gas general rate increase of approximately $11.6 million annually or 7.5 percent above current rates. The requested increase is primarily to recover investments in system upgrades and pipeline replacement projects enhancing the reliability, safety and integrity of the natural gas system, as well as increased costs to operate and maintain that system. On December 13, 2023, the NDPSC approved an interim rate increase of approximately $10.1 million annually or 6.5 percent above current rates, subject to refund, for service rendered on and after January 1, 2024. This matter is pending before the NDPSC.
SDPUC
On August 15, 2023, Montana-Dakota filed a request with the SDPUC for an electric general rate increase of approximately $3.0 million annually or 17.3 percent above current rates. The requested increase is primarily to recover investments in production, transmission and distribution facilities and the associated depreciation, operation and maintenance expense and taxes associated with the increased investment. On January 26, 2024, Montana-Dakota filed a notice of intent to implement interim rates of $2.7 million annually or 15.4 percent above current rates. The interim rates, subject to refund, were effective March 1, 2024. On July 26, 2024, an all-party settlement agreement was filed reflecting an annual revenue increase of $1.4 million or 8.6 percent overall. The reduction from the original filing includes changes to the overall return, lower depreciation rates and other settled items. This matter is pending before the SDPUC.
On August 15, 2023, Montana-Dakota filed a request with the SDPUC for a natural gas general rate increase of approximately $7.4 million annually or 11.2 percent above current rates. The requested increase is primarily to recover investments in system upgrades and pipeline replacement projects enhancing the reliability, safety and integrity of the natural gas system, as well as increased costs to operate and maintain that system. On January 26, 2024, Montana-Dakota filed a notice of intent to implement interim rates, subject to refund, which were effective March 1, 2024. On July 26, 2024, an all-party settlement agreement was filed reflecting an annual revenue increase of $5.4 million or 8.1 percent overall. The reduction from the original filing includes lower depreciation rates, changes to the overall return and other settled items. This matter is pending before the SDPUC.
WUTC
On March 29, 2024, Cascade filed a request with the WUTC for a multi-year natural gas general rate increase of $43.8 million or 11.6 percent effective March 1, 2025 and $11.7 million or 2.8 percent to be effective March 1, 2026. Multi-year filings are now required by Washington law that went into effect on January 1, 2022. The requested increase is primarily to recover infrastructure investments necessary to provide safe and reliable service and higher operating costs due to inflation. This matter is pending before the WUTC.