XML 166 R85.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments And Contingencies (Narrative) (Details)
1 Months Ended 12 Months Ended
Jan. 01, 2018
Jun. 30, 2016
USD ($)
Dec. 31, 2017
USD ($)
claim
MW
Jun. 30, 2017
USD ($)
May 31, 2017
USD ($)
Jan. 31, 2017
USD ($)
Nov. 30, 2016
USD ($)
Oct. 31, 2016
USD ($)
Sep. 30, 2016
USD ($)
Aug. 31, 2016
USD ($)
Jul. 31, 2016
USD ($)
Jun. 30, 2016
USD ($)
May 31, 2016
USD ($)
Apr. 30, 2016
USD ($)
Dec. 31, 2015
USD ($)
Oct. 31, 2015
USD ($)
Feb. 28, 2014
USD ($)
Nov. 30, 2013
USD ($)
Dec. 31, 2017
USD ($)
program
claim
plaintiff
reactor
MW
Dec. 31, 2016
USD ($)
Dec. 31, 2015
USD ($)
Dec. 31, 2014
USD ($)
Sep. 30, 2015
USD ($)
Commitments And Contingencies [Line Items]                                              
Accidental Outage Coverage Weekly Indemnity Payment Period                                     364 days        
Accidental Outage Coverage Weekly Indemnity Final Payment Period                                     406 days        
Proceeds from insurance                                     $ 26,157,000 $ 20,968,000 $ 24,399,000    
Number of financial protection programs | program                                     2        
Insurance coverage for public liability by American Nuclear Insurers     $ 450,000,000                               $ 450,000,000        
Maximum retrospective insurance premium obligation per reactor per incident     127,300,000                               127,300,000        
Maximum retrospective insurance premium obligation per incident     1,146,000,000                               1,146,000,000        
Rate of maximum retrospective premium per year per nuclear power reactor     $ 19,000,000                               19,000,000        
ANI combined with Secondary Financial Protection Coverage                                     13,000,000,000        
Additional damage coverage for a terrorist event                                     $ 100,000,000,000        
Number of nuclear reactor included in the Secondary Financial Protection program | reactor                                     102        
Total premium for reactor under secondary financial protection program                                     $ 13,000,000,000        
Maximum recovery nuclear insurance policies for property damage caused by Terrorist Act                                     3,240,000,000        
Maximum conventional property insurance coverage on an each and every loss basis                                     400,000,000        
Minimum value of power plants, substations to be covered under conventional property insurance                                     5,000,000        
Purchase of terrorism insurance coverage                                     300,000,000        
Amount of additional insurance coverage per occurrence                                     $ 20,000,000        
Number of asbestos lawsuits | claim     200                               200        
Number of claimants in asbestos lawsuits | plaintiff                                     500        
Reduction in fee Entergy’s nuclear owner/licensee subsidiaries have been charged related to spent nuclear fuel storage                                   $ 0          
Percentage of Weekly Indemnity Paid After Deductible Period has Passed                                     100.00%        
Percentage of Weekly Indemnity Paid After Deductible Second Period has Passed                                     80.00%        
Insurance coverage for public liability prior to January 1, 2017     $ 375,000,000                               $ 375,000,000        
Accidental Outage Coverage Weekly Indemnity Second Payment Period                                     364 days        
Percentage of Weekly Indemnity Paid After Deductible Final Period has Passed                                     80.00%        
Effective Income Tax Rate Reconciliation, at Federal Statutory Income Tax Rate, Percent 21.00%                                   35.00%        
Increase (Decrease) in Regulatory Liabilities                                     $ 2,915,795,000 158,031,000 61,241,000    
Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Capacity Supply Obligations in ISO New England | MW     677                               677        
Grand Gulf [Member]                                              
Commitments And Contingencies [Line Items]                                              
Ownership percentage by a non-affiliated company                                     10.00%        
Indian Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     $ 500,000,000        
Vermont Yankee [Member]                                              
Commitments And Contingencies [Line Items]                                              
Insurance coverage for public liability by American Nuclear Insurers     $ 100,000,000                               100,000,000        
Operational Perils [Member]                                              
Commitments And Contingencies [Line Items]                                              
Self-insured retention per occurrence                                     20,000,000        
Earthquake and Flood [Member]                                              
Commitments And Contingencies [Line Items]                                              
Maximum conventional property insurance coverage on an each and every loss basis                                     400,000,000        
Self-insured retention per occurrence                                     40,000,000        
Named Windstorm and Associated Storm Surge [Member]                                              
Commitments And Contingencies [Line Items]                                              
Maximum conventional property insurance coverage on an each and every loss basis                                     125,000,000        
Self-insured retention per occurrence                                     40,000,000        
Non-Nuclear and Non-Radioactive Damage [Member] | Vermont Yankee [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     50,000,000        
Non-Nuclear and Non-Radioactive Damage [Member] | Pilgrim, Palisades, and Indian Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     500,000,000        
Wind and Flood [Member] | Indian Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance Deductible                                     $ 10,000,000        
