Note 2: Airedale Facility Fire

In September 2013, a fire caused significant destruction to the Company’s Airedale manufacturing facility and offices in Rawdon (Leeds), United Kingdom.  The Company reports Airedale’s financial results within the Building HVAC segment.  There were no injuries caused by the fire.  The Rawdon facility, which is leased, was used to manufacture cooling products and solutions for a variety of applications, including data centers, clean rooms, retail, leisure and process cooling. The Company suspended operations at the Rawdon site as a result of the fire; however, it transferred operations to temporary facilities while it rebuilt the leased facility.  The Company completed the reconstruction and relocation to the Rawdon facility in fiscal 2016.

The Company’s insurance covered damage to the leased facility, equipment, inventory, and other assets, as well as business interruption and lost profits, and recovery-related expenses caused by the fire.  Since the date of the fire, the Company has received cash proceeds totaling $99.0 million from its insurance provider for covered losses, and recorded losses and costs caused by the fire in the same statement of operations line as the related insurance recovery.