Acquisitions

Hot Spring Energy Facility

In November 2012, Entergy Arkansas purchased the Hot Spring Energy Facility, a 620 MW combined-cycle natural gas turbine unit located in Malvern, Arkansas, from KGen Hot Spring LLC for approximately $253 million.  The FERC and the APSC approved the transaction.

Hinds Energy Facility

In November 2012, Entergy Mississippi purchased the Hinds Energy Facility, a 450 MW combined-cycle natural gas turbine unit located in Jackson, Mississippi, from KGen Hinds LLC for approximately $206 million.  The FERC and the MPSC approved the transaction.

Palisades Purchased Power Agreement

Entergy’s purchase of the Palisades plant in 2007 included a unit-contingent, 15-year purchased power agreement (PPA) with Consumers Energy for 100% of the plant’s output, excluding any future uprates.  Prices under the PPA range from $43.50/MWh in 2007 to $61.50/MWh in 2022, and the average price under the PPA is $51/MWh.  For the PPA, which was at below-market prices at the time of the acquisition, Entergy will amortize a liability to revenue over the life of the agreement.  The amount that will be amortized each period is based upon the difference between the present value calculated at the date of acquisition of each year’s difference between revenue under the agreement and revenue based on estimated market prices.  Amounts amortized to revenue were $16 million in 2014, $18 million in 2013, and $17 million in 2012.  The amounts to be amortized to revenue for the next five years will be $15 million in 2015, $13 million for 2016, $12 million for 2017, $8 million for 2018, and $13 million for 2019.

NYPA Value Sharing Agreements

Entergy’s purchase of the FitzPatrick and Indian Point 3 plants from NYPA included value sharing agreements with NYPA.  In October 2007, Entergy subsidiaries and NYPA amended and restated the value sharing agreements to clarify and amend certain provisions of the original terms.  Under the amended value sharing agreements, Entergy subsidiaries made annual payments to NYPA based on the generation output of the Indian Point 3 and FitzPatrick plants from January 2007 through December 2014.  Entergy subsidiaries paid NYPA $6.59 per MWh for power sold from Indian Point 3, up to an annual cap of $48 million, and $3.91 per MWh for power sold from FitzPatrick, up to an annual cap of $24 million.  The annual payment for each year’s output was due by January 15 of the following year.  Entergy recorded the liability for payments to NYPA as power is generated and sold by Indian Point 3 and FitzPatrick.  An amount equal to the liability was recorded to the plant asset account as contingent purchase price consideration for the plants.  In 2014, 2013, and 2012, Entergy Wholesale Commodities recorded approximately $72 million as plant for generation during each of those years.  This amount was depreciated over the expected remaining useful life of the plants.

Dispositions

In November 2013, Entergy sold Entergy Solutions District Energy, a business wholly-owned by Entergy in the Entergy Wholesale Commodities segment that owns and operates district energy assets serving the business districts in Houston and New Orleans. Entergy sold Entergy Solutions District Energy for $140 million and realized a pre-tax gain of $44 million on the sale.

Entergy Louisiana [Member]  
Acquisitions And Dispositions
ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, and Entergy Mississippi)

Acquisitions

Hot Spring Energy Facility

In November 2012, Entergy Arkansas purchased the Hot Spring Energy Facility, a 620 MW combined-cycle natural gas turbine unit located in Malvern, Arkansas, from KGen Hot Spring LLC for approximately $253 million.  The FERC and the APSC approved the transaction.

Hinds Energy Facility

In November 2012, Entergy Mississippi purchased the Hinds Energy Facility, a 450 MW combined-cycle natural gas turbine unit located in Jackson, Mississippi, from KGen Hinds LLC for approximately $206 million.  The FERC and the MPSC approved the transaction.