Percentage of Additional Property Insurance Deductible for Loss in Excess of Deductible                                     10.00%        
Maximum Additional Property Insurance Deductible                                     $ 50,000,000        
Accidental Outage Coverage Program [Member] | Nuclear Plants [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     327,600,000                               327,600,000        
Accidental Outage Coverage Program [Member] | Grand Gulf [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     327,600,000                               327,600,000        
Accidental Outage Coverage Program [Member] | Waterford 3 and Grand Gulf [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     327,600,000                               327,600,000        
Flood, Earthquake and Volcanic Eruption [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     500,000,000        
Wind, Flood, Earthquake and Volcanic Eruption [Member] | Vermont Yankee [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance Deductible                                     $ 10,000,000        
Percentage of Additional Property Insurance Deductible for Loss in Excess of Deductible                                     10.00%        
Maximum Additional Property Insurance Deductible                                     $ 50,000,000        
Wind [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance Deductible                                     $ 10,000,000        
Percentage of Additional Property Insurance Deductible for Loss in Excess of Deductible                                     10.00%        
Maximum Additional Property Insurance Deductible                                     $ 50,000,000        
Flood event [Member] | ANO and Grand Gulf [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     500,000,000        
Flood event [Member] | River Bend and Waterford 3 [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     500,000,000        
Subsequent Event [Member]                                              
Commitments And Contingencies [Line Items]                                              
Effective Income Tax Rate Reconciliation, at Federal Statutory Income Tax Rate, Percent 21.00%                                            
Utility [Member] | Primary Layer [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     1,500,000,000                               1,500,000,000        
Utility [Member] | Blanket Layer [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     100,000,000                               100,000,000        
Utility [Member] | Earthquake and Volcanic Eruption [Member]                                              
Commitments And Contingencies [Line Items]                                              
Primary Insurance Layer Conditions Of Coverage                                     500,000,000        
Entergy Wholesale Commodities [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Carrying Value of Nuclear Plant                                             $ 718,000,000
Entergy Wholesale Commodities [Member] | FitzPatrick [Member]                                              
Commitments And Contingencies [Line Items]                                              
Carrying Value of Nuclear Plant                                             $ 742,000,000
Entergy Wholesale Commodities [Member] | Palisades [Member]                                              
Commitments And Contingencies [Line Items]                                              
Carrying Value of Nuclear Plant                             $ 859,000,000         558,000,000 859,000,000    
Entergy Wholesale Commodities [Member] | Indian Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Carrying Value of Nuclear Plant                                       2,619,000,000      
Entergy Wholesale Commodities [Member] | Primary Layer [Member] | Big Rock Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     500,000,000                               500,000,000        
Entergy Wholesale Commodities [Member] | Primary Layer [Member] | Indian Point [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     1,600,000,000                               1,600,000,000        
Entergy Wholesale Commodities [Member] | Primary Layer [Member] | Vermont Yankee [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     50,000,000                               50,000,000        
Entergy Wholesale Commodities [Member] | Primary Layer [Member] | Pilgrim and Palisades [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance insured amount per occurrence     $ 1,115,000,000                               1,115,000,000        
Nuclear [Member] | Wind [Member]                                              
Commitments And Contingencies [Line Items]                                              
Property Insurance Deductible                                     $ 10,000,000        
Percentage of Additional Property Insurance Deductible for Loss in Excess of Deductible                                     10.00%        
Maximum Additional Property Insurance Deductible                                     $ 50,000,000        
Entergy Mississippi [Member]                                              
Commitments And Contingencies [Line Items]                                              
Proceeds from insurance                                     $ 0 0 12,932,000    
Percentage of capacity and energy agreed to sell by system energy from grand gulf                                     33.00%        
Average monthly payments under unit power sales agreement                                     $ 17,000,000        
Purchased Percentage Of Capacity And Energy Based On Agreement                                     31.30%        
Amortization period of cost                                     27 years        
Allocated amortization cost in percentage                                     43.97%        
Increase (Decrease) in Regulatory Liabilities                                     $ 405,395,000 (2,986,000) 9,172,000    
Entergy Texas [Member]                                              
Commitments And Contingencies [Line Items]                                              
Proceeds from insurance                                     $ 2,431,000 0 0    
Number of asbestos lawsuits | claim     80                               80        
Number of claimants in asbestos lawsuits | plaintiff                                     600        
