XML 72 R63.htm IDEA: XBRL DOCUMENT v3.2.0.727
Environmental matters (Details 2) - Jun. 30, 2015 - USD ($)
Total
Portland Harbor Site [Member]  
Site Contingency [Line Items]  
Environmental matters investigative costs $ 70,000,000
Eugene, OR Manufactured Gas Plant Site [Member]  
Site Contingency [Line Items]  
Site contingency, low estimate, loss exposure 500,000
Site contingency, high estimate, loss exposure $ 11,000,000
Estimated proportional share of cleanup liability 50.00%
Accrual for environmental loss contingencies $ 1,700,000
Bremerton, WA Manufactured Gas Plant Site [Member]  
Site Contingency [Line Items]  
Site contingency, low estimate, loss exposure 340,000
Site contingency, high estimate, loss exposure 6,400,000
Accrual for environmental loss contingencies 12,300,000
Bellingham, WA Manufactured Gas Plant Site [Member]  
Site Contingency [Line Items]  
Site contingency, loss exposure not accrued, best estimate $ 8,000,000