Palisades Purchased Power Agreement

Entergy’s purchase of the Palisades plant in 2007 included a unit-contingent, 15-year purchased power agreement (PPA) with Consumers Energy for 100% of the plant’s output, excluding any future uprates.  Prices under the PPA range from $43.50/MWh in 2007 to $61.50/MWh in 2022, and the average price under the PPA is $51/MWh.  For the PPA, which was at below-market prices at the time of the acquisition, Entergy will amortize a liability to revenue over the life of the agreement.  The amount that will be amortized each period is based upon the difference between the present value calculated at the date of acquisition of each year’s difference between revenue under the agreement and revenue based on estimated market prices.  Amounts amortized to revenue were $16 million in 2014, $18 million in 2013, and $17 million in 2012.  The amounts to be amortized to revenue for the next five years will be $15 million in 2015, $13 million for 2016, $12 million for 2017, $8 million for 2018, and $13 million for 2019.

NYPA Value Sharing Agreements

Entergy’s purchase of the FitzPatrick and Indian Point 3 plants from NYPA included value sharing agreements with NYPA.  In October 2007, Entergy subsidiaries and NYPA amended and restated the value sharing agreements to clarify and amend certain provisions of the original terms.  Under the amended value sharing agreements, Entergy subsidiaries made annual payments to NYPA based on the generation output of the Indian Point 3 and FitzPatrick plants from January 2007 through December 2014.  Entergy subsidiaries paid NYPA $6.59 per MWh for power sold from Indian Point 3, up to an annual cap of $48 million, and $3.91 per MWh for power sold from FitzPatrick, up to an annual cap of $24 million.  The annual payment for each year’s output was due by January 15 of the following year.  Entergy recorded the liability for payments to NYPA as power is generated and sold by Indian Point 3 and FitzPatrick.  An amount equal to the liability was recorded to the plant asset account as contingent purchase price consideration for the plants.  In 2014, 2013, and 2012, Entergy Wholesale Commodities recorded approximately $72 million as plant for generation during each of those years.  This amount was depreciated over the expected remaining useful life of the plants.

Dispositions

In November 2013, Entergy sold Entergy Solutions District Energy, a business wholly-owned by Entergy in the Entergy Wholesale Commodities segment that owns and operates district energy assets serving the business districts in Houston and New Orleans. Entergy sold Entergy Solutions District Energy for $140 million and realized a pre-tax gain of $44 million on the sale.

Entergy Arkansas [Member]  
Acquisitions And Dispositions
ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, and Entergy Mississippi)

Acquisitions

Hot Spring Energy Facility

In November 2012, Entergy Arkansas purchased the Hot Spring Energy Facility, a 620 MW combined-cycle natural gas turbine unit located in Malvern, Arkansas, from KGen Hot Spring LLC for approximately $253 million.  The FERC and the APSC approved the transaction.

Hinds Energy Facility

In November 2012, Entergy Mississippi purchased the Hinds Energy Facility, a 450 MW combined-cycle natural gas turbine unit located in Jackson, Mississippi, from KGen Hinds LLC for approximately $206 million.  The FERC and the MPSC approved the transaction.

Palisades Purchased Power Agreement

Entergy’s purchase of the Palisades plant in 2007 included a unit-contingent, 15-year purchased power agreement (PPA) with Consumers Energy for 100% of the plant’s output, excluding any future uprates.  Prices under the PPA range from $43.50/MWh in 2007 to $61.50/MWh in 2022, and the average price under the PPA is $51/MWh.  For the PPA, which was at below-market prices at the time of the acquisition, Entergy will amortize a liability to revenue over the life of the agreement.  The amount that will be amortized each period is based upon the difference between the present value calculated at the date of acquisition of each year’s difference between revenue under the agreement and revenue based on estimated market prices.  Amounts amortized to revenue were $16 million in 2014, $18 million in 2013, and $17 million in 2012.  The amounts to be amortized to revenue for the next five years will be $15 million in 2015, $13 million for 2016, $12 million for 2017, $8 million for 2018, and $13 million for 2019.

