Regulatory matters and revenues subject to refund
3 Months Ended
Mar. 31, 2015
Regulated Operations [Abstract]  
Regulatory matters and revenues subject to refund
Regulatory matters and revenues subject to refund
On August 11, 2014, Montana-Dakota filed an application with the MTPSC for a natural gas rate increase. Montana-Dakota requested a total increase of approximately $3.0 million annually or approximately 3.6 percent above current rates. The requested increase includes the costs associated with the increased investment in facilities, including ongoing investment in new and replacement distribution facilities, depreciation and taxes associated with the increased investment as well as an increase in Montana-Dakota's operation and maintenance expenses. On February 3, 2015, the MTPSC approved an interim increase of $2.0 million or approximately 2.3 percent, subject to refund, to be effective with service rendered on and after February 6, 2015. On March 18, 2015, Montana-Dakota and the Montana Consumer Counsel filed a settlement agreement that resolved all issues of the application and reflected a natural gas rate increase of $2.5 million annually or approximately 3.0 percent. An amended stipulation reflecting minor changes in rate design was submitted on March 24, 2015. On April 28, 2015, the MTPSC approved the settlement rates, which are expected to be effective with service rendered on and after May 11, 2015.

On October 3, 2014, Montana-Dakota filed an application with the WYPSC for a natural gas rate increase. Montana-Dakota requested a total increase of approximately $788,000 annually or approximately 4.1 percent above current rates. The requested increase includes the costs associated with the increased investment in facilities, including ongoing investment in new and replacement distribution facilities and the associated operation and maintenance expenses, depreciation and taxes associated with the increase in investment. On April 16, 2015, Montana-Dakota and the Wyoming Office of Consumer Advocate filed a stipulation and agreement that resolved all issues between the parties and reflected a natural gas rate increase of $501,000 annually or approximately 2.6 percent. The WYPSC has scheduled a hearing for this matter on May 19, 2015.

On November 14, 2014, Montana-Dakota filed an application with the NDPSC for approval to implement the rate adjustment associated with the electric generation resource recovery rider approved by the NDPSC on August 20, 2014. On January 7, 2015, the NDPSC approved the rate adjustments of $5.3 million annually to be effective with service rendered on and after January 9, 2015.

On December 22, 2014, Montana-Dakota filed an application for advance determination of prudence and a certificate of public convenience and necessity with the NDPSC for the Thunder Spirit Wind project. This project will provide energy, capacity and renewable energy credits to Montana-Dakota's electric customers in North Dakota, Montana and South Dakota. The NDPSC has scheduled a hearing for this matter on May 14, 2015.

On February 6, 2015, Montana-Dakota filed an application with the NDPSC for a natural gas rate increase. Montana-Dakota requested a total increase of approximately $4.3 million annually or approximately 3.4 percent above current rates. The requested increase includes the costs associated with the increased investment in facilities, including ongoing investment in new and replacement distribution facilities, depreciation and taxes associated with the increased investment as well as an increase in Montana-Dakota's operation and maintenance expenses. Montana-Dakota requested an interim increase of $4.3 million or 3.4 percent, subject to refund, which was approved by the NDPSC on March 11, 2015, effective with service rendered on or after April 7, 2015. A technical hearing has been scheduled for July 20-21, 2015. This matter is pending before the NDPSC.

On March 31, 2015, Cascade filed an application with the OPUC for a natural gas rate increase. Cascade requested a total increase of approximately $3.6 million annually or approximately 5.1 percent above current rates. The requested increase includes the costs associated with the increased investment in facilities, including ongoing investment in new and replacement distribution facilities and the associated operation and maintenance expenses, depreciation and taxes associated with the increase in investment, as well as environmental remediation expenses.

On April 10, 2015, Montana-Dakota submitted a request to the NDPSC to update the environmental cost recovery rider to reflect actual costs incurred through February 2015 and projected costs through June 2016 related to the recovery of Montana-Dakota's share of the costs resulting from the environmental retrofit required to be installed at the Big Stone Station. The request also includes costs associated with the environmental upgrade required at the Lewis & Clark Station to comply with the EPA's MATS rule. The filing also requests a revision to the environmental cost recovery rider that will allow future recovery of ongoing reagent costs required to meet environmental standards as a monthly adjustment. A total of $8.1 million is requested to be recovered under the adjustment. If approved, the rates would be effective July 1, 2015, through June 30, 2016.