Increase (Decrease) in Regulatory Liabilities                                     $ 410,968,000 2,106,000 1,271,000    
System Energy [Member]                                              
Commitments And Contingencies [Line Items]                                              
Number of nuclear power reactors | reactor                                     1        
Increase (Decrease) in Regulatory Liabilities                                     $ 331,251,000 33,438,000 (33,686,000)    
System Energy [Member] | Grand Gulf [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount       $ 49,000,000                                      
System Energy ownership in nuclear unit                   90.00%                          
Damages awarded for previously capitalized costs                   $ 16,000,000                          
Damages awarded for previously recorded operation and maintenance                   9,000,000                          
Damages awarded for previously recorded nuclear fuel expense                   19,000,000                          
Reduction of previously recorded deprecation expense                   5,000,000                          
Plant balance reduction                   11,000,000                          
Entergy New Orleans [Member]                                              
Commitments And Contingencies [Line Items]                                              
Number of asbestos lawsuits | claim     80                               80        
Number of claimants in asbestos lawsuits | plaintiff                                     600        
Percentage of capacity and energy agreed to sell by system energy from grand gulf                                     17.00%        
Average monthly payments under unit power sales agreement                                     $ 9,400,000        
Purchased Percentage Of Capacity And Energy Based On Agreement                                     24.70%        
Amortization period of cost                                     27 years        
Allocated amortization cost in percentage                                     29.80%        
Increase (Decrease) in Regulatory Liabilities                                     $ 110,147,000 (3,997,000) (7,359,000)    
Entergy New Orleans [Member] | Flood, Earthquake and Named Windstorm [Member]                                              
Commitments And Contingencies [Line Items]                                              
Maximum conventional property insurance coverage on an each and every loss basis                                     50,000,000        
Entergy Louisiana [Member]                                              
Commitments And Contingencies [Line Items]                                              
Payments made under purchased power agreement                                     $ 122,900,000 158,700,000 146,000,000    
Required energy for the production of Vidalia project in percentage                                     94.00%        
Estimated Payments Under Purchased Power Agreement in Next Twelve Months     $ 129,000,000                               $ 129,000,000        
Estimated Payments Under Purchased Power Agreement in Year Two and Thereafter     $ 1,680,000,000                               1,680,000,000        
Credit rates agreed by subsidiary for each year under settlement related to tax benefits from tax treatment of purchased power agreement                                     $ 11,000,000        
Number of years for which credit rates agreed by subsidiary under settlement related to tax benefits from the tax treatment of purchased power agreement                                     10 years        
Amount of remaining benefits of tax credit by crediting rate payers                                     $ 20,235,000        
Maximum period up to which remaining benefit of tax accounting election shared                                     15 years        
Proceeds from insurance                                     $ 5,305,000 10,564,000 0    
Number of nuclear power reactors | reactor                                     2        
Number of asbestos lawsuits | claim     80                               80        
Number of claimants in asbestos lawsuits | plaintiff                                     600        
Percentage of capacity and energy agreed to sell by system energy from grand gulf                                     14.00%        
Average monthly payments under unit power sales agreement                                     $ 7,800,000        
Purchased Percentage Of Capacity And Energy Based On Agreement                                     26.90%        
Amortization period of cost                                     27 years        
Allocated amortization cost in percentage                                     26.23%        
Increase (Decrease) in Regulatory Liabilities                                     $ 605,453,000 62,351,000 96,234,000    
Entergy Louisiana [Member] | Waterford 3 [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount                   53,000,000                          
Damages awarded for previously capitalized costs             $ 41,000,000                                
Damages awarded for previously recorded operation and maintenance             2,000,000                                
Damages awarded for previously recorded nuclear fuel expense             10,000,000                                
Reduction of previously recorded deprecation expense             $ 3,000,000                                
Entergy Louisiana [Member] | River Bend [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount         $ 600,000       $ 5,000,000         $ 42,000,000                  
Damages awarded for previously capitalized costs                   17,000,000                          
Damages awarded for previously recorded operation and maintenance           $ 3,000,000       2,000,000                          
Damages awarded for previously recorded nuclear fuel expense           2,000,000       23,000,000                          
Reduction of previously recorded deprecation expense                   3,000,000                          
Plant balance reduction                   $ 14,000,000                          
Entergy Arkansas [Member]                                              
Commitments And Contingencies [Line Items]                                              
Estimated cost to restore ANO to service                                     95,000,000        
