Acquisitions

Walnut Bend Solar

In June 2020, Entergy Arkansas signed an agreement for the purchase of an approximately 100 MW to-be-constructed solar photovoltaic energy facility, Walnut Bend Solar facility, to be sited on approximately 1,000 acres in Lee County, Arkansas. Acquisition of the Walnut Bend Solar facility was initially approved by the APSC in July 2021. The agreement was amended by the parties in February 2023 and the revised agreement was approved by the APSC in July 2023. In February 2024, Entergy Arkansas made an initial payment of $170 million to acquire the facility. The project will achieve commercial operation once testing is completed and the project has achieved substantial completion. Entergy Arkansas currently expects the project to achieve commercial operation in the first half of 2024, at which time a substantial completion payment of approximately $20 million is expected.

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022. In April 2023 both Entergy Mississippi and the tax equity
investor made additional capital contributions to the tax equity partnership that were then used to make the substantial completion payment of $30 million for acquisition of the facility. The final payment of $5 million for acquisition of the facility was made in October 2023. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in MS Sunflower Partnership, LLC.

Searcy Solar

In March 2019, Entergy Arkansas entered into a build-own-transfer agreement for the purchase of an approximately 100 MW solar energy facility to be sited on approximately 800 acres in White County near Searcy, Arkansas. The project, Searcy Solar facility, was being constructed by a subsidiary of NextEra Energy Resources. In April 2020 the APSC issued an order approving Entergy Arkansas’s acquisition of the Searcy Solar facility as being in the public interest. In May 2021, Entergy Arkansas filed with the APSC an application seeking to amend its certificate for the Searcy Solar facility to allow for the use of a tax equity partnership to acquire and own the facility. The tax equity partnership structure is expected to reduce costs and yield incremental net benefits to customers beyond those expected under the build-own-transfer structure alone. The APSC approved Entergy Arkansas’s tax equity partnership request in September 2021. AR Searcy Partnership, LLC was formed for the tax equity partnership with Entergy Arkansas as its managing member. In November 2021 both Entergy Arkansas and the tax equity investor made capital contributions to the tax equity partnership that were then used to acquire the facility. Upon substantial completion of the facility in December 2021, the tax equity partnership completed the purchase of the Searcy Solar facility. The purchase price for the Searcy Solar facility was approximately $133 million, which included a final payment of $1 million made in 2022. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in AR Searcy Partnership, LLC.

Hardin County Peaking Facility

In June 2021, Entergy Texas purchased the Hardin County Peaking Facility, an existing 147 MW simple-cycle gas-fired peaking power plant in Kountze, Texas, from East Texas Electric Cooperative, Inc. In addition, also in June 2021, Entergy Texas sold a 7.56% partial interest in the Montgomery County Power Station to East Texas Electric Cooperative, Inc. for approximately $68 million. The two interdependent transactions were approved by the PUCT in April 2021. The purchase price for the Hardin County Peaking Facility was approximately $37 million.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million, and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.
Indian Point Energy Center

In April 2019, Entergy entered into an agreement to sell, directly or indirectly, 100% of the equity interests in the subsidiaries that own Indian Point 1, Indian Point 2, and Indian Point 3, after Indian Point 3 had been shut down and defueled, to a Holtec International subsidiary. In November 2020 the NRC approved the sale of the plants to Holtec. Indian Point 3 was shut down in April 2021 and defueled in May 2021. In May 2021 the New York State Public Service Commission approved the sale of the plant to Holtec. The transaction closed in May 2021. The sale included the transfer of the licenses, spent fuel, decommissioning liabilities, and nuclear decommissioning trusts for the three units. The transaction resulted in a charge of $340 million ($268 million net-of-tax) in the second quarter of 2021. The disposition-date fair value of the nuclear decommissioning trust funds was approximately $2,387 million, and the disposition-date fair value of the asset retirement obligations was $1,996 million. The transaction also included materials and supplies and prepaid assets.
Entergy Arkansas [Member]  
Mergers, Acquisitions and Dispositions Disclosures [Text Block] ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Mississippi, and Entergy Texas)
Acquisitions

