Commitments, Guarantees and Contingencies - North Dakota Wind Development (Details) (USD $)
In Millions, unless otherwise specified
Sep. 30, 2012
Dec. 31, 2011
North Dakota Wind Development [Line Items]    
Capital Cost Spent to Date $ 45.7 $ 27.8
Bison 1 Wind Project [Member]
   
North Dakota Wind Development [Line Items]    
Transmission Line Length (Miles) 22  
Transmission Line Capacity (kV) 230  
Generating Unit Capacity (MW) 82  
Total Project Cost 174.3  
Bison 2 Wind Project [Member]
   
North Dakota Wind Development [Line Items]    
Generating Unit Capacity (MW) 105  
Expected Capital Cost 160.0  
Capital Cost Spent to Date 129.2  
Bison 3 Wind Project [Member]
   
North Dakota Wind Development [Line Items]    
Generating Unit Capacity (MW) 105  
Expected Capital Cost 160.0  
Capital Cost Spent to Date $ 131.0  
DC Transmission Line from Square Butte [Member]
   
North Dakota Wind Development [Line Items]    
Transmission Line Length (Miles) 465  
Transmission Line Capacity (kV) 250