NYPA Value Sharing Agreements

Entergy’s purchase of the FitzPatrick and Indian Point 3 plants from NYPA included value sharing agreements with NYPA.  In October 2007, Entergy subsidiaries and NYPA amended and restated the value sharing agreements to clarify and amend certain provisions of the original terms.  Under the amended value sharing agreements, Entergy subsidiaries made annual payments to NYPA based on the generation output of the Indian Point 3 and FitzPatrick plants from January 2007 through December 2014.  Entergy subsidiaries paid NYPA $6.59 per MWh for power sold from Indian Point 3, up to an annual cap of $48 million, and $3.91 per MWh for power sold from FitzPatrick, up to an annual cap of $24 million.  The annual payment for each year’s output was due by January 15 of the following year.  Entergy recorded the liability for payments to NYPA as power is generated and sold by Indian Point 3 and FitzPatrick.  An amount equal to the liability was recorded to the plant asset account as contingent purchase price consideration for the plants.  In 2014, 2013, and 2012, Entergy Wholesale Commodities recorded approximately $72 million as plant for generation during each of those years.  This amount was depreciated over the expected remaining useful life of the plants.

Dispositions

In November 2013, Entergy sold Entergy Solutions District Energy, a business wholly-owned by Entergy in the Entergy Wholesale Commodities segment that owns and operates district energy assets serving the business districts in Houston and New Orleans. Entergy sold Entergy Solutions District Energy for $140 million and realized a pre-tax gain of $44 million on the sale.

Entergy Mississippi [Member]  
Acquisitions And Dispositions
ACQUISITIONS AND DISPOSITIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, and Entergy Mississippi)

Acquisitions

Hot Spring Energy Facility

In November 2012, Entergy Arkansas purchased the Hot Spring Energy Facility, a 620 MW combined-cycle natural gas turbine unit located in Malvern, Arkansas, from KGen Hot Spring LLC for approximately $253 million.  The FERC and the APSC approved the transaction.

Hinds Energy Facility

In November 2012, Entergy Mississippi purchased the Hinds Energy Facility, a 450 MW combined-cycle natural gas turbine unit located in Jackson, Mississippi, from KGen Hinds LLC for approximately $206 million.  The FERC and the MPSC approved the transaction.

Palisades Purchased Power Agreement

Entergy’s purchase of the Palisades plant in 2007 included a unit-contingent, 15-year purchased power agreement (PPA) with Consumers Energy for 100% of the plant’s output, excluding any future uprates.  Prices under the PPA range from $43.50/MWh in 2007 to $61.50/MWh in 2022, and the average price under the PPA is $51/MWh.  For the PPA, which was at below-market prices at the time of the acquisition, Entergy will amortize a liability to revenue over the life of the agreement.  The amount that will be amortized each period is based upon the difference between the present value calculated at the date of acquisition of each year’s difference between revenue under the agreement and revenue based on estimated market prices.  Amounts amortized to revenue were $16 million in 2014, $18 million in 2013, and $17 million in 2012.  The amounts to be amortized to revenue for the next five years will be $15 million in 2015, $13 million for 2016, $12 million for 2017, $8 million for 2018, and $13 million for 2019.

NYPA Value Sharing Agreements

Entergy’s purchase of the FitzPatrick and Indian Point 3 plants from NYPA included value sharing agreements with NYPA.  In October 2007, Entergy subsidiaries and NYPA amended and restated the value sharing agreements to clarify and amend certain provisions of the original terms.  Under the amended value sharing agreements, Entergy subsidiaries made annual payments to NYPA based on the generation output of the Indian Point 3 and FitzPatrick plants from January 2007 through December 2014.  Entergy subsidiaries paid NYPA $6.59 per MWh for power sold from Indian Point 3, up to an annual cap of $48 million, and $3.91 per MWh for power sold from FitzPatrick, up to an annual cap of $24 million.  The annual payment for each year’s output was due by January 15 of the following year.  Entergy recorded the liability for payments to NYPA as power is generated and sold by Indian Point 3 and FitzPatrick.  An amount equal to the liability was recorded to the plant asset account as contingent purchase price consideration for the plants.  In 2014, 2013, and 2012, Entergy Wholesale Commodities recorded approximately $72 million as plant for generation during each of those years.  This amount was depreciated over the expected remaining useful life of the plants.

Dispositions

In November 2013, Entergy sold Entergy Solutions District Energy, a business wholly-owned by Entergy in the Entergy Wholesale Commodities segment that owns and operates district energy assets serving the business districts in Houston and New Orleans. Entergy sold Entergy Solutions District Energy for $140 million and realized a pre-tax gain of $44 million on the sale.