Walnut Bend Solar

In June 2020, Entergy Arkansas signed an agreement for the purchase of an approximately 100 MW to-be-constructed solar photovoltaic energy facility, Walnut Bend Solar facility, to be sited on approximately 1,000 acres in Lee County, Arkansas. Acquisition of the Walnut Bend Solar facility was initially approved by the APSC in July 2021. The agreement was amended by the parties in February 2023 and the revised agreement was approved by the APSC in July 2023. In February 2024, Entergy Arkansas made an initial payment of $170 million to acquire the facility. The project will achieve commercial operation once testing is completed and the project has achieved substantial completion. Entergy Arkansas currently expects the project to achieve commercial operation in the first half of 2024, at which time a substantial completion payment of approximately $20 million is expected.

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022. In April 2023 both Entergy Mississippi and the tax equity
investor made additional capital contributions to the tax equity partnership that were then used to make the substantial completion payment of $30 million for acquisition of the facility. The final payment of $5 million for acquisition of the facility was made in October 2023. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in MS Sunflower Partnership, LLC.

Searcy Solar

In March 2019, Entergy Arkansas entered into a build-own-transfer agreement for the purchase of an approximately 100 MW solar energy facility to be sited on approximately 800 acres in White County near Searcy, Arkansas. The project, Searcy Solar facility, was being constructed by a subsidiary of NextEra Energy Resources. In April 2020 the APSC issued an order approving Entergy Arkansas’s acquisition of the Searcy Solar facility as being in the public interest. In May 2021, Entergy Arkansas filed with the APSC an application seeking to amend its certificate for the Searcy Solar facility to allow for the use of a tax equity partnership to acquire and own the facility. The tax equity partnership structure is expected to reduce costs and yield incremental net benefits to customers beyond those expected under the build-own-transfer structure alone. The APSC approved Entergy Arkansas’s tax equity partnership request in September 2021. AR Searcy Partnership, LLC was formed for the tax equity partnership with Entergy Arkansas as its managing member. In November 2021 both Entergy Arkansas and the tax equity investor made capital contributions to the tax equity partnership that were then used to acquire the facility. Upon substantial completion of the facility in December 2021, the tax equity partnership completed the purchase of the Searcy Solar facility. The purchase price for the Searcy Solar facility was approximately $133 million, which included a final payment of $1 million made in 2022. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in AR Searcy Partnership, LLC.

Hardin County Peaking Facility

In June 2021, Entergy Texas purchased the Hardin County Peaking Facility, an existing 147 MW simple-cycle gas-fired peaking power plant in Kountze, Texas, from East Texas Electric Cooperative, Inc. In addition, also in June 2021, Entergy Texas sold a 7.56% partial interest in the Montgomery County Power Station to East Texas Electric Cooperative, Inc. for approximately $68 million. The two interdependent transactions were approved by the PUCT in April 2021. The purchase price for the Hardin County Peaking Facility was approximately $37 million.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million, and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.
Indian Point Energy Center

In April 2019, Entergy entered into an agreement to sell, directly or indirectly, 100% of the equity interests in the subsidiaries that own Indian Point 1, Indian Point 2, and Indian Point 3, after Indian Point 3 had been shut down and defueled, to a Holtec International subsidiary. In November 2020 the NRC approved the sale of the plants to Holtec. Indian Point 3 was shut down in April 2021 and defueled in May 2021. In May 2021 the New York State Public Service Commission approved the sale of the plant to Holtec. The transaction closed in May 2021. The sale included the transfer of the licenses, spent fuel, decommissioning liabilities, and nuclear decommissioning trusts for the three units. The transaction resulted in a charge of $340 million ($268 million net-of-tax) in the second quarter of 2021. The disposition-date fair value of the nuclear decommissioning trust funds was approximately $2,387 million, and the disposition-date fair value of the asset retirement obligations was $1,996 million. The transaction also included materials and supplies and prepaid assets.
Entergy Mississippi [Member]  
Mergers, Acquisitions and Dispositions Disclosures [Text Block] ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Mississippi, and Entergy Texas)
Acquisitions

