Asset Retirement Obligations Asset Retirement Obligations
9 Months Ended
Sep. 30, 2018
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

Entergy Arkansas [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

Entergy Louisiana [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

Entergy Mississippi [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

Entergy New Orleans [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

Entergy Texas [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.

System Energy [Member]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. The following are updates to that discussion.

In the first quarter 2018, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for River Bend as a result of a revised decommissioning cost study. The revised estimate resulted in an $85.4 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining life of the unit.

As discussed in the Form 10-K, Entergy Wholesale Commodities plant owners will submit filings with the NRC for planned shutdown activities as the nuclear plants individually approach and begin decommissioning. Entergy Nuclear Generation Company expects to file its Post-Shutdown Decommissioning Activities Report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge. See Note 14 to the financial statements in the Form 10-K for a discussion of impairment of the Pilgrim plant.