Deferred Fuel and Purchased Energy Costs Excluded From Revised Energy Cost Rate                                 $ 65,900,000            
Proceeds From Insurance Settlement, Operating and Investing Activities                                           $ 50,000,000  
Proceeds from insurance                                     $ 0 10,404,000 11,654,000    
Number of nuclear power reactors | reactor                                     2        
Number of asbestos lawsuits | claim     80                               80        
Number of claimants in asbestos lawsuits | plaintiff                                     600        
Percentage of capacity and energy agreed to sell by system energy from grand gulf                                     36.00%        
Average monthly payments under unit power sales agreement                                     $ 19,500,000        
Purchased Percentage Of Capacity And Energy Based On Agreement                                     17.10%        
Amortization period of cost                                     27 years        
Incremental NRC Inspection Costs                                         53,000,000    
NRC inspection and performance improvement costs                                       44,000,000      
Increase (Decrease) in Regulatory Liabilities                                     $ 1,043,507,000 $ 62,994,000 $ (11,123,000)    
Entergy Arkansas [Member] | ANO [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount                     $ 31,000,000                        
Damages awarded for previously capitalized costs               $ 6,000,000                              
Damages awarded for previously recorded operation and maintenance               5,000,000                              
Damages awarded for previously recorded nuclear fuel expense               19,000,000                              
Damages awarded for previously recorded taxes other than income taxes               1,000,000                              
Entergy Wholesale Commodities [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
NRC inspection costs                                     50,000,000        
Entergy Wholesale Commodities [Member] | Indian Point and Fitzpatrick [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount                             $ 81,000,000                
Entergy Wholesale Commodities [Member] | Indian Point 3 [Member]                                              
Commitments And Contingencies [Line Items]                                              
Damages awarded for previously capitalized costs   $ 45,000,000                                          
Damages awarded for previously recorded operation and maintenance   2,000,000                                          
Reduction of previously recorded deprecation expense   8,000,000                                          
Plant balance reduction   37,000,000                                          
Entergy Wholesale Commodities [Member] | FitzPatrick [Member]                                              
Commitments And Contingencies [Line Items]                                              
Damages awarded for previously capitalized costs   32,000,000                                          
Damages awarded for previously recorded operation and maintenance   2,000,000                                          
Reduction of previously recorded deprecation expense   1,000,000                                          
Plant balance reduction   10,000,000                                          
Carrying Value of Nuclear Plant   $ 0                   $ 0                      
Entergy Wholesale Commodities [Member] | Palisades [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount                 $ 14,000,000             $ 21,000,000              
Damages awarded for previously capitalized costs           11,000,000                                  
Damages awarded for previously recorded operation and maintenance           3,000,000                                  
Reduction of previously recorded deprecation expense           1,000,000                                  
Plant balance reduction           10,000,000                                  
Entergy Wholesale Commodities [Member] | Indian Point 2 [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount               $ 34,000,000                              
Damages awarded for previously capitalized costs           14,000,000                                  
Damages awarded for previously recorded operation and maintenance           15,000,000                                  
Damages awarded for previously recorded decommissioning expense           3,000,000                                  
Damages awarded for previously recorded taxes other than income taxes           2,000,000                                  
Reduction of previously recorded deprecation expense           3,000,000                                  
Plant balance reduction           $ 11,000,000                                  
Entergy Wholesale Commodities [Member] | Vermont Yankee [Member]                                              
Commitments And Contingencies [Line Items]                                              
Litigation Settlement, Amount                         $ 19,000,000                    
Damages awarded for previously capitalized costs                       15,000,000                      
Damages awarded for previously recorded operation and maintenance                       4,000,000                      
Reduction of previously recorded deprecation expense                       2,000,000                      
Reduction to operation and maintenance expense                       $ 13,000,000                      
Entergy Wholesale Commodities [Member] | Minimum [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Expected NRC inspection costs     $ 45,000,000                               45,000,000        
Entergy Wholesale Commodities [Member] | Maximum [Member] | Pilgrim [Member]                                              
Commitments And Contingencies [Line Items]                                              
Expected NRC inspection costs     60,000,000                               $ 60,000,000        
Vidalia Purchased Power Agreement [Member]                                              
Commitments And Contingencies [Line Items]                                              
Increase (Decrease) in Regulatory Liabilities     $ (30,500,000)