Walnut Bend Solar

In June 2020, Entergy Arkansas signed an agreement for the purchase of an approximately 100 MW to-be-constructed solar photovoltaic energy facility, Walnut Bend Solar facility, to be sited on approximately 1,000 acres in Lee County, Arkansas. Acquisition of the Walnut Bend Solar facility was initially approved by the APSC in July 2021. The agreement was amended by the parties in February 2023 and the revised agreement was approved by the APSC in July 2023. In February 2024, Entergy Arkansas made an initial payment of $170 million to acquire the facility. The project will achieve commercial operation once testing is completed and the project has achieved substantial completion. Entergy Arkansas currently expects the project to achieve commercial operation in the first half of 2024, at which time a substantial completion payment of approximately $20 million is expected.

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022. In April 2023 both Entergy Mississippi and the tax equity
investor made additional capital contributions to the tax equity partnership that were then used to make the substantial completion payment of $30 million for acquisition of the facility. The final payment of $5 million for acquisition of the facility was made in October 2023. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in MS Sunflower Partnership, LLC.

Searcy Solar

In March 2019, Entergy Arkansas entered into a build-own-transfer agreement for the purchase of an approximately 100 MW solar energy facility to be sited on approximately 800 acres in White County near Searcy, Arkansas. The project, Searcy Solar facility, was being constructed by a subsidiary of NextEra Energy Resources. In April 2020 the APSC issued an order approving Entergy Arkansas’s acquisition of the Searcy Solar facility as being in the public interest. In May 2021, Entergy Arkansas filed with the APSC an application seeking to amend its certificate for the Searcy Solar facility to allow for the use of a tax equity partnership to acquire and own the facility. The tax equity partnership structure is expected to reduce costs and yield incremental net benefits to customers beyond those expected under the build-own-transfer structure alone. The APSC approved Entergy Arkansas’s tax equity partnership request in September 2021. AR Searcy Partnership, LLC was formed for the tax equity partnership with Entergy Arkansas as its managing member. In November 2021 both Entergy Arkansas and the tax equity investor made capital contributions to the tax equity partnership that were then used to acquire the facility. Upon substantial completion of the facility in December 2021, the tax equity partnership completed the purchase of the Searcy Solar facility. The purchase price for the Searcy Solar facility was approximately $133 million, which included a final payment of $1 million made in 2022. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in AR Searcy Partnership, LLC.

Hardin County Peaking Facility

In June 2021, Entergy Texas purchased the Hardin County Peaking Facility, an existing 147 MW simple-cycle gas-fired peaking power plant in Kountze, Texas, from East Texas Electric Cooperative, Inc. In addition, also in June 2021, Entergy Texas sold a 7.56% partial interest in the Montgomery County Power Station to East Texas Electric Cooperative, Inc. for approximately $68 million. The two interdependent transactions were approved by the PUCT in April 2021. The purchase price for the Hardin County Peaking Facility was approximately $37 million.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million, and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.
Indian Point Energy Center

In April 2019, Entergy entered into an agreement to sell, directly or indirectly, 100% of the equity interests in the subsidiaries that own Indian Point 1, Indian Point 2, and Indian Point 3, after Indian Point 3 had been shut down and defueled, to a Holtec International subsidiary. In November 2020 the NRC approved the sale of the plants to Holtec. Indian Point 3 was shut down in April 2021 and defueled in May 2021. In May 2021 the New York State Public Service Commission approved the sale of the plant to Holtec. The transaction closed in May 2021. The sale included the transfer of the licenses, spent fuel, decommissioning liabilities, and nuclear decommissioning trusts for the three units. The transaction resulted in a charge of $340 million ($268 million net-of-tax) in the second quarter of 2021. The disposition-date fair value of the nuclear decommissioning trust funds was approximately $2,387 million, and the disposition-date fair value of the asset retirement obligations was $1,996 million. The transaction also included materials and supplies and prepaid assets.
Entergy Texas [Member]  
Mergers, Acquisitions and Dispositions Disclosures [Text Block] ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Mississippi, and Entergy Texas)
Acquisitions

