Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy Arkansas [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy Gulf States Louisiana [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy Louisiana [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

System Energy [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy Mississippi [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy New Orleans
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.

Entergy Texas [Member]
 
Asset Retirement Obligations

NOTE 13. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

See Note 9 to the financial statements in the Form 10-K for a discussion of asset retirement obligations. Following is an update to that discussion.

 

            In the first quarter of 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for a nuclear site as a result of a revised decommissioning cost study.  The revised estimate resulted in a $46.6 million reduction in the decommissioning cost liability, along with a corresponding reduction in the related asset retirement cost asset.

 

            In the third quarter 2013, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee as a result of a revised decommissioning cost study. The revised estimate resulted in a $58 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The increase in the estimated decommissioning cost liability resulted from the change in expectation regarding the timing of decommissioning cash flows due to the decision to cease operations of the plant. See Note 11 to the financial statements herein for further discussion of the Vermont Yankee plant.

 

Assuming the end of Vermont Yankee operations in the fourth quarter 2014, the amount required to meet the NRC minimum for decommissioning financial assurance for license termination is $566 million. The Vermont Yankee decommissioning trust had a balance of approximately $584 million as of September 30, 2013, excluding the $40 million guarantee by Entergy Corporation to satisfy NRC requirements following the 2009 review of financial assurance levels. Filings with the NRC for planned shutdown activities will determine whether any other financial assurance may be required and will specifically address funding for spent fuel management, which will be required until the federal government takes possession of the fuel and removes it from the site, per its current obligations.