Walnut Bend Solar

In June 2020, Entergy Arkansas signed an agreement for the purchase of an approximately 100 MW to-be-constructed solar photovoltaic energy facility, Walnut Bend Solar facility, to be sited on approximately 1,000 acres in Lee County, Arkansas. Acquisition of the Walnut Bend Solar facility was initially approved by the APSC in July 2021. The agreement was amended by the parties in February 2023 and the revised agreement was approved by the APSC in July 2023. In February 2024, Entergy Arkansas made an initial payment of $170 million to acquire the facility. The project will achieve commercial operation once testing is completed and the project has achieved substantial completion. Entergy Arkansas currently expects the project to achieve commercial operation in the first half of 2024, at which time a substantial completion payment of approximately $20 million is expected.

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022. In April 2023 both Entergy Mississippi and the tax equity
investor made additional capital contributions to the tax equity partnership that were then used to make the substantial completion payment of $30 million for acquisition of the facility. The final payment of $5 million for acquisition of the facility was made in October 2023. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in MS Sunflower Partnership, LLC.

Searcy Solar

In March 2019, Entergy Arkansas entered into a build-own-transfer agreement for the purchase of an approximately 100 MW solar energy facility to be sited on approximately 800 acres in White County near Searcy, Arkansas. The project, Searcy Solar facility, was being constructed by a subsidiary of NextEra Energy Resources. In April 2020 the APSC issued an order approving Entergy Arkansas’s acquisition of the Searcy Solar facility as being in the public interest. In May 2021, Entergy Arkansas filed with the APSC an application seeking to amend its certificate for the Searcy Solar facility to allow for the use of a tax equity partnership to acquire and own the facility. The tax equity partnership structure is expected to reduce costs and yield incremental net benefits to customers beyond those expected under the build-own-transfer structure alone. The APSC approved Entergy Arkansas’s tax equity partnership request in September 2021. AR Searcy Partnership, LLC was formed for the tax equity partnership with Entergy Arkansas as its managing member. In November 2021 both Entergy Arkansas and the tax equity investor made capital contributions to the tax equity partnership that were then used to acquire the facility. Upon substantial completion of the facility in December 2021, the tax equity partnership completed the purchase of the Searcy Solar facility. The purchase price for the Searcy Solar facility was approximately $133 million, which included a final payment of $1 million made in 2022. See Note 1 to the financial statements for further discussion of the HLBV method of accounting used to account for the investment in AR Searcy Partnership, LLC.

Hardin County Peaking Facility

In June 2021, Entergy Texas purchased the Hardin County Peaking Facility, an existing 147 MW simple-cycle gas-fired peaking power plant in Kountze, Texas, from East Texas Electric Cooperative, Inc. In addition, also in June 2021, Entergy Texas sold a 7.56% partial interest in the Montgomery County Power Station to East Texas Electric Cooperative, Inc. for approximately $68 million. The two interdependent transactions were approved by the PUCT in April 2021. The purchase price for the Hardin County Peaking Facility was approximately $37 million.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million, and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.
Indian Point Energy Center

In April 2019, Entergy entered into an agreement to sell, directly or indirectly, 100% of the equity interests in the subsidiaries that own Indian Point 1, Indian Point 2, and Indian Point 3, after Indian Point 3 had been shut down and defueled, to a Holtec International subsidiary. In November 2020 the NRC approved the sale of the plants to Holtec. Indian Point 3 was shut down in April 2021 and defueled in May 2021. In May 2021 the New York State Public Service Commission approved the sale of the plant to Holtec. The transaction closed in May 2021. The sale included the transfer of the licenses, spent fuel, decommissioning liabilities, and nuclear decommissioning trusts for the three units. The transaction resulted in a charge of $340 million ($268 million net-of-tax) in the second quarter of 2021. The disposition-date fair value of the nuclear decommissioning trust funds was approximately $2,387 million, and the disposition-date fair value of the asset retirement obligations was $1,996 million. The transaction also included materials and supplies and